AIA® Document A141™ – 2014 Exhibit A Design-Build Amendment
Exhibit 10.31.3
AIA® Document A141™ – 2014 Exhibit A Design-Build Amendment
This Amendment is incorporated into the accompanying AIA Document A141™–2014, Standard Form of Agreement Between Owner and Design-Builder dated the 29th of December 2017 (the “Agreement”). The effective date of this Exhibit A Amendment (“Third Amendment”) is the 23rd day of January in the year 2019.
(In words, indicate day, month and year.)
for the following PROJECT:
(Name and location or address)
Athenex Dunkirk Plant Project, for Athenex, Inc. Manufacturing Facility located in
Dunkirk, NY
THE OWNER:
(Name, legal status and address)
Athenex, Inc. ("Athenex")
Conventus Building
0000 Xxxx Xxxxxx, Xxxxx 000
Buffalo, New York 14203
THE DESIGN-BUILDER:
(Name, legal status and address)
Exyte U.S., Inc. ("Exyte” f/k/a M+W U.S. Inc.)
0000 Xxxxx Xxxx, Xxxxx 000
Plano, Texas 75074
Design-Builder’s Architect (“Architect” or “Subconsultant”) is:
Genesis Architects
000 Xxxxxxxx Xxxx
Plymouth Meeting, PA 19462
RECITALS
WHEREAS, Owner and Design-Builder entered into that certain Agreement on or about December 29, 2017;
WHEREAS, Owner and Design-Builder entered into the First Amendment to the Agreement, dated effective March 27, 2018 (“First Amendment”);
WHEREAS, Owner and Design-Builder entered into the Second Amendment to the Agreement (“Second Amendment”), dated effective October 1, 2018;
WHEREAS, Owner and Design-Builder desire to amend the Agreement by entering into this Exhibit A (as referenced in the Agreement) Third Amendment to the Agreement.
NOW THEREFORE, for good and valuable consideration, the receipt and sufficiency of which are hereby acknowledged, the Owner and Design-Builder hereby amend the Agreement as follows.
A.1 CONTRACT SUM
A.2 CONTRACT TIME
A.3 INFORMATION UPON WHICH THIRD AMENDMENT IS BASED
A.4 DESIGN-BUILDER’S PERSONNEL, CONTRACTORS AND SUPPLIERS
A.5 COST OF THE WORK
ARTICLE A.1 CONTRACT SUM
§ A.1.1 The Owner shall pay the Design-Builder the Contract Sum in current funds for the Design-Builder’s performance of the Contract after the execution of this Third Amendment.
(Check the appropriate box.)
[ ] Stipulated Sum, in accordance with Section A.1.2 below
[ ] Cost of the Work plus the Design-Builder’s Fee, in accordance with Section A.1.3 below
[ XX ] Cost of the Work plus the Design-Builder’s Fee with a Guaranteed Maximum Price, in accordance with Section A.1.4 below
(Based on the selection above, complete Section A.1.2, A.1.3 or A.1.4 below.)
§ A.1.2 Not used.
§ A.1.3 Not used.
§ A.1.4 Cost of the Work Plus Design-Builder’s Fee With a Guaranteed Maximum Price
§ A.1.4.1 The Cost of the Work is as defined in Article A.5, Cost of the Work.
§ A.1.4.2 The Design-Builder’s Fee: 2.5% of Cost of Work
(State a lump sum, percentage of Cost of the Work or other provision for determining the Design-Builder’s Fee and the method for adjustment to the Fee for changes in the Work.)
The Design-Builder’s Fee shall be 2.5% of the Cost of Work.
§ A.1.4.3 Guaranteed Maximum Price
§ A.1.4.3.1The sum of the Cost of the Work, the Design-Builder’s Fee, and Xxxx’x Fee (defined below) is guaranteed by the Design-Builder not to exceed Two hundred twelve million, five hundred ninety four thousand, eight hundred six dollars ($ 212,594,806 ), subject to additions and deductions for changes in the Work as provided in the Design-Build Documents. Costs that would cause the Guaranteed Maximum Price (“GMP”) to be exceeded shall be paid by the Design-Builder without reimbursement by the Owner.
(Insert specific provisions if the Design-Builder is to participate in any savings.)
Design-Builder is entitled to shared savings based on the final Contract cost including Fee (“Final Cost”), being delivered under $212,594,806. If the Final Cost of the Project is less than $ 212,594,806, then Design-Builder shall be entitled to the first $150,000 (one-hundred and fifty thousand dollars) of the total savings. Thereafter, Design-Builder shall be compensated in a shared savings value, which shall equal Forty Percent (40%) of the difference between the Final Cost and $ 212,444,806 (GMP - $150,000 = $212,444,806).
§ A.1.4.3.2 Itemized Statement of the Guaranteed Maximum Price
Provided below is an itemized statement of the Guaranteed Maximum Price organized by trade categories, allowances, contingencies, alternates, the Design-Builder’s Fee, and other items that comprise the Guaranteed Maximum Price.
2
(Provide information below or reference an attachment.)
See Exyte Cost Breakdown of Guaranteed Maximum Price, including Design-Builder's fee, attached hereto as EXHIBIT 1.
The Guaranteed Maximum Price is based on the total dollar value of the Project and shall not be considered a line-item GMP. For the avoidance of doubt, Design-Builder is striving to ensure that that Project’s overall Final Cost is delivered at or under the GMP amount; however, Design-Builder is not guaranteeing to meet any particular line-item amount. As such, Design-Builder shall have the authority to reallocate funds within the GMP value as necessary, without increasing the GMP budget.
§ A.1.4.3.3 The Guaranteed Maximum Price is based on the following alternates, if any, which are described in the Design-Build Documents and are hereby accepted by the Owner:
(State the numbers or other identification of accepted alternates. If the Owner is permitted to accept other alternates subsequent to the execution of this Third Amendment, attach a schedule of such other alternates showing the change in the Cost of the Work and Guaranteed Maximum Price for each and the deadline by which the alternate must be accepted.)
|
1) |
GMP includes equipment purchases for Boilers, Chillers and Cooling Towers as outlined in signed Recommendation to Award, (RTA), executed prior to execution of this Agreement. |
|
2) |
Additional requests by Athenex to reduce scope and defer various areas/equipment are incorporated into this price; however, contract documents (drawings and specifications) have not been updated to reflect the reduced scope. Drawings 1-A-214_RJ_Notes_25OCT18 and 1-A-224_RI_Notes_22OCT18 as outlined on the Drawings list (Exhibit 3) clearly identify the scope reduction areas. GMP pricing sheets as shown in Exhibit 1 (dated March 1, 2019) hereto outline the process equipment and other items removed from the GMP and associated scopes of work (including but not limited to other disciplines such as mechanical, electrical, architectural, and controls). For the avoidance of doubt, the following packages have been removed from the GMP and associated scopes of work: |
Bid Package Number |
Bid Package Description |
PQ008 |
Formulation Tanks and Platforms |
PQ009 |
TCU |
PQ011 |
Transfer and Utility Panels |
PQ013 |
Syringe Assembly and labeling |
PQ017 |
Downflow Booths |
PQ018 |
Mixproof Valve Manifold |
|
3) |
GMP price includes costs for winter conditions, temporary in-fills, temporary power and temporary heat as previously agreed and currently being executed to maintain the project schedule. Owner agrees that these costs are included within the GMP and shall be reimbursed. |
§ A.1.4.3.4 Unit Prices, if any:
(Identify item, state the unit price, and state any applicable quantity limitations.)
Item |
Units and Limitations |
Price per Unit ($0.00) |
NOT APPLICABLE |
|
|
§ A.1.4.3.5 Assumptions, if any, on which the Guaranteed Maximum Price is based:
GMP is based on Phase 1 area only, including equipment lists and User Requirements Specification Number 5, dated February 20, 2018.
3
User Requirements Specification Number 6, dated October 19, 2018 and issued November 2, 2018, lists deferred areas and scope reductions captured via the subcontractor bidding efforts. For the avoidance of doubt, the terms and the scope in User Requirements Specification Number 6 is not included in this Third Amendment, the Agreement, and/or all related exhibits and amendments thereto, and the items outlined in the User Requirements Specifications that are not included in the drawings are not considered required scope for this Project. The Parties further understand and agree that the Contract Drawings and Specifications listed in Exhibits 2 & 3 represent the agreed-upon scope of work, and therefore, supersede and override the terms of User Requirements Specifications.
The Parties hereto understand and agree that if deferred scope is added back into the Project, then a Change Order, increasing the GMP cost and Contract Time , shall be issued to address all additional scope changes, in accordance with § 6.2 and 8.2 of the Agreement.
§ A.1.5 Payments
§ A.1.5.1 Progress Payments
§ A.1.5.1.1Based upon Applications for Payment submitted to the Owner by the Design-Builder, the Owner shall make progress payments on account of the Contract Sum to the Design-Builder as provided below and elsewhere in the Design-Build Documents.
§ A.1.5.1.2The period covered by each Application for Payment shall be one calendar month ending on the last day of the month, or as follows:
§ A.1.5.1.3Provided that an Application for Payment is received not later than the 30TH day of the month, the Owner shall make payment of the certified and undisputed amount to the Design-Builder not later than the 30TH day of the subsequent month. Timely payment is a material term to this Agreement. Exyte also recognizes that Project funding is being provided to Athenex by the State of New York. Amounts remaining unpaid sixty (60) days after certified and undisputed invoiced amounts are received by Athenex from Exyte shall bear interest at the rate of 1.5% per month on the unpaid balance. Exyte acknowledges that approval of the New York State Empire State Development Corporation is required under this Contract prior to payment. Said approval shall not be unreasonably withheld. Exyte further acknowledges its responsibility to provide appropriate documentation required by the New York State Empire Development Corporation, including, but not limited to, all required payment application forms and MWBE information/certifications.
(Federal, state or local laws may require payment within a certain period of time.)
§ A.1.5.1.4With each Application for Payment where the Contract Sum is based upon the Cost of the Work, or the Cost of the Work with a Guaranteed Maximum Price, the Design-Builder shall submit payrolls, xxxxx cash accounts, receipted invoices or invoices with check vouchers attached, and any other evidence required by the Owner to demonstrate that cash disbursements already made by the Design-Builder on account of the Cost of the Work equal or exceed (1) progress payments already received by the Design-Builder, less (2) that portion of those payments attributable to the Design-Builder’s Fee; plus (3) payrolls for the period covered by the present Application for Payment.
§ A.1.5.1.5With each Application for Payment where the Contract Sum is based upon a Stipulated Sum or Cost of the Work with a Guaranteed Maximum Price, the Design-Builder shall submit the most recent schedule of values in accordance with the Design-Build Documents. The schedule of values shall allocate the entire Contract Sum among the various portions of the Work. Compensation for design services, if any, shall be shown separately. Where the Contract Sum is based on the Cost of the Work with a Guaranteed Maximum Price, the Design-Builder’s Fee shall be shown separately. The schedule of values shall be prepared in such form and supported by such data to substantiate its accuracy as the Owner may require. This schedule of values, unless objected to by the Owner, shall be used as a basis for reviewing the Design-Builder’s Applications for Payment.
§ A.1.5.1.6In taking action on the Design-Builder’s Applications for Payment, the Owner shall be entitled to rely on the accuracy and completeness of the information furnished by the Design-Builder and shall not be deemed to have made a detailed examination, audit or arithmetic verification of the documentation submitted in accordance with Sections A.1.5.1.4 or A.1.5.1.5, or other supporting data; to have made exhaustive or continuous on-site inspections; or to have made examinations to ascertain how or for what purposes the Design-Builder has used amounts previously paid. Such examinations, audits and verifications, if required by the Owner, will be performed by the Owner’s auditors acting in the sole interest of the Owner.
4
§ A.1.5.1.7 Except with the Owner’s prior approval, the Design-Builder shall not make advance payments to suppliers for materials or equipment which have not been delivered and stored at the site.
§ A.1.5.2 Not used.
§ A.1.5.3 Not used.
§ A.1.5.4 Progress Payments—Cost of the Work Plus a Fee with a Guaranteed Maximum Price
§ A.1.5.4.1 Applications for Payment where the Contract Sum is based upon the Cost of the Work Plus a Fee with a Guaranteed Maximum Price shall show the percentage of completion of each portion of the Work as of the end of the period covered by the Application for Payment. The percentage of completion shall be the lesser of (1) the percentage of that portion of the Work which has actually been completed; or (2) the percentage obtained by dividing (a) the expense that has actually been incurred by the Design-Builder on account of that portion of the Work for which the Design-Builder has made or intends to make actual payment prior to the next Application for Payment by (b) the share of the Guaranteed Maximum Price allocated to that portion of the Work in the schedule of values.
§ A.1.5.4.2Subject to other provisions of the Design-Build Documents, the amount of each progress payment shall be computed as follows:
.1 Take that portion of the Guaranteed Maximum Price properly allocable to completed Work as determined by multiplying the percentage of completion of each portion of the Work by the share of the Guaranteed Maximum Price allocated to that portion of the Work in the schedule of values. Pending final determination of cost to the Owner of changes in the Work, amounts not in dispute shall be included as provided in Section 6.3.9 of the Agreement.
.2 Add that portion of the Guaranteed Maximum Price properly allocable to materials and equipment delivered and suitably stored at the site for subsequent incorporation in the Work, or if approved in advance by the Owner, suitably stored off the site at a location agreed upon in writing;
.3 Add the Design-Builder’s Fee, less retainage of ten percent ( 10 %). The Design-Builder’s Fee shall be computed upon the Cost of the Work at the rate stated in Section A.1.4.2 or, if the Design-Builder’s Fee is stated as a fixed sum in that Section, shall be an amount that bears the same ratio to that fixed-sum fee as the Cost of the Work bears to a reasonable estimate of the probable Cost of the Work upon its completion;
.4 Unless noted otherwise in the individual subcontract(s) or purchase order(s), the subtract retainage of ten percent ( 10 %) from that portion of the Work that the Design-Builder self-performs;
.5 Subtract the aggregate of previous payments made by the Owner;
.6 Subtract the shortfall, if any, indicated by the Design-Builder in the documentation required by Section A.1.5.1.4 to substantiate prior Applications for Payment, or resulting from errors subsequently discovered by the Owner’s auditors in such documentation; and
.7 Subtract amounts, if any, for which the Owner has withheld or nullified a payment as provided in Section 9.5 of the Agreement.
§ A.1.5.4.3 The Owner and Design-Builder shall agree upon (1) a mutually acceptable procedure for review and approval of payments to the Architect, Consultants, and Contractors and (2) the percentage of retainage held on agreements with the Architect, Consultants, and Contractors; and the Design-Builder shall execute agreements in accordance with those terms.
§ A.1.5.4.4 The Owner agrees that Design-Builder’s subcontractor, The Pike Company (“Pike”) is entitled to a fee (“Pike’s Fee”) based on Xxxx’x management of the Civil/Structural and Architectural scopes of Work (“Xxxx’x Scope”). Xxxx’x fee is a Not to Exceed amount of $1,350,000 M USD (one million three-hundred and fifty thousand dollars), and is itemized in the GMP breakdown sheet in Exhibit 1, dated March 1, 2019. The Parties agree that Xxxx’x Fee as stated herein is separate and in addition to the consultant management fee in an amount not to exceed $3,061,360 as referenced in § 4.1 of Design Builder’s subcontract with Xxxx dated December 12, 2018. The Parties hereto further understand and agree that Xxxx’x Fee is separate and independent from Design-Builder’s Fee. Design-Builder shall compensate Pike for Pike’s Fee, provided however, that Owner shall pay Design-Builder for the full amount of Xxxx’x Fee, and such amount paid by the Owner shall equal the amount that Design-Builder pays for Xxxx’x Scope of services.
5
§ A.1.5.5 Final Payment
§ A.1.5.5.1 Final payment, constituting the entire unpaid balance of the Contract Sum, shall be made by the Owner to the Design-Builder not later than 30 days after the Design-Builder has fully performed the Contract and the requirements of Section 9.10 of the Agreement have been satisfied, except for the Design-Builder’s responsibility to correct non-conforming Work discovered after final payment or to satisfy other requirements, if any, which extend beyond final payment.
§ A.1.5.5.2 If the Contract Sum is based on the Cost of the Work, the Owner’s auditors will review and report in writing on the Design-Builder’s final accounting within 30 days after the Design-Builder delivers the final accounting to the Owner. Based upon the Cost of the Work the Owner’s auditors report to be substantiated by the Design-Builder’s final accounting, and provided the other conditions of Section 9.10 of the Agreement have been met, the Owner will, within seven days after receipt of the written report of the Owner’s auditors, either issue a final Certificate for Payment, or notify the Design-Builder in writing of the reasons for withholding a certificate as provided in Section 9.5.1 of the Agreement.
ARTICLE A.2 CONTRACT TIME
§ A.2.1 Contract Time, as defined in the Agreement at Section 1.4.13, is the period of time, including authorized adjustments, for Substantial Completion of the Work.
§ A.2.2 The Design-Builder shall achieve Substantial Completion of the Work not later than: January 31, 2020.
(Insert number of calendar days. Alternatively, a calendar date may be used when coordinated with the date of commencement. If appropriate, insert requirements for earlier Substantial Completion of certain portions of the Work.)
Portion of Work |
Substantial Completion Date |
Substantial Completion |
January 31, 2020 |
, subject to adjustments of the Contract Time as provided in the Design-Build Documents. The Parties acknowledge and agree that all references to the Substantial Completion Date in the Contract, the First Amendment, the Second Amendment, and/or all Contract exhibits, attachments, or related documents shall be removed, replaced, and updated with the Substantial Completion Date stated herein.
(Insert provisions, if any, for liquidated damages relating to failure to achieve Substantial Completion on time or for bonus payments for early completion of the Work.)
Parties have agreed to Liquidated Damages as defined in Section 14.1.7 in the A141-2017 Agreement Between Owner and Design Builder with the Effective Date of December 29, 2017 and as superseded by the First Amendment, with a First Amendment with an Effective Date of March 27, 2018.
The Liquidated Damages, as agreed by the First Amendment, start February 1, 2020.
ARTICLE A.3 INFORMATION UPON WHICH THIRD AMENDMENT IS BASED
§ A.3.1 The Contract Sum and Contract Time set forth in this Third Amendment are based on the following:
See Attachment 1 for summary of the Contract Sum; See Attachment 2 for summary of the Contract Time.
§ A.3.1.1 The Supplementary and other Conditions of the Contract:
Document |
Title |
Date |
Pages |
First Amendment – 27 MAR 18 Second Amendment - Executed 5 OCT 18 |
|
|
|
6
§ A.3.1.2 The Specifications:
(Either list the specifications here or refer to an exhibit attached to this Third Amendment.)
See Exhibit 2
Section |
Title |
Date |
Pages |
|
|
|
|
§ A.3.1.3 The Drawings:
(Either list the drawings here or refer to an exhibit attached to this Third Amendment.)
See Exhibit 3
Number |
Title |
Date |
|
|
|
§ A.3.1.4The Sustainability Plan, if any: - NOT USED.
(If the Owner identified a Sustainable Objective in the Owner’s Criteria, identify the document or documents that comprise the Sustainability Plan by title, date and number of pages, and include other identifying information. The Sustainability Plan identifies and describes the Sustainable Objective; the targeted Sustainable Measures; implementation strategies selected to achieve the Sustainable Measures; the Owner’s and Design-Builder’s roles and responsibilities associated with achieving the Sustainable Measures; the specific details about design reviews, testing or metrics to verify achievement of each Sustainable Measure; and the Sustainability Documentation required for the Project, as those terms are defined in Exhibit C to the Agreement.)
Title |
Date |
Pages |
None |
|
|
Other identifying information
None
§ A.3.1.5 Allowances and Contingencies:
(Identify any agreed upon allowances and contingencies, including a statement of their basis.)
.1 Allowances
Allowances, also identified as “Yet to Buy” costs, for various Scopes of Work are shown by work package or division. See Exhibit 1 (dated March 1, 2019).
.2 Contingencies
Contingency is identified in Exhibit 1 (dated March 1, 2019)and is intended to be used by Design-Build Contractor as required to support project execution.
§ A.3.1.6 Design-Builder’s assumptions and clarifications:
Client will be responsible for Commissioning of all building systems for both validated and non-validated systems. Commission, Qualification and Validation (CQV) requirements for all validated systems have not been provided to the design-build contractor and efforts to support those requirements are not included in this GMP . Client agrees that assembly, execution and acceptance of all documentation and turn-over packages required to support commissioning efforts are within their scope. Design-Build contractor will provide labor, via subcontractors, to support execution of the clients commissioning efforts for non-validated systems.
7
§ A.3.1.7 Deviations from the Owner’s Criteria as adjusted by a Modification:
There are no known deviations from the Owner’s Criteria at this time, however several late changes have been excluded (see Exhibit 3, referred to as “Deferred Scope Drawings”) or identified to be covered under contingency (see Exhibit 1, dated March 1, 2019). Drawings and Specifications have been generated and reviewed with the Owner and all Owner questions or concerns have been addressed and are accepted by all parties. Drawing list and pricing back-up identify deferred scope and applicable price reductions. Credit for areas and equipment removed from the scope are incorporated into this GMP.
§ A.3.1.8 To the extent the Design-Builder shall be required to submit any additional Submittals to the Owner for review, indicate any such submissions below:
Not Applicable
ARTICLE A.4 DESIGN-BUILDER’S PERSONNEL, CONTRACTORS AND SUPPLIERS
§ A.4.1 The Design-Builder’s key personnel are identified below:
(Identify name, title and contact information.)
.1 Superintendent
Xxxxx Xxxxxx
.2 Project Manager
Xxxx Xxxxx
.3 Others
Xxx Xxxx – Project Director
§ A.4.2 The Design-Builder shall retain the following Consultants, Contractors and suppliers, identified below:
(List name, discipline, address and other information.)
Design-Builder’s Architect (“Architect”) is:
Genesis Architects
000 Xxxxxxxx Xxxx
Plymouth Meeting, PA 19462
Xxxx Xxxxx/Xxxxx Xxxxx Engineering and Surveying P.C.
000 Xxxxxx Xxxx
Xxxxxxx Park, NY 12065
Xxxxx Xxxxxxxxx Xxx
000 Xx. Xxxx Xxxxxx, Xxxxx 000
Rochester, NY 14604
The Pike Company, Inc.
Xxx Xxxxxx Xxxxxx
Rochester, NY 14607
ARTICLE A.5 COST OF THE WORK
§ A.5.1 Cost To Be Reimbursed as Part of the Contract
§ A.5.1.1 Labor Costs
§ A.5.1.1.1 Wages of construction workers directly employed by the Design-Builder to perform the construction of the Work at the site or, with the Owner's prior approval, at off-site offices or workshops.
8
§ A.5.1.1.2 With the Owner’s prior approval, wages or salaries of the Design-Builder's supervisory and administrative personnel when stationed at the site.
(If it is intended that the wages or salaries of certain personnel stationed at the Design-Builder's principal or other offices shall be included in the Cost of the Work, identify below the personnel to be included, whether for all or only part of their time, and the rates at which their time will be charged to the Work.)
Person Included |
Status (full-time/part-time) |
Rate ($0.00) |
Rate (unit of time) |
See Table – Exhibit 4, dated March 1, 2019 |
|
|
|
§ A.5.1.1.3 Wages and salaries of the Design-Builder's supervisory or administrative personnel engaged at factories, workshops or on the road, in expediting the production or transportation of materials or equipment required for the Work, but only for that portion of their time required for the Work. Annual rate increases for staffing will be provided in the 2nd Quarter of each year and incorporated into the billable rates previously provided. Any rate increases shall not increase the project GMP Cost.
§ A.5.1.1.4 Costs paid or incurred by the Design-Builder for taxes, insurance, contributions, assessments and benefits required by law or collective bargaining agreements and, for personnel not covered by such agreements, customary benefits such as sick leave, medical and health benefits, holidays, vacations and pensions, provided such costs are based on wages and salaries included in the Cost of the Work under Section A.5.1.1.
§ A.5.1.1.5 Not used.
§ A.5.1.2 Contract Costs. Payments made by the Design-Builder to the Architect, Consultants, Contractors and suppliers in accordance with the requirements of their subcontracts.
§ A.5.1.3 Costs of Materials and Equipment Incorporated in the Completed Construction
§ A.5.1.3.1 Costs, including transportation and storage, of materials and equipment incorporated or to be incorporated in the completed construction.
§ A.5.1.3.2 Costs of materials described in the preceding Section A.5.1.3.1 in excess of those actually installed to allow for reasonable waste and spoilage. Unused excess materials, if any, shall become the Owner's property at the completion of the Work or, at the Owner's option, shall be sold by the Design-Builder. Any amounts realized from such sales shall be credited to the Owner as a deduction from the Cost of the Work.
§ A.5.1.4 Costs of Other Materials and Equipment, Temporary Facilities and Related Items
§ A.5.1.4.1 Costs of transportation, storage, installation, maintenance, dismantling and removal of materials, supplies, temporary facilities, machinery, equipment and hand tools not customarily owned by construction workers that are provided by the Design-Builder at the site and fully consumed in the performance of the Work. Costs of materials, supplies, temporary facilities, machinery, equipment and tools that are not fully consumed shall be based on the cost or value of the item at the time it is first used on the Project site less the value of the item when it is no longer used at the Project site. Costs for items not fully consumed by the Design-Builder shall mean fair market value.
§ A.5.1.4.2 Rental charges for temporary facilities, machinery, equipment and hand tools not customarily owned by construction workers that are provided by the Design-Builder at the site and costs of transportation, installation, minor repairs, dismantling and removal. The total rental cost of any Design-Builder-owned item may not exceed the purchase price of any comparable item. Rates of Design-Builder-owned equipment and quantities of equipment shall be subject to the Owner's prior approval.
§ A.5.1.4.3 Costs of removal of debris from the site of the Work and its proper and legal disposal.
§ A.5.1.4.4 Costs of document reproductions, electronic communications, postage and parcel delivery charges, dedicated data and communications services, teleconferences, Project websites, extranets and reasonable xxxxx cash expenses of the site office.
§ A.5.1.4.5 Costs of materials and equipment suitably stored off the site at a mutually acceptable location, with the Owner's prior approval.
9
§ A.5.1.5 Miscellaneous Costs
§ A.5.1.5.1 Premiums for that portion of insurance and bonds required by the Design-Build Documents that can be directly attributed to the Contract. With the Owner's prior approval self-insurance for either full or partial amounts of the coverages required by the Design-Build Documents.
§ A.5.1.5.2 Sales, use or similar taxes imposed by a governmental authority that are related to the Work and for which the Design-Builder is liable.
§ A.5.1.5.3 Fees and assessments for the building permit and for other permits, licenses and inspections for which the Design-Builder is required by the Design-Build Documents to pay.
§ A.5.1.5.4 Fees of laboratories for tests required by the Design-Build Documents, except those related to defective or nonconforming Work for which reimbursement is excluded by Section 15.5.3 of the Agreement or by other provisions of the Design-Build Documents, and which do not fall within the scope of Section A.5.1.6.3.
§ A.5.1.5.5 Royalties and license fees paid for the use of a particular design, process or product required by the Design-Build Documents; the cost of defending suits or claims for infringement of patent rights arising from such requirement of the Design-Build Documents; and payments made in accordance with legal judgments against the Design-Builder resulting from such suits or claims and payments of settlements made with the Owner's consent. However, such costs of legal defenses, judgments and settlements shall not be included in the calculation of the Design-Builder's Fee or subject to the Guaranteed Maximum Price. If such royalties, fees and costs are excluded by the second to last sentence of Section 3.1.13.2 of the Agreement or other provisions of the Design-Build Documents, then they shall not be included in the Cost of the Work.
§ A.5.1.5.6 With the Owner's prior approval, costs for electronic equipment and software directly related to the Work
§ A.5.1.5.7.Deposits lost for causes other than the Design-Builder's negligence or failure to fulfill a specific responsibility in the Design-Build Documents.
§ A.5.1.5.8 With the Owner's prior approval, which shall not be unreasonably withheld, legal, mediation and arbitration costs, including attorneys' fees, other than those arising from disputes between the Owner and Design-Builder, reasonably incurred by the Design-Builder after the execution of the Agreement and in the performance of the Work.
§ A.5.1.5.9 With the Owner’s prior approval, expenses incurred in accordance with the Design-Builder's standard written personnel policy for relocation, and temporary living allowances of, the Design-Builder's personnel required for the Work.
§ A.5.1.5.10 That portion of the reasonable expenses of the Design-Builder's supervisory or administrative personnel incurred while traveling in discharge of duties connected with the Work.
§ A.5.1.6 Other Costs and Emergencies
§ A.5.1.6.1 Other costs incurred in the performance of the Work if, and to the extent, approved in advance in writing by the Owner.
§ A.5.1.6.2 Costs incurred in taking action to prevent threatened damage, injury or loss in case of an emergency affecting the safety of persons and property.
§ A.5.1.6.3 Costs of repairing or correcting damaged or nonconforming Work executed by the Design-Builder, Contractors or suppliers, provided that such damaged or nonconforming Work was not caused by negligence or failure to fulfill a specific responsibility of the Design-Builder and only to the extent that the cost of repair or correction is not recovered by the Design-Builder from insurance, sureties, Contractors, suppliers, or others.
§ A.5.1.7 Related Party Transactions
§ A.5.1.7.1 For purposes of Section A.5.1.7, the term “related party” shall mean a parent, subsidiary, affiliate or other entity having common ownership or management with the Design-Builder; any entity in which any stockholder in, or management employee of, the Design-Builder owns any interest in excess of ten percent in the aggregate; or any person or entity which has the right to control the business or affairs of the Design-Builder. The term “related party” includes any member of the immediate family of any person identified above.
10
§ A.5.1.7.2 If any of the costs to be reimbursed arise from a transaction between the Design-Builder and a related party, the Design-Builder shall notify the Owner of the specific nature of the contemplated transaction, including the identity of the related party and the anticipated cost to be incurred, before any such transaction is consummated or cost incurred. If the Owner, after such notification, authorizes the proposed transaction, then the cost incurred shall be included as a cost to be reimbursed, and the Design-Builder shall procure the Work, equipment, goods or service from the related party, as a Contractor, according to the terms of Section A.5.4. If the Owner fails to authorize the transaction, the Design-Builder shall procure the Work, equipment, goods or service from some person or entity other than a related party according to the terms of Section A.5.4.
§ A.5.2 Costs Not to Be Reimbursed as Part of this Contract
The Cost of the Work shall not include the items listed below:
.1 Salaries and other compensation of the Design-Builder's personnel stationed at the Design-Builder's principal office or offices other than the site office, except as specifically provided in Section A.5.1.1;
.2 Expenses of the Design-Builder's principal office and offices other than the site office;
.3 Overhead and general expenses, except as may be expressly included in Section A.5.1;
.4 The Design-Builder's capital expenses, including interest on the Design-Builder's capital employed for the Work;
.5 Except as provided in Section A.5.1.6.3 of this Agreement, costs due to the negligence or failure of the Design-Builder, Contractors and suppliers or anyone directly or indirectly employed by any of them or for whose acts any of them may be liable to fulfill a specific responsibility of the Contract;
.6 Any cost not specifically and expressly described in Section A.5.1; and
.7 Costs, other than costs included in Change Orders approved by the Owner, that would cause the Guaranteed Maximum Price to be exceeded.
§ A.5.3 Discounts, Rebates, and Refunds
§ A.5.3.1Cash discounts obtained on payments made by the Design-Builder shall accrue to the Owner if (1) before making the payment, the Design-Builder included them in an Application for Payment and received payment from the Owner, or (2) the Owner has deposited funds with the Design-Builder with which to make payments; otherwise, cash discounts shall accrue to the Design-Builder. Trade discounts, rebates, refunds and amounts received from sales of surplus materials and equipment shall accrue to the Owner, and the Design-Builder shall make provisions so that they can be obtained.
§ A.5.3.2 Amounts that accrue to the Owner in accordance with Section A.5.3.1 shall be credited to the Owner as a deduction from the Cost of the Work.
§ A.5.4 Other Agreements
§ A.5.4.1 When the Design-Builder has provided a Guaranteed Maximum Price, and a specific bidder (1) is recommended to the Owner by the Design-Builder; (2) is qualified to perform that portion of the Work; and (3) has submitted a bid that conforms to the requirements of the Design-Build Documents without reservations or exceptions, but the Owner requires that another bid be accepted, then the Design-Builder may require that a Change Order be issued to adjust the Guaranteed Maximum Price by the difference between the bid of the person or entity recommended to the Owner by the Design-Builder and the amount of the subcontract or other agreement actually signed with the person or entity designated by the Owner.
§ A.5.4.2 Agreements between the Design-Builder and Contractors shall conform to the applicable payment provisions of the Design-Build Documents, and shall not be awarded on the basis of cost plus a fee without the prior consent of the Owner. If an agreement between the Design Builder and a Contractor is awarded on a cost plus a fee basis, the Design-Builder shall provide in the agreement for the Owner to receive the same audit rights with regard to the Cost of the Work performed by the Contractor as the Owner receives with regard to the Design-Builder in Section A.5.5, below.
§ A.5.4.3 The agreements between the Design-Builder and Architect and other Consultants identified in the Agreement shall be in writing. These agreements shall be promptly provided to the Owner upon the Owner’s written request.
§ A.5.5 Accounting Records
The Design-Builder shall keep full and detailed records and accounts related to the cost of the Work and exercise such controls as may be necessary for proper financial management under the Contract and to substantiate all costs incurred. The accounting and control systems shall be satisfactory to the Owner. The Owner and the Owner’s auditors shall, during
11
regular business hours and upon reasonable notice, be afforded access to, and shall be permitted to audit and copy, the Design-Builder’s records and accounts, including complete documentation supporting accounting entries, books, correspondence, instructions, drawings, receipts, subcontracts, Contractor’s proposals, purchase orders, vouchers, memoranda and other data relating to the Contract. The Design-Builder shall preserve these records for a period of three years after final payment, or for such longer period as may be required by law.
§ A.5.6 Relationship of the Parties
The Design-Builder accepts the relationship of trust and confidence established by this Agreement and covenants with the Owner to exercise the Design-Builder’s skill and judgment in furthering the interests of the Owner; to furnish efficient construction administration, management services and supervision; to furnish at all times an adequate supply of workers and materials; and to perform the Work in an expeditious and economical manner consistent with the Owner’s interests.
§ A.5.7 Additional Terms
§ A.5.7.1 The Parties acknowledge, understand, and agree that Design-Builder underwent a name-change on or about August 31, 2018, wherein Design-Builder changed its name from “M+W U.S., Inc.” (“M+W”) to “Exyte U.S., Inc.” (“Exyte”). As such, all references to “M+W” in the Agreement, the First Amendment, the Second Amendment, and all other related Contract documents, exhibits, and/or attachments shall be removed and replaced with “Exyte.”
§ A.5.7.2 Notwithstanding anything in the Agreement, the First Amendment, the Second Amendment, and all other related Contract documents, exhibits, and/or attachments to the contrary, Owner acknowledges and agrees that any and all warranties related to the pre-purchase of long lead equipment (hereinafter, “Long Lead Equipment Warranties”, which shall mean equipment purchased by Design-Builder and assigned to a subcontractor for installation. Examples include, but are not limited to: Chillers, Boilers, Cooling Towers, Electrical Switchgear, and process equipment as identified in the procurement matrix) may be subject to expiration prior to the warranty periods set forth in the Agreement. As such, the Parties acknowledge and agree that Design-Builder shall have no obligation, duty, or liability to correct defective Work following the expiration of the respective Long Lead Equipment Warranties, and Owner hereby releases Design-Builder from all damages, costs, or liabilities following the expiration of such Long Lead Equipment Warranties.
§ A.5.7.3 In addition to the limitation of liability outlined in § 3.1.14.3 of the Agreement, Owner acknowledges and agrees that Design-Builder’s liability shall be capped for all damages that arise out of or relate to Xxxxx Corporation’s (“Eaton”) and/or Mechanical Equipment Corporation, Inc.’s (“MECO”) acts or omissions, work, or respective subcontract. Notwithstanding anything in the Agreement, the First Amendment, the Second Amendment, and all other related Contract documents, exhibits, and/or attachments to the contrary:
A.5.7.3.1 In the event that Eaton causes or contributes to any liabilities, costs, and/or direct or indirect damages to Owner (consequential or otherwise), Design-Builder, and/or the Project (including, but not limited to, the performance or non-performance of Xxxxx’x equipment or work) (collectively, “Eaton-related Damages”), Owner agrees that Design-Builder’s liability in connection with the Eaton-related Damages shall not exceed the amount that Design-Builder actually recovers from Eaton for the Eaton-related Damages. For the avoidance of doubt, Owner agrees that Design-Builder will not be responsible for any Eaton-related Damages or costs that exceed the amount that Design-Builder actually recovers from Eaton.
A.5.7.3.2 In the event that MECO causes or contributes to any liabilities, costs, and/or direct or indirect damages to Owner (consequential or otherwise), Design-Builder, and/or the Project (including, but not limited to, the performance or non-performance of XXXX’s equipment or work) (collectively, “MECO-related Damages”), Owner agrees that Design-Builder’s liability in connection with the MECO-related Damages shall not exceed the amount that Design-Builder actually recovers from MECO for the MECO-related Damages. For the avoidance of doubt, Owner agrees that Design-Builder will not be responsible for any MECO-related Damages or costs that exceed the amount that Design-Builder actually recovers from MECO.
§ A.5.7.4 The Owner acknowledges and agrees that should Design-Builder submit its Applications for Payment in accordance with the terms of the Agreement and the forms included in Exhibit E to the Agreement, then Owner shall, diligently and without delay, proceed with issuing a Certification for Payment in accordance with the seven day timeframe referenced in § 9.4 (“Certificates for Payment”) of the Agreement. The Parties hereto understand and agree that all invoiced amounts ending in cents may be rounded to the nearest whole dollar amount, and as such, the Owner further acknowledges and agrees that the issuances of a Certification for Payment shall not be delayed, withheld, or rejected due to matters involving rounding discrepancies and/or mismatches.
12
This Third Amendment to the Agreement entered into as of the day and year first written above.
|
Exyte U.S., INC. |
|
/s/ Xxxxxxx Xxxxxx March 7, 2019 |
|
/s/ Xxxx Xxxxxxxxx March 7, 2019 |
OWNER (Signature) |
|
DESIGN-BUILDER(Signature) |
XXXX XXXXXX, Vice-President Operations |
|
XXXX XXXXXXXXX, CFO |
(Printed name and title) |
|
(Printed name and title) |
|
|
/s/ Xxxx Xxxxxxx March 8, 2019 |
|
|
DESIGN-BUILDER(Signature) |
|
|
XXXX XXXXXXX, President |
|
|
(Printed name and title) |
13
Athenex GMP Summary |
Exyte U.S. Inc. |
|
|
|
|
March 2018 BOD Estimate |
|
|
Current Commitments |
|
PCO Forecast |
|
Procurement Forecast |
|
Total |
|
|||
1 |
Division 01 |
General Requirements |
$ |
5,015,730 |
|
$ |
465,290 |
|
|
|
|
$ |
4,384,717 |
|
$ |
4,850,007 |
|
2 |
Division 02 |
Existing Conditions |
$ |
28,766 |
|
$ |
28,766 |
|
|
|
|
$ |
- |
|
$ |
28,766 |
|
3 |
Division 03 |
Concrete |
$ |
7,727,690 |
|
$ |
7,738,324 |
|
$ |
3,205,932 |
|
$ |
- |
|
$ |
10,944,257 |
|
4 |
Division 04 |
Masonry |
$ |
2,713,860 |
|
$ |
- |
|
$ |
- |
|
$ |
2,336,042 |
|
$ |
2,336,042 |
|
5 |
Division 05 |
Metals |
$ |
12,038,894 |
|
$ |
11,648,614 |
|
$ |
4,254,505 |
|
$ |
- |
|
$ |
15,903,119 |
|
6 |
Division 06 |
Wood, Plastic & Composites |
$ |
635,459 |
|
$ |
- |
|
$ |
- |
|
$ |
- |
|
$ |
- |
|
7 |
Division 07 |
Thermal & Moisture Protection |
$ |
7,879,221 |
|
$ |
5,340,124 |
|
$ |
1,684,451 |
|
$ |
- |
|
$ |
7,024,575 |
|
8 |
Division 08 |
Openings |
$ |
3,747,181 |
|
$ |
704,000 |
|
$ |
283,298 |
|
$ |
285,000 |
|
$ |
1,272,298 |
|
9 |
Division 09 |
Finishes |
$ |
8,440,596 |
|
$ |
- |
|
$ |
- |
|
$ |
11,234,602 |
|
$ |
11,234,602 |
|
10 |
Division 10 |
Specialties |
$ |
451,326 |
|
$ |
- |
|
$ |
- |
|
$ |
602,053 |
|
$ |
602,053 |
|
11 |
Division 11 |
Equipment |
$ |
2,528,360 |
|
$ |
12,760 |
|
$ |
- |
|
$ |
1,375,099 |
|
$ |
1,387,859 |
|
12 |
Division 12 |
Furnishings |
$ |
619,073 |
|
$ |
- |
|
$ |
- |
|
$ |
753,000 |
|
$ |
753,000 |
|
13 |
Division 13 |
Special Construction |
$ |
4,600,078 |
|
$ |
- |
|
$ |
- |
|
$ |
4,894,067 |
|
$ |
4,894,067 |
|
14 |
Division 14 |
Coveying Equipment |
$ |
470,316 |
|
$ |
- |
|
$ |
- |
|
$ |
406,400 |
|
$ |
406,400 |
|
21 |
Division 21 |
Fire Suppression |
$ |
2,157,401 |
|
$ |
- |
|
$ |
- |
|
$ |
2,064,600 |
|
$ |
2,064,600 |
|
22 |
Division 22 |
Plumbing |
$ |
10,826,130 |
|
$ |
2,981,686 |
|
$ |
306,851 |
|
$ |
2,838,839 |
|
$ |
6,127,376 |
|
23 |
Division 23 |
Heating, Ventilation & AC |
$ |
41,064,161 |
|
$ |
2,183,853 |
|
$ |
- |
|
$ |
22,996,572 |
|
$ |
25,180,425 |
|
25 |
Division 25 |
Integrated Automation |
$ |
5,869,253 |
|
$ |
- |
|
$ |
- |
|
$ |
9,129,149 |
|
$ |
9,129,149 |
|
26 |
Division 26 |
Electrical |
$ |
16,044,041 |
|
$ |
12,858,263 |
|
$ |
518,000 |
|
$ |
12,532,000 |
|
$ |
25,908,263 |
|
27 |
Division 27 |
Communications |
$ |
1,839,190 |
|
$ |
- |
|
$ |
- |
|
$ |
1,551,000 |
|
$ |
1,551,000 |
|
28 |
Division 28 |
Electronic Safety and Security |
$ |
1,431,839 |
|
$ |
- |
|
$ |
- |
|
$ |
336,758 |
|
$ |
336,758 |
|
31 |
Division 31 |
Earthwork |
$ |
7,060,929 |
|
$ |
5,813,140 |
|
$ |
454,025 |
|
$ |
- |
|
$ |
6,267,166 |
|
32 |
Division 32 |
Exterior Improvements |
$ |
2,446,666 |
|
$ |
1,787,020 |
|
$ |
60,000 |
|
$ |
- |
|
$ |
1,847,020 |
|
33 |
Division 33 |
Utilities |
$ |
9,497,824 |
|
$ |
4,761,082 |
|
$ |
15,000 |
|
$ |
659,950 |
|
$ |
5,436,032 |
|
34 |
Division 34 |
Transportation |
$ |
- |
|
$ |
- |
|
$ |
- |
|
$ |
- |
|
$ |
- |
|
35 |
Division 35 |
Waterway & Marine Const. |
$ |
- |
|
$ |
- |
|
$ |
- |
|
$ |
- |
|
$ |
- |
|
40 |
Division 40 |
Process Integration |
$ |
3,902,677 |
|
$ |
- |
|
$ |
- |
|
$ |
- |
|
$ |
- |
|
41 |
Division 41 |
Materials Processing & Handling Equipment |
$ |
18,251,360 |
|
$ |
- |
|
$ |
- |
|
$ |
14,552,248 |
|
$ |
14,552,248 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
$ |
- |
|
|
|
COW: |
$ |
177,288,021 |
|
$ |
56,322,922 |
|
$ |
10,782,063 |
|
$ |
92,932,096 |
|
$ |
160,037,081 |
|
|
|
Yet-to-buy |
|
|
|
|
|
|
|
|
|
|
|
|
$ |
4,804,470 |
|
|
|
Indirects |
$ |
29,541,453 |
|
|
|
|
|
|
|
|
|
|
$ |
34,565,930 |
|
|
|
Contingency |
$ |
31,777,847 |
|
|
|
|
|
|
|
|
|
|
$ |
13,187,324 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Totals |
$ |
238,607,321 |
|
|
|
|
|
|
|
|
|
|
$ |
212,594,806 |
|
Exhibit 1 - Page 1 of 14 March 1, 2019 |
CONFIDENTIAL |
. |
Athenex GMP Pending Procurement Summary |
Exyte U.S. Inc. |
Division |
Bid Package Number |
Bid Package Description |
|
|
FINAL BID Selected for GMP |
|
Estimated Amount "Yet to Buy" in Award Value |
Recommended Award Value |
|
|
Grand Total Contingency |
|
|
GMP Value |
|
Bidder Selected for Pricing |
||||
1 |
GRxx |
General Requirements |
|
|
$ |
3,844,717 |
|
|
$ |
3,844,717 |
|
|
$ |
- |
|
|
$ |
3,844,717 |
|
N/A - multiple |
1 |
S101 |
Security Services (GR's) |
|
|
|
|
|
|
$ |
- |
|
|
$ |
- |
|
|
$ |
- |
|
Summerville |
1 |
E102 |
Building Temporary Power |
|
|
$ |
540,000 |
|
|
$ |
540,000 |
|
|
$ |
- |
|
|
$ |
540,000 |
|
Xxxxxxxx |
1 |
BP52 |
Waste Management (Void - GR's) |
|
|
$ |
- |
|
|
$ |
- |
|
|
$ |
- |
|
|
$ |
- |
|
GR's |
1 |
BP54 |
Portable Toilets (Void - GR's) |
|
|
$ |
- |
|
|
$ |
- |
|
|
$ |
- |
|
|
$ |
- |
|
GR's |
1 |
BP56 |
Deck / Stairs Trailers (Void - GR's) |
|
|
$ |
- |
|
|
$ |
- |
|
|
$ |
- |
|
|
$ |
- |
|
GR's |
1 |
BP57 |
Maintain lawns, temp roads, snow plowing (Div 1) |
|
|
|
|
|
|
$ |
- |
|
|
$ |
- |
|
|
$ |
- |
|
|
3 |
BP44 |
Concrete Curbs and exterior slabs (In Div. 3) |
|
|
|
|
|
|
|
|
|
|
$ |
- |
|
|
|
|
|
State Group |
3 |
BP48 |
Exterior foundations - out buildings (VOID) |
|
|
|
|
|
|
|
|
|
|
$ |
- |
|
|
|
|
|
Void |
3 |
BP61 |
Polished Concrete Sealer (None shown See BP50) |
|
|
|
|
|
|
$ |
- |
|
|
$ |
- |
|
|
$ |
- |
|
Void |
3 |
|
Concrete floor cutting / core drilling & in-fill (YTB) |
|
|
|
|
|
|
$ |
- |
|
|
$ |
- |
|
|
$ |
- |
|
Void |
4 |
BP10 |
Exterior Stone Veneer |
|
|
$ |
334,000 |
|
|
$ |
334,000 |
|
|
$ |
- |
|
|
$ |
334,000 |
|
FSR |
4 |
BP55 |
Interior CMU |
|
|
$ |
2,002,042 |
|
|
$ |
2,002,042 |
|
|
$ |
- |
|
|
$ |
2,002,042 |
|
FSR |
5 |
BP18 |
Misc. Metals, Lobby Stairs, Railings (In Div. 5) |
|
|
|
|
|
|
$ |
- |
|
|
$ |
- |
|
|
$ |
- |
|
Stone Bridge |
5 |
BP24 |
Stainless Steel Wall Sheathing and equipment platforms (Void - In Div 5?) |
|
|
|
|
|
|
$ |
- |
|
|
$ |
- |
|
|
$ |
- |
|
|
5 |
BP51 |
Exterior Structural Studs (In Committed Log) |
|
|
$ |
- |
|
|
$ |
- |
|
|
$ |
- |
|
|
$ |
- |
|
Xxxxx |
5 |
|
Misc. Metals to support MEP penetrations/roof curbs |
|
|
|
|
|
|
$ |
- |
|
|
$ |
- |
|
|
$ |
- |
|
|
6 |
TBD |
BUDGET PLACEHOLDER - DIV. 6 |
|
|
$ |
635,459 |
|
|
$ |
635,459 |
|
|
$ |
- |
|
|
$ |
- |
|
|
7 |
BP11 |
Spray on Fireproofing |
|
|
$ |
- |
|
|
$ |
- |
|
|
$ |
- |
|
|
$ |
- |
|
Xxxxx |
7 |
BP12 |
Insulated Wall Panels/Louvers |
|
|
|
|
|
|
|
|
|
|
$ |
- |
|
|
|
|
|
Building Inovations Group (BIG) |
7 |
BP16 |
Curtain Wall & storefront |
|
|
|
|
|
|
|
|
|
|
$ |
- |
|
|
|
|
|
Krueg |
7 |
BP17 |
Roofing - Need to ensure cutting of deck for MEP trades. |
|
|
|
|
|
|
$ |
- |
|
|
$ |
- |
|
|
$ |
- |
|
X.X. Xxxxxxx |
8 |
BP15 |
Interior Overhead Coiling Doors (Void - in BP19) |
|
|
$ |
- |
|
|
$ |
- |
|
|
$ |
- |
|
|
$ |
- |
|
|
8 |
BP28 |
Glass and Glazing; interior storefronts |
|
|
$ |
285,000 |
|
|
$ |
285,000 |
|
|
$ |
- |
|
|
$ |
285,000 |
|
R.E. Xxxx |
8 |
|
BUDGET PLACEHOLDER |
|
|
$ |
2,222,209 |
|
|
$ |
2,222,209 |
|
|
$ |
- |
|
|
$ |
- |
|
Removed for De-scope |
9 |
BP14 |
Doors/Frames/Hardware - Core and Shell (Void in BP 27) |
|
|
|
|
|
|
$ |
- |
|
|
$ |
- |
|
|
$ |
- |
|
|
9 |
BP25 |
Millwork & Cabinets |
|
|
$ |
989,602 |
|
|
$ |
989,602 |
|
|
$ |
- |
|
|
$ |
989,602 |
|
Infinity Northeast (Only Bidder) |
9 |
BP26 |
Sealants (In BP27) |
|
|
|
|
|
|
$ |
- |
|
|
$ |
- |
|
|
$ |
- |
|
|
9 |
BP27 |
Interior gyp board walls, ceilings, ACT ceilling, door/frames/hardware; top of wall firestopping; wall and corner guards; fire extinguishers; floor mats |
|
|
$ |
7,300,000 |
|
|
$ |
7,300,000 |
|
|
$ |
- |
|
|
$ |
7,300,000 |
|
Xxxxx Construction (Low Bidder) |
9 |
BP29 |
Ceramic Tile |
|
|
$ |
559,700 |
|
|
$ |
559,700 |
|
|
$ |
- |
|
|
$ |
559,700 |
|
Xxxxx-Xxxxxxx |
9 |
BP32 |
Resilent Flooring & Carpeting |
|
|
$ |
653,150 |
|
|
$ |
653,150 |
|
|
$ |
- |
|
|
$ |
653,150 |
|
Heritage Contract Flooring |
9 |
BP31 |
Carpeting (In BP32) |
|
|
|
|
|
|
$ |
- |
|
|
$ |
- |
|
|
$ |
- |
|
|
9 |
BP33 |
Painting |
|
|
$ |
604,500 |
|
|
$ |
604,500 |
|
|
$ |
- |
|
|
$ |
604,500 |
|
ICC (RW) |
9 |
BP37 |
Toilet/Bath Accessories (In BP27) |
|
|
|
|
|
|
$ |
- |
|
|
$ |
- |
|
|
$ |
- |
|
|
9 |
BP38 |
Operable Partitions (In BP27) |
|
|
|
|
|
|
$ |
- |
|
|
$ |
- |
|
|
$ |
- |
|
|
9 |
BP50 |
Epoxy Resin Flooring |
|
|
$ |
1,127,650 |
|
|
$ |
1,127,650 |
|
|
$ |
- |
|
|
$ |
1,127,650 |
|
MJA |
10 |
BP34 |
Toilet Partitions |
|
|
$ |
91,625 |
|
|
$ |
91,625 |
|
|
$ |
- |
|
|
$ |
91,625 |
|
Infinity Northeast (Only Bidder) |
10 |
BP35 |
Interior Signage (Code & Interior/exterior) |
|
|
$ |
240,000 |
|
|
$ |
240,000 |
|
|
$ |
- |
|
|
$ |
240,000 |
|
ASI |
10 |
BP36 |
Lockers |
|
|
$ |
270,428 |
|
|
$ |
270,428 |
|
|
$ |
- |
|
|
$ |
270,428 |
|
Kraftwerks |
Exhibit 1 - Page 2 of 14 March 1, 2019 |
CONFIDENTIAL |
. |
Athenex GMP Pending Procurement Summary |
Exyte U.S. Inc. |
Division |
Bid Package Number |
Bid Package Description |
|
|
FINAL BID Selected for GMP |
|
Estimated Amount "Yet to Buy" in Award Value |
Recommended Award Value |
|
Grand Total Contingency |
|
GMP Value |
|
Bidder Selected for Pricing |
|||||||||
11 |
BP19 |
Loading Dock Equipment (Includes BP15 budget) |
|
|
$ |
875,099 |
|
|
$ |
875,099 |
|
$ |
- |
|
$ |
875,099 |
|
Rite Xxxx |
|||||
11 |
BP20 |
Vaults |
|
|
$ |
- |
|
|
$ |
- |
|
$ |
- |
|
$ |
- |
|
Custom Vault |
|||||
11 |
BP21 |
Coolers |
|
|
$ |
500,000 |
|
|
$ |
500,000 |
|
$ |
- |
|
$ |
500,000 |
|
Xxxxxx Xxxxxxxx |
|||||
12 |
BP40 |
Laboratory Casework |
|
|
$ |
753,000 |
|
|
$ |
753,000 |
|
$ |
- |
|
$ |
753,000 |
|
Kraftwerks |
|||||
13 |
C101 |
Clean Room Systems |
|
|
$ |
4,871,317 |
|
|
$ |
4,871,317 |
|
$ |
- |
|
$ |
4,871,317 |
|
PCI |
|||||
13 |
BP47 |
Pre-Cast Building |
|
|
$ |
22,750 |
|
|
$ |
22,750 |
|
$ |
- |
|
$ |
22,750 |
|
Hy-Grade Precast |
|||||
14 |
BP22 |
Elevators |
|
|
$ |
406,400 |
|
|
$ |
406,400 |
|
$ |
- |
|
$ |
406,400 |
|
Schindler |
|||||
21 |
FP101 |
Fire Protection |
|
|
$ |
2,064,600 |
|
|
$ |
2,064,600 |
|
$ |
- |
|
$ |
2,064,600 |
|
SRI |
|||||
22 |
M102 |
Plumbing |
|
|
$ |
2,838,839 |
|
|
$ |
2,838,839 |
|
$ |
- |
|
$ |
2,838,839 |
|
|
|||||
22 |
BP23 |
Underground Plumbing |
|
|
|
|
|
|
|
|
|
$ |
- |
|
|
|
|
XX Xxxxxxx |
|||||
23 |
M101 |
Wet Mechanical |
|
|
$ |
10,769,004 |
|
|
$ |
10,769,004 |
|
$ |
- |
|
$ |
10,769,004 |
|
|
|||||
23 |
M101 |
Multi-package award credit |
|
|
$ |
(1,298,000 |
) |
|
$ |
(1,298,000 |
) |
$ |
- |
|
$ |
(1,298,000 |
) |
XX Xxxxxxxx |
|||||
23 |
M103 |
Dry Mechanical |
|
|
$ |
13,525,568 |
|
|
$ |
13,525,568 |
|
$ |
- |
|
$ |
13,525,568 |
|
XX Xxxxxxxx |
|||||
25 |
E101-040 |
I&C |
|
|
$ |
9,129,149 |
|
|
$ |
9,129,149 |
|
$ |
- |
|
$ |
9,129,149 |
|
U & S |
|||||
26 |
E101 |
Electrical Distirbution (MV) |
|
|
$ |
12,532,000 |
|
|
$ |
12,532,000 |
|
$ |
- |
|
$ |
12,532,000 |
|
Xxxxxxxx |
|||||
26 |
|
Switchyard |
|
|
$ |
- |
|
|
$ |
- |
|
$ |
- |
|
$ |
- |
|
Xxxxxxxx |
|||||
26 |
|
Long Lead Switch Gear |
|
|
$ |
- |
|
|
|
|
|
$ |
- |
|
|
|
|
Xxxxx |
|||||
26 |
LLE007 |
Stand-By Generators |
|
|
$ |
- |
|
|
|
|
|
$ |
- |
|
$ |
- |
|
Xxxxxxx (Xxxxxx) |
|||||
27 |
E101-027 |
IT |
|
|
$ |
1,551,000 |
|
|
$ |
1,551,000 |
|
$ |
- |
|
$ |
1,551,000 |
|
Xxxxxxxx |
|||||
28 |
E101-028 |
Security Safety (Cameras/Badge Readers) |
|
|
$ |
336,758 |
|
|
$ |
336,758 |
|
$ |
- |
|
$ |
336,758 |
|
Buffalo Fire and Secuity |
|||||
28 |
E101-023 |
Fire Alarm (Void 0 In E101) |
|
|
$ |
- |
|
|
$ |
- |
|
$ |
- |
|
$ |
- |
|
|
|||||
32 |
BP43 |
Asphalt Paving (In PCO Log) |
|
|
|
|
|
|
|
|
|
$ |
- |
|
|
|
|
St. Xxxxxx |
|||||
32 |
BP45 |
Fencing (Client Request) |
|
|
$ |
- |
|
|
$ |
- |
|
$ |
- |
|
$ |
- |
|
St. Xxxxxx |
|||||
32 |
BP42 |
Soil Prep & Landscaping (Void - In BP05) |
|
|
|
|
|
|
$ |
- |
|
$ |
- |
|
$ |
- |
|
|
|||||
33 |
BP59 |
Water Storage Tank and Pad |
|
|
$ |
659,950 |
|
|
$ |
659,950 |
|
$ |
- |
|
$ |
659,950 |
|
The State Group (only bidder) |
|||||
40 |
N/A |
Process Automation |
|
|
|
|
|
|
$ |
- |
|
$ |
- |
|
$ |
- |
|
|
|||||
41 |
P101 |
Process Piping Systems |
|
|
$ |
5,215,289 |
|
|
$ |
5,215,289 |
|
$ |
- |
|
$ |
5,215,289 |
|
XX Xxxxxxxx |
|||||
41 |
PQ001 |
Parts Washer |
|
|
$ |
342,065 |
|
|
$ |
342,065 |
|
$ |
- |
|
$ |
342,065 |
|
Biopharma Systems, LLC |
|||||
41 |
PQ002 |
Terminal Steriler & Autoclaves |
|
|
$ |
283,419 |
|
|
$ |
283,419 |
|
$ |
- |
|
$ |
283,419 |
|
Biopharma Systems, LLC |
|||||
41 |
PQ003 |
Pure Steam |
|
|
$ |
218,305 |
|
|
$ |
218,305 |
|
$ |
- |
|
$ |
218,305 |
|
AquaChem |
|||||
41 |
PQ005 |
WFI Pretreatment & Generation |
|
|
$ |
1,176,670 |
|
|
$ |
1,176,670 |
|
$ |
- |
|
$ |
1,176,670 |
|
Meco |
|||||
41 |
PQ006 |
WFI Storage and Distribution |
|
|
$ |
735,882 |
|
|
$ |
735,882 |
|
$ |
- |
|
$ |
735,882 |
|
Meco |
|||||
41 |
PQ007 |
OFCA Generation |
|
|
$ |
328,950 |
|
|
$ |
328,950 |
|
$ |
- |
|
$ |
328,950 |
|
Ingersol Rand |
|||||
41 |
PQ008 |
Formulation Tanks and Platforms |
|
|
|
|
|
|
$ |
- |
|
$ |
- |
|
|
|
|
Deferred |
|||||
41 |
PQ009 |
TCU |
|
|
$ |
- |
|
|
$ |
- |
|
$ |
- |
|
|
|
|
Deferred |
|||||
41 |
PQ011 |
Transfer and Utility Panels |
|
|
|
|
|
|
$ |
- |
|
$ |
- |
|
|
|
|
Deferred |
|||||
41 |
PQ013 |
Syringe Assembly and labeling |
|
|
|
|
|
|
$ |
- |
|
$ |
- |
|
|
|
|
Deferred |
|||||
41 |
PQ014 |
CIP Skids |
|
|
$ |
335,927 |
|
|
$ |
335,927 |
|
$ |
- |
|
$ |
335,927 |
|
TBD - Redesign on-going |
|||||
41 |
PQ015 |
WWT Tanks (Including lift stations/neutralization) |
|
|
$ |
1,056,446 |
|
|
$ |
1,056,446 |
|
$ |
- |
|
$ |
1,056,446 |
|
Xxxx Process Equipment |
|||||
41 |
PQ016 |
pH Neutrailzation and Lift Station (Void in PQ15) |
|
|
|
|
|
|
$ |
- |
|
$ |
- |
|
$ |
- |
|
In PQ15 |
|||||
41 |
PQ017 |
Downflow Booths |
|
|
|
|
|
|
$ |
- |
|
$ |
- |
|
$ |
- |
|
Deferred |
|||||
41 |
PQ018 |
Mixproof Valve Manifold |
|
|
|
|
|
|
$ |
- |
|
$ |
- |
|
$ |
- |
|
Deferred |
|||||
41 |
PQ010 |
WFI Cooler |
|
|
$ |
946,700 |
|
|
$ |
946,700 |
|
$ |
- |
|
$ |
946,700 |
|
Xxxxxxxxxx / Exergy |
|||||
41 |
PQ019 |
Pallet Washer |
|
|
|
|
|
|
$ |
- |
|
$ |
- |
|
$ |
- |
|
Deferred |
|||||
41 |
PQ020 |
Heat Exchanger (Void - in PQ15) |
|
|
|
|
|
|
$ |
- |
|
$ |
- |
|
$ |
- |
|
In PQ15 |
|||||
41 |
PQ021 |
Centrifugal Pumps (Void - in PQ15) |
|
|
|
|
|
|
$ |
- |
|
$ |
- |
|
$ |
- |
|
In PQ15 |
|||||
41 |
PQ022 |
AODD Pumps (Void - in PQ15) |
|
|
|
|
|
|
$ |
- |
|
$ |
- |
|
$ |
- |
|
In PQ15 |
|||||
41 |
TBD |
Remaining Misc. Equipment |
|
|
$ |
3,912,595 |
|
|
$ |
3,912,595 |
|
$ |
- |
|
$ |
3,912,595 |
|
Estimate per Equipment List Rev. 6 |
|||||
|
|
|
|
|
|
|
|
|
$ |
- |
|
|
|
|
|
|
|
|
|||||
|
|
|
|
|
|
Yet To Buy |
|
$ |
- |
|
|
|
$ |
- |
|
$ |
92,932,096 |
|
Both Yet to Buy and Contingency Relocated to Cover Sheet 21JAN19 |
Exhibit 1 - Page 3 of 14 March 1, 2019 |
CONFIDENTIAL |
. |
Athenex GMP - Process Equipment List |
. |
*The equipment listed below identifies the process equipment to be procured via the GMP. With the exception of equipment packages listed on the "Pending Procurement" sheets, under division 41, equiment which is not listed or funded below, is not included in the GMP
Div. |
Description |
BOD Estimate |
|
Status (Deferred, Athenex, Exyte, Other Package) |
GMP Value |
||
41 |
Utility Panel for Portable Tank |
$ |
19,397 |
|
Deferred |
$ |
- |
41 |
API Benchtop Powder Hood #1 |
$ |
23,387 |
|
Deferred |
$ |
- |
41 |
API Benchtop Scale #1 |
$ |
7,997 |
|
Deferred |
$ |
- |
41 |
Utility Panel for Portable Tank |
$ |
19,397 |
|
Deferred |
$ |
- |
41 |
API Benchtop Powder Hood #2 |
$ |
23,387 |
|
Deferred |
$ |
- |
41 |
API Benchtop Scale #2 |
$ |
7,997 |
|
Deferred |
$ |
- |
41 |
IV/Syringe Used-to-clean EQ Pass through |
$ |
20,327 |
|
Deferred |
$ |
- |
41 |
Walkie Lift |
$ |
4,192 |
|
Athenex |
$ |
- |
41 |
Isolated Filling Line (2- 100mL) 30 unit/min |
$ |
219,122 |
|
Deferred |
$ |
- |
41 |
Automated Tub Cover and liner removal |
$ |
38,259 |
|
Deferred |
$ |
- |
41 |
Syringe Filler #2 30 unit/min |
$ |
38,259 |
|
Deferred |
$ |
- |
41 |
Plunger Insertion |
$ |
38,259 |
|
Deferred |
$ |
- |
41 |
Isolator TBD |
$ |
38,259 |
|
Deferred |
$ |
- |
41 |
VHP Unit for Isolator TBD |
$ |
38,259 |
|
Deferred |
$ |
- |
41 |
Wash Station |
$ |
4,795 |
|
Deferred |
$ |
- |
41 |
Utility Carts |
$ |
2,096 |
|
Deferred |
$ |
- |
41 |
Automated Denester |
$ |
310,685 |
|
Deferred |
$ |
- |
41 |
Machine Inspection (cosmetic, particulate) |
$ |
1,550,774 |
|
Deferred |
$ |
- |
41 |
Automated Renester |
$ |
310,149 |
|
Deferred |
$ |
- |
41 |
Manual Syringe Inspection system in lieu of Automated |
$ |
(1,750,000) |
|
Deferred |
$ |
- |
41 |
Placeholder for EQ Line items |
$ |
5,843,675 |
|
Deferred |
$ |
- |
41 |
Summarized Packaging utility use |
$ |
2,096 |
|
Deferred |
$ |
- |
41 |
Utility Carts |
$ |
15,206 |
|
Deferred |
$ |
- |
41 |
Manual Quality Checking Station |
$ |
6,957 |
|
Deferred |
$ |
- |
41 |
Hand Packing Station |
$ |
6,957 |
|
Deferred |
$ |
- |
41 |
Case Taper Machine MISC-007 |
$ |
4,527 |
|
Deferred |
$ |
- |
41 |
Label Dispenser MISC-008 |
$ |
4,527 |
|
Deferred |
$ |
- |
41 |
Isolated Filling System 10 unit/min |
$ |
78,798 |
|
Deferred |
$ |
- |
41 |
Bag Filler (2 head custom filler) |
$ |
12,575 |
|
Deferred |
$ |
- |
41 |
Isolator TBD |
$ |
21,125 |
|
Deferred |
$ |
- |
41 |
VHP Unit for Isolator TBD |
|
0 |
|
Deferred |
$ |
- |
41 |
Manual Quality Checking Station |
$ |
3,806 |
|
Deferred |
$ |
- |
41 |
Hand Packing Station |
$ |
3,806 |
|
Deferred |
$ |
- |
41 |
Case Taper Machine MISC-009 |
$ |
3,806 |
|
Deferred |
$ |
- |
41 |
Label Dispenser MISC-010 |
$ |
5,332 |
|
Deferred |
$ |
- |
41 |
ISO 5 Laminar Flow Bench #1 8 ft. |
$ |
7,427 |
|
Athenex |
$ |
- |
41 |
ISO 5 Laminar Flow Bench #2 8 ft. |
$ |
7,427 |
|
Athenex |
$ |
- |
41 |
ISO 5 Laminar Flow Bench #3 8 ft. |
$ |
9,523 |
|
Athenex |
$ |
- |
41 |
ISO 5 Laminar Flow Bench #4 8 ft. |
$ |
9,523 |
|
Athenex |
$ |
- |
41 |
ISO 5 Laminar Flow Bench #5 8 ft. |
$ |
13,715 |
|
Athenex |
$ |
- |
41 |
ISO 5 Laminar Flow Bench #6 8 ft. |
$ |
4,192 |
|
Athenex |
$ |
- |
41 |
Terminal Sterilizer #1 (Air/Steam) 380 cf |
$ |
933,551 |
|
Deferred |
$ |
- |
41 |
Homogenizer 50 L MX-001 |
$ |
25,685 |
|
Athenex |
$ |
- |
41 |
Top-loading balance (Isolator) WS-006 |
$ |
12,575 |
|
Athenex |
$ |
- |
41 |
Process Water POU |
$ |
4,192 |
|
PQ10 (WFI Coolers) |
$ |
- |
41 |
Sachet Filler 120 unit/min |
$ |
45,468 |
|
Athenex |
$ |
- |
41 |
Discharge Conveyor |
$ |
2,096 |
|
Athenex |
$ |
- |
41 |
Ointment Ultrasonic cleaner 10 gal |
$ |
9,791 |
|
Athenex |
$ |
- |
41 |
Process Water POU |
$ |
26,606 |
|
PQ10 (WFI Coolers) |
$ |
- |
41 |
Wash Sink |
$ |
32,893 |
|
Exyte |
$ |
32,893.00 |
41 |
Ointment Used-to-clean EQ Pass through MISC-036 |
$ |
8,138 |
|
Deferred |
$ |
- |
41 |
Checkweigher CW-001 |
$ |
17,017 |
|
Athenex |
$ |
- |
41 |
Hand Packing Station |
$ |
3,806 |
|
Athenex |
$ |
- |
41 |
Case Taper Machine MISC-013 |
$ |
3,806 |
|
Athenex |
$ |
- |
41 |
Label Dispenser MISC-014 |
$ |
3,806 |
|
Athenex |
$ |
- |
41 |
Excipient Bench Scale #1 |
$ |
26,606 |
|
Deferred |
$ |
- |
41 |
Excipient Portable Floor Scale #1 3300 lbs. |
$ |
22,063 |
|
Deferred |
$ |
- |
41 |
Down flow Booth Solvent or Powder 10 ft. |
$ |
200,876 |
|
Deferred |
$ |
- |
41 |
3 lab sinks, glassware washer |
$ |
17,302 |
|
Exyte provide Lab Sinks, Athenex provide Glass Washers |
$ |
17,302.00 |
41 |
Misc. Lab Sinks, Benchtop EQ |
$ |
4,192 |
|
Exyte provide Lab Sinks, Athenex provide Benchtop Eq. |
$ |
4,192.00 |
41 |
Misc. Lab Sinks, Benchtop EQ |
$ |
15,206 |
|
Exyte provide Lab Sinks, Athenex provide Benchtop Eq. |
$ |
15,206.00 |
41 |
Decontamination Sterilizer 35 cf AUTO-004 |
$ |
376,574 |
|
PQ2 (Autoclave) |
$ |
- |
41 |
Pallet Washer, Automatic |
$ |
103,187 |
|
Athenex |
$ |
- |
41 |
Isco Sampler |
$ |
4,376 |
|
Athenex |
$ |
- |
41 |
Incubators (3) |
$ |
141,750 |
|
Exyte |
$ |
141,750 |
41 |
ISO 5 Laminar Flow Bench #1 - Xxxxx, flow, balances |
$ |
36,500 |
|
Exyte - Athenex Estimate |
$ |
36,500.00 |
41 |
ISO 5 Laminar Flow Bench #2 - Xxxxx, flow, balances |
$ |
36,500 |
|
Exyte - Athenex Estimate |
$ |
36,500.00 |
41 |
ISO 5 Laminar Flow Bench #3 - Xxxxx, flow, balances |
$ |
36,500 |
|
Exyte - Athenex Estimate |
$ |
36,500.00 |
41 |
ISO 5 Laminar Flow Bench #4 - Xxxxx, flow, balances |
$ |
36,500 |
|
Exyte - Athenex Estimate |
$ |
36,500.00 |
41 |
ISO 5 Laminar Flow Bench #5 - Xxxxx, flow, balances |
$ |
36,500 |
|
Exyte - Athenex Estimate |
$ |
36,500.00 |
41 |
ISO 5 Laminar Flow Bench #6 - Xxxxx, flow, balances |
$ |
36,500 |
|
Exyte - Athenex Estimate |
$ |
36,500.00 |
41 |
Carts / Totes / Balance Cable 15 / 100 / 8 |
$ |
17,650 |
|
Exyte - Athenex Estimate |
$ |
17,650.00 |
Exhibit 1 - Page 4 of 14
March 1, 2019
Athenex GMP - Process Equipment List |
. |
Div. |
Description |
BOD Estimate |
|
Status (Deferred, Athenex, Exyte, Other Package) |
GMP Value |
||
41 |
Labler Printers - SW / INK |
$ |
50,500 |
|
Exyte - Athenex Estimate |
$ |
50,500.00 |
41 |
Formulation Isolator |
$ |
200,000 |
|
Exyte - Athenex Estimate |
$ |
200,000.00 |
41 |
Formulation TCU |
$ |
8,000 |
|
Exyte - Athenex Estimate |
$ |
8,000.00 |
41 |
Homogenizer - INCREASE SIZE TO 100L (from 10L) |
$ |
200,000 |
|
Exyte - Athenex Estimate |
$ |
200,000.00 |
41 |
Top-loading balance (Isolator) |
$ |
18,000 |
|
Exyte - Athenex Estimate |
$ |
18,000.00 |
41 |
Top-loading balance (Formulation) |
$ |
18,000 |
|
Exyte - Athenex Estimate |
$ |
18,000.00 |
41 |
Sachet Filler - |
$ |
750,000 |
|
Exyte - Athenex Estimate |
$ |
750,000.00 |
41 |
Discharge Conveyor |
$ |
10,000 |
|
Exyte - Athenex Estimate |
$ |
10,000.00 |
41 |
Ointment Ultrasonic cleaner - INCREASED TO 2 CLEANE |
$ |
12,000 |
|
Exyte - Athenex Estimate |
$ |
12,000.00 |
41 |
Checkweigher - ADDED COST OF CHECKWEIGHER |
$ |
87,000 |
|
Exyte - Athenex Estimate |
$ |
87,000.00 |
41 |
OINTMENT PACKAGING AND SERIALIZATION |
$ |
250,000 |
|
Exyte - Athenex Estimate |
$ |
250,000.00 |
41 |
Filter Integrity Testing Equipment - $46,000 each - 1 only |
$ |
46,000 |
|
Exyte - Athenex Estimate |
$ |
46,000.00 |
41 |
Placeholder for Conveyor Line items |
$ |
15,000 |
|
Exyte - Athenex Estimate |
$ |
15,000.00 |
41 |
Pallet Washer, Automatic |
$ |
103,000 |
|
Exyte - Athenex Estimate |
$ |
103,000.00 |
00 |
Xxxxxxx Xxxxxxxxxxxxxx |
$ |
8,000 |
|
Exyte - Athenex Estimate |
$ |
8,000.00 |
41 |
ISCO Sampler |
$ |
4,376 |
|
Exyte - Athenex Estimate |
$ |
4,376.00 |
41 |
Portable Autoclave |
$ |
37,275 |
|
Exyte - Athenex Estimate |
$ |
37,275.00 |
41 |
Laminar Flow Hood #1 |
$ |
5,355 |
|
Exyte - Athenex Estimate |
$ |
5,355.00 |
41 |
Laminar Flow Hood #2 |
$ |
5,355 |
|
Exyte - Athenex Estimate |
$ |
5,355.00 |
41 |
Biosafety Cabinet #1 |
$ |
8,400 |
|
Exyte - Athenex Estimate |
$ |
8,400.00 |
41 |
Biosafety Cabinet #2 |
$ |
8,400 |
|
Exyte - Athenex Estimate |
$ |
8,400.00 |
41 |
Biosafety Cabinet #3 |
$ |
8,400 |
|
Exyte - Athenex Estimate |
$ |
8,400.00 |
41 |
Biosafety Cabinet #4 |
$ |
8,400 |
|
Exyte - Athenex Estimate |
$ |
8,400.00 |
41 |
Biosafety Cabinet #5 |
$ |
8,400 |
|
Exyte - Athenex Estimate |
$ |
8,400.00 |
41 |
Biosafety Cabinet #6 |
$ |
8,400 |
|
Exyte - Athenex Estimate |
$ |
8,400.00 |
41 |
Biosafety Cabinet #7 |
$ |
8,400 |
|
Exyte - Athenex Estimate |
$ |
8,400.00 |
41 |
Biosafety Cabinet #8 |
$ |
8,400 |
|
Exyte - Athenex Estimate |
$ |
8,400.00 |
41 |
Refrigerator: Reach-in #1 |
$ |
10,500 |
|
Exyte - Athenex Estimate |
$ |
10,500.00 |
41 |
Refrigerator: Reach-in #2 |
$ |
10,500 |
|
Exyte - Athenex Estimate |
$ |
10,500.00 |
41 |
Refrigerator: Reach-in #5 |
$ |
10,500 |
|
Exyte - Athenex Estimate |
$ |
10,500.00 |
41 |
Freezer: Reach-in #1 |
$ |
13,650 |
|
Exyte - Athenex Estimate |
$ |
13,650.00 |
41 |
Freezer: Reach-in #2 |
$ |
13,651 |
|
Exyte - Athenex Estimate |
$ |
13,651.00 |
41 |
Forced Air Oven, 3.7 cu ft |
$ |
4,200 |
|
Exyte - Athenex Estimate |
$ |
4,200.00 |
41 |
Lab ultrasonic Bath, 2.8 L |
$ |
2,100 |
|
Exyte - Athenex Estimate |
$ |
2,100.00 |
41 |
Milliflex single head pump |
$ |
12,600 |
|
Exyte - Athenex Estimate |
$ |
12,600.00 |
41 |
Milliflex 3 head pump head |
$ |
18,900 |
|
Exyte - Athenex Estimate |
$ |
18,900.00 |
41 |
pH/conductivity meters |
$ |
13,230 |
|
Exyte - Athenex Estimate |
$ |
13,230.00 |
41 |
Plate Reader |
$ |
61,950 |
|
Exyte - Athenex Estimate |
$ |
61,950.00 |
41 |
XPE56 series micro analytical balance |
$ |
81,900 |
|
Exyte - Athenex Estimate |
$ |
81,900.00 |
41 |
XPE205 analytical balance |
$ |
37,800 |
|
Exyte - Athenex Estimate |
$ |
37,800.00 |
41 |
Viscometer, RVDV2T |
$ |
4,095 |
|
Exyte - Athenex Estimate |
$ |
4,095.00 |
41 |
Viscometer, LVDV2T CP |
$ |
4,410 |
|
Exyte - Athenex Estimate |
$ |
4,410.00 |
41 |
Viscometer sample cup |
$ |
945 |
|
Exyte - Athenex Estimate |
$ |
945.00 |
41 |
0.8 deg CP spindle |
$ |
420 |
|
Exyte - Athenex Estimate |
$ |
420.00 |
41 |
3 deg /2.4 cm CP spindle |
$ |
420 |
|
Exyte - Athenex Estimate |
$ |
420.00 |
41 |
TOC Meter, M9 Laboratory |
$ |
38,850 |
|
Exyte - Athenex Estimate |
$ |
38,850.00 |
41 |
TOC Meter, M series autosampler |
$ |
11,550 |
|
Exyte - Athenex Estimate |
$ |
11,550.00 |
41 |
TOC Meter Part 11 compliance package DataPro 2 SW |
$ |
3,465 |
|
Exyte - Athenex Estimate |
$ |
3,465.00 |
41 |
TOC IQOQ Package and on-site validation/calibration |
$ |
8,820 |
|
Exyte - Athenex Estimate |
$ |
8,820.00 |
41 |
micro lab laminar flow bench 36" |
$ |
25,200 |
|
Exyte - Athenex Estimate |
$ |
25,200.00 |
41 |
autotitrator |
$ |
34,650 |
|
Exyte - Athenex Estimate |
$ |
34,650.00 |
41 |
autotitrator 21 CFR Part 11 SW package and validaiton |
$ |
5,250 |
|
Exyte - Athenex Estimate |
$ |
5,250.00 |
41 |
glassware washer |
$ |
48,300 |
|
Exyte - Athenex Estimate |
$ |
48,300.00 |
41 |
glassware washer racks |
$ |
48,300 |
|
Exyte - Athenex Estimate |
$ |
48,300.00 |
41 |
small glassware washer |
$ |
11,550 |
|
Exyte - Athenex Estimate |
$ |
11,550.00 |
41 |
bosch visual inspection hood for lab |
$ |
8,400 |
|
Exyte - Athenex Estimate |
$ |
8,400.00 |
41 |
UPLC - Total of 7 |
$ |
735,000 |
|
Exyte - Athenex Estimate |
$ |
735,000.00 |
41 |
software |
$ |
56,994 |
|
Exyte - Athenex Estimate |
$ |
56,994.00 |
41 |
Software SQT |
$ |
8,736 |
|
Exyte - Athenex Estimate |
$ |
8,736.00 |
41 |
annual software maintenance |
$ |
17,850 |
|
Exyte - Athenex Estimate |
$ |
17,850.00 |
41 |
LACE Server |
$ |
42,000 |
|
Exyte - Athenex Estimate |
$ |
42,000.00 |
41 |
annual calibration service - 7 UPLC's |
$ |
162,855 |
|
Exyte - Athenex Estimate |
$ |
162,855.00 |
|
Original Estimated Value |
$ |
12,772,811 |
|
Final GMP Value |
$ |
3,912,595.00 |
Exhibit 1 - Page 5 of 14
March 1, 2019
Yet To Buy Analysis |
. |
Definitions: |
Yet-to-buy: Identified tasks, which cannot be quantified or qualified in sufficient detail during the procurement process, but are necessary to provide a complete and functional system. The cost for bonds, as deemed necessary by the design-build contractor, are also included in these funds. Contingency: Costs for a future event or circumstance which is possible, but can not be predicted with certainty. GMP YTB Summary |
Division |
Package |
YTB Value |
Comments |
|
1 |
Temp Power |
$ |
18,000 |
Did not increase Div. 1 total of $4.8M |
4 |
Exterior Stone Veneer |
$ |
20,000 |
Coordination with exterior devices. Doors, badge readers, etc. Misc. blocking/coordination with cold form |
4 |
Interior CMU |
$ |
100,000 |
Misc. angles/supports and fire stopping required to support late bulletin changes to CMU package. Includes penetrations for duct, cable tray, not clearly shown. Include remobilization for walls left open to support process equipment move-in. |
8 |
Glass and Glazing: interiors |
$ |
30,000 |
Coordination with stair landings and exterior mullions at lobby. Know this will required additional coordination |
9 |
Millwork & Cabinets |
$ |
35,000 |
Rigging, move-in and coordination with other trades for utilities/power/IT, including protection of finished product |
9 |
Interiors Package |
$ |
365,000 |
Significant number of penetrations and late changes will add fire stopping, door hardware coordination and finish changes. Hold-areas for move-in of equipment. Coordination with IT/Secuirty and other hardware issues expected. |
9 |
Ceramic Tile |
$ |
30,000 |
Additional sub-base excluded by bidders. Includes coordination with other trades and OT as needed. |
9 |
Resilent Flooring and Carpet |
$ |
25,000 |
Coordination with interiors, temporary protection of finished floor and repairs due to damages. |
9 |
Painting |
$ |
- |
|
9 |
Epoxy Resign Flooring |
$ |
50,000 |
Coordination with interiors, temporary protection of finished floor and repairs due to damages. |
10 |
Toilet Partitions |
$ |
8,000 |
Misc. metals to support hung partitions. |
10 |
Lockers |
$ |
15,000 |
Protection of final products. Coordination with other trades/services. |
10 |
Interior Signage |
$ |
- |
|
11 |
Loading Dock Equipment |
$ |
85,000 |
6% Price increase expected 2/1 due to lack of award. Expect to relocate steel and air-curtains due to coordination of insulated doors |
11 |
Coolers |
$ |
25,000 |
Rigging, move-in coordination. POC coordintion locations need to be finalized |
12 |
Laboratory Casework |
$ |
50,000 |
Coordination with other trades for utilities, rigging and protection of finished product. |
13 |
Clean Room Systems |
$ |
250,000 |
Known door changes, additional rough-in for clocks, EMS/PCS devices, extended GC to hold open areas for process equipment move-in. |
13 |
Precast Buildings |
$ |
5,000 |
Additional fans, lights, desk-top items & finish requests |
14 |
Elevators |
$ |
10,000 |
Pit coordination issue known. Depth/sump locations expected to be changed |
21 |
Fire Protection |
$ |
50,000 |
Additional heads due to wall changes, height changes. Ductwork blockages will required added heads. |
22 |
Plumbing |
$ |
150,000 |
Overtime and rework of floor drains/restrooms or other coordination requirements. |
23 |
Wet mechanical |
$ |
500,000 |
Winter conditions, coordination of deferred scope with end of line by-passes. Support of IT rooms with potential changes to cooling design. (CRAC's vs rack cooling) Flushing issues with AHJ or environment groups. (Frac tanks). Includes OT or shift differential as needed to support schedule. |
23 |
Dry mechanical |
$ |
850,000 |
Balancing issues, damper testing for AHJ, exhaust fan issues due to deferred scope, winter continues, support with dehumidication to support finishes, OT, winter conditions, potential off- shift differential. Added back AHU-120, however removed $100K for fencing and $150K for exterior "A" signage on building. |
25 |
I&C |
$ |
450,000 |
Relocation of RIO's, I/O's. Coordination with VFD's and owner XXX changes not currently available. |
26 |
Electrical Distribution |
$ |
600,000 |
Panel Schedule changes due to deferred scope, gaps in equipment feeders. Sequence of Op's/communications plan for generators and ATS. Wiring to Gen Sets/Communications to primary substations. Includes $120K winter conditions. Includes potential union wage rate increase. Includes power for dehumidification units. Includes additional Xxxx-Ties of approx. $100k. |
27 |
IT |
$ |
50,000 |
Changes to clock system, device locations which continue to be on-going. Minor wiring diagram changes, supports within rooms. |
28 |
Security |
$ |
50,000 |
Additional devices, cameras and badge reader support. Cable lengths for 24V power seems to be too long and expect additional transformers. |
33 |
Water Storage Tank and Pad |
$ |
20,000 |
Site leveling/grading and coordination with fire water pump building |
41 |
Process Piping |
$ |
300,000 |
Rigging coordination, support of CQV efforts which are not identified but are expected. Spec gases for testing/commissioning support. Costs to relocate devices based on process equipment requirements/POC's. |
Exhibit 1 - Page 6 of 14 March 1, 2019 |
CONFIDENTIAL |
. |
Yet To Buy Analysis |
. |
41 |
Parts Washer |
$ |
57,000 |
$32K in alternates provided by vendor and anticipated to be needed. Coordination with other trades for POC's and internior configuration of equipment. Includes expediting submittals/equipment due to schedule. |
41 |
Autoclave |
$ |
54,000 |
Includes lternates provided by vendor and anticipated to be needed. Coordination with other trades for rigging and connections to POC's. Includes expediting submittals/equipment due to schedule. |
41 |
Pure Steam |
$ |
60,000 |
Includes additional POC's, filters/start-up concerns. Includes pre-heater, graphics manager, other alternates expecting client approval. |
41 |
WFI Pretreatment & Generation |
$ |
150,000 |
Includes SOO changes expected, additional testing/validation by vendor expected to be required. Includes vendor alternates expected to be required by owner. |
41 |
WFI Storage & Distribution |
$ |
50,000 |
Includes alternates provided by vendor and expected to be requested by owner. |
41 |
OFCA |
$ |
35,000 |
Includes reduction for smaller dryer (option) and other options. |
41 |
CIP Skids |
$ |
- |
|
41 |
WWT Tanks |
$ |
60,000 |
Rigging/move-in coordination due to late arrival of equipment. Includes DEC testing support, chemicals and minor AHJ requests |
41 |
WFI Coolers |
$ |
35,000 |
Rigging and start-up support - multiple mobilizations. |
41 |
Remaining process equipment |
$ |
- |
|
|
SUBTOTAL |
$ |
4,642,000 |
|
Fee/Insurance |
$ |
162,470 |
Added due to request to move this value below COW Value |
|
TOTAL |
$ |
4,804,470 |
Total value carried "below the line" for YTB. |
Exhibit 1 - Page 7 of 14 March 1, 2019 |
CONFIDENTIAL |
. |
Athenex GMP Indirects Summary |
. |
Indirect Cost Categories |
|
|
Total (Deferred Scope) |
Design |
|
$ |
12,557,128 |
EPCM Services |
|
$ |
12,329,008 |
EPCM GC's |
|
$ |
2,697,883 |
EPCM Fee (M+W) |
|
$ |
4,000,927 |
EPCM Fee (Pike) |
|
$ |
1,350,000 |
EPCM Insurance |
|
$ |
1,600,371 |
Xxxx XX Insurance |
|
$ |
30,613 |
|
|
|
|
Total: |
|
$ |
34,565,930 |
Design Summary
Description |
|
|
Total (Deferred Scope) |
Concept Design / Site Conditions |
|
$ |
397,225 |
Basis of Design including Bridging /PCM Services |
|
$ |
1,920,489 |
BOD Accelerated Efforts / Pre-Con Services/ PCM Services |
|
$ |
2,247,266 |
Detail Design Allowance |
|
$ |
5,846,935 |
Construction Administration |
|
$ |
2,145,213 |
|
|
|
|
Total |
|
$ |
12,557,128 |
Exhibit 1 - Page 8 of 14 March 1, 2019 |
CONFIDENTIAL |
. |
Athenex GMP Indirects Summary |
. |
|
Athenex Facility - Dunkirk, NY |
|
|
|
|
General Conditions - GMP Value |
|
|
|
|
January, 2019 |
|
|
|
|
|
|
|
|
GEN |
ERAL CONDITIONS |
|
Cost |
Comments |
1 |
Safety Equipment/PPE |
$ |
18,600 |
|
2 |
Safety incentives |
$ |
23,250 |
|
3 |
Safety training / documentation |
$ |
74,000 |
|
4 |
First aid supplies |
$ |
15,000 |
|
5 |
Safety signage, type, AHJ Requirements during Construction |
$ |
38,500 |
|
6 |
Blue Prints - Drawings/Reprographics |
$ |
57,500 |
|
7 |
Bid Advertisement |
$ |
45,000 |
|
8 |
Office supplies - printer ink, paper, pens, reproduction, etc. |
$ |
51,000 |
|
9 |
Pantry Supplies (Napkins, paper towels, plastic silver ware, etc.) |
$ |
18,500 |
|
10 |
Toilet Supplies (toilet paper, hands was liquid, broom, mop, cleaning liquids) |
$ |
16,600 |
|
11 |
Cell Phones / Walkie Talkies |
$ |
82,720 |
|
12 |
Office Vehicles (Rental, Fuel, Maintenance Costs) |
$ |
22,000 |
|
13 |
Team Meetings/Catering/Site Recognition Events |
$ |
19,000 |
|
14 |
Computers, software, printers, Copier, Plotters, service maint. contracts, etc. |
$ |
205,530 |
|
15 |
Furnishings, white boards, chairs |
$ |
78,000 |
|
16 |
Postal/ messenger services |
$ |
26,000 |
|
17 |
Staff relocation |
$ |
80,000 |
|
18 |
Monthly staff per diem |
$ |
608,200 |
|
19 |
Offsite Staff Travel |
$ |
105,500 |
|
20 |
Construction waste dumpsters |
$ |
0 |
General Requirement |
21 |
Construction turnstiles |
$ |
0 |
Not Required |
22 |
Project signage |
$ |
31,000 |
|
23 |
Water truck |
$ |
0 |
General Requirement |
24 |
Site inspections / Factory inspections M+W Staff only |
$ |
0 |
Not Required |
25 |
Site trailer (Construction, site meetings) 6-wide 72'x60', Safety 2-wide 24'x60', 2-wide Break 24' x 60' |
$ |
369,200 |
|
|
Xxxxxxxxx Warehouse- 7,000sf |
$ |
0 |
Athenex Paid Direct |
|
Xxxxxxxxx Parking Acreage 3.1 |
$ |
0 |
Athenex Paid Direct |
26 |
Utilities for Xxxxxxxxx Rented Spaces |
$ |
0 |
Athenex Paid Direct |
27 |
Site Conex |
$ |
51,300 |
|
28 |
Utilities for site trailers (tie-ins for water, power, septic) |
$ |
321,000 |
|
29 |
Temp Construction Utilities (e.g. Construction Power, Temp Heat) |
$ |
0 |
Athenex Paid Direct |
30 |
Permits |
$ |
0 |
Athenex Paid Direct |
31 |
Snow removal |
$ |
0 |
General Requirement |
32 |
Road sweeping |
$ |
0 |
General Requirement |
33 |
Site gators ($46,490 Cost to date + $1,500 maintance/repairs if needed) |
$ |
47,990 |
|
34 |
Site Security |
$ |
0 |
General Requirement |
35 |
Site Fencing |
$ |
0 |
Site Contractor (COW) |
35 |
BIM Coordination Efforts |
$ |
491,800 |
|
|
|
$ |
2,897,190 |
|
|
Adjustments |
|
|
|
1 |
Xxxxxxxxx Warehouse- 7,000sf |
-$ |
42,000 |
|
2 |
Xxxxxxxxx Parking Acreage 3.1 |
-$ |
30,000 |
|
3 |
Utilities for Xxxxxxxxx Rented Spaces |
-$ |
108,000 |
|
4 |
National Grid Adjustment - Paid by Athenex |
-$ |
4,236 |
|
5 |
National Grid Adjustment - Paid by Athenex |
-$ |
15,071 |
|
|
|
|
|
|
|
GMP Value - General Conditions |
$ |
2,697,883 |
|
|
|
|
|
|
Exhibit 1 - Page 9 of 14 March 1, 2019 |
CONFIDENTIAL |
. |
Athenex GMP General Conditions |
. |
|
Athenex Facility - Dunkirk, NY |
|
|
|
|
General Conditions - GMP Value |
|
|
|
|
January, 2019 |
|
|
|
|
|
|
|
|
GEN |
ERAL CONDITIONS |
|
Cost |
Comments |
1 |
Safety Equipment/PPE |
$ |
18,600 |
|
2 |
Safety incentives |
$ |
23,250 |
|
3 |
Safety training / documentation |
$ |
74,000 |
|
4 |
First aid supplies |
$ |
15,000 |
|
5 |
Safety signage, type, AHJ Requirements during Construction |
$ |
38,500 |
|
6 |
Blue Prints - Drawings/Reprographics |
$ |
57,500 |
|
7 |
Bid Advertisement |
$ |
45,000 |
|
8 |
Office supplies - printer ink, paper, pens, reproduction, etc. |
$ |
51,000 |
|
9 |
Pantry Supplies (Napkins, paper towels, plastic silver ware, etc.) |
$ |
18,500 |
|
10 |
Toilet Supplies (toilet paper, hands was liquid, broom, mop, cleaning liquids) |
$ |
16,600 |
|
11 |
Cell Phones / Walkie Talkies |
$ |
82,720 |
|
12 |
Office Vehicles (Rental, Fuel, Maintenance Costs) |
$ |
22,000 |
|
13 |
Team Meetings/Catering/Site Recognition Events |
$ |
19,000 |
|
14 |
Computers, software, printers, Copier, Plotters, service maint. contracts, etc. |
$ |
205,530 |
|
15 |
Furnishings, white boards, chairs |
$ |
78,000 |
|
16 |
Postal/ messenger services |
$ |
26,000 |
|
17 |
Staff relocation |
$ |
80,000 |
|
18 |
Monthly staff per diem |
$ |
608,200 |
|
19 |
Offsite Staff Travel |
$ |
105,500 |
|
20 |
Construction waste dumpsters |
$ |
0 |
General Requirement |
21 |
Construction turnstiles |
$ |
0 |
Not Required |
22 |
Project signage |
$ |
31,000 |
|
23 |
Water truck |
$ |
0 |
General Requirement |
24 |
Site inspections / Factory inspections M+W Staff only |
$ |
0 |
Not Required |
25 |
Site trailer (Construction, site meetings) 6-wide 72'x60', Safety 2-wide 24'x60', 2-wide Break 24' x 60' |
$ |
369,200 |
|
|
Xxxxxxxxx Warehouse- 7,000sf |
$ |
0 |
Athenex Paid Direct |
|
Xxxxxxxxx Parking Acreage 3.1 |
$ |
0 |
Athenex Paid Direct |
26 |
Utilities for Xxxxxxxxx Rented Spaces |
$ |
0 |
Athenex Paid Direct |
27 |
Site Conex |
$ |
51,300 |
|
28 |
Utilities for site trailers (tie-ins for water, power, septic) |
$ |
321,000 |
|
29 |
Temp Construction Utilities (e.g. Construction Power, Temp Heat) |
$ |
0 |
Athenex Paid Direct |
30 |
Permits |
$ |
0 |
Athenex Paid Direct |
31 |
Snow removal |
$ |
0 |
General Requirement |
32 |
Road sweeping |
$ |
0 |
General Requirement |
33 |
Site gators ($46,490 Cost to date + $1,500 maintance/repairs if needed) |
$ |
47,990 |
|
34 |
Site Security |
$ |
0 |
General Requirement |
35 |
Site Fencing |
$ |
0 |
Site Contractor (COW) |
35 |
BIM Coordination Efforts |
$ |
491,800 |
|
|
|
$ |
2,897,190 |
|
|
Adjustments |
|
|
|
1 |
Xxxxxxxxx Warehouse- 7,000sf |
-$ |
42,000 |
|
2 |
Xxxxxxxxx Parking Acreage 3.1 |
-$ |
30,000 |
|
3 |
Utilities for Xxxxxxxxx Rented Spaces |
-$ |
108,000 |
|
4 |
National Grid Adjustment - Paid by Athenex |
-$ |
4,236 |
|
5 |
National Grid Adjustment - Paid by Athenex |
-$ |
15,071 |
|
|
|
|
|
|
|
GMP Value - General Conditions |
$ |
2,697,883 |
|
|
|
|
|
|
Exhibit 1 - Page 10 of 14 March 1, 2019 |
CONFIDENTIAL |
. |
Athenex GMP General Requirement Summary |
Division 1. |
Division 1
Item |
Scope Overview |
|
Total ($) |
Comments |
1 |
Temporary Heat |
$ |
320,000 |
Installation/Removal (Not utilities) |
2 |
Temporary Guard Shacks with Security Gate |
$ |
9,900 |
|
3 |
Security personnel |
$ |
264,000 |
|
4 |
Document Support for Commissioning |
$ |
302,750 |
|
5 |
Temporary Construction Power |
$ |
600,000 |
|
6 |
Site General Condition |
$ |
- |
Civil Contractor (COW) |
7 |
Textura Program |
$ |
- |
Not Used |
8 |
Roof Access (Stair Towers) 12 Months |
$ |
75,036 |
|
9 |
Lull w/ Operator |
$ |
93,900 |
|
10 |
Maintain Perimeter Cable System/Toe Boards for Openings |
$ |
130,061 |
|
11 |
First Aid Equip |
$ |
- |
General Conditions |
12 |
Safety - Fire Protection |
$ |
100,000 |
|
13 |
Temp Floor Protection (Material and Labor) |
$ |
222,893 |
|
14 |
Temp Protection at Exteriors & Openings (Material and Labor) |
$ |
399,210 |
|
15 |
Temp. Access Pathway for Athenex personell after TCO |
$ |
- |
Not Required per Athenex |
16 |
Temp Elevator Protection |
$ |
16,717 |
|
17 |
Temp Toilet(Rent - 20 ea @ 20 mos.) |
$ |
78,014 |
|
18 |
Parking / Site / Roads (Clearing, Snow/Salting, and Maintenance) |
$ |
356,637 |
|
19 |
Lawn Maintenance |
$ |
11,145 |
|
20 |
Job Photographs |
$ |
- |
Not Required per Athenex |
21 |
Blue Prints |
$ |
- |
General Conditions |
22 |
Bid Advertising |
$ |
- |
General Conditions |
23 |
Supplies - Postage & Handling |
$ |
- |
General Conditions |
24 |
Job Sign |
$ |
17,832 |
|
25 |
Job Signs/Temp |
$ |
557 |
|
26 |
Surveying - 2-man crew, initial bldg layout, BM's |
$ |
27,862 |
|
27 |
Current Cleanup including Slab Maintenance (4 Laborers) |
$ |
551,290 |
|
28 |
Rent Dumpster (C&D, Metals, Cardboard) (10/week @ 20 mos) |
$ |
872,202 |
|
29 |
Final Cleanup - Core and Shell |
$ |
400,000 |
|
|
GENERAL REQUIREMENTS TOTAL |
$ |
4,850,007 |
|
Exhibit 1 - Page 11 of 14 March 1, 2019 |
CONFIDENTIAL |
. |
September 2017 to February 2018
April 2018 to September 2018 February 2018 to September 2019 October 2019 to June 2020 |
1900 |
||||||||
|
Title/Position |
Resource |
Duration/ Quantity |
|
Hr Rate $$ |
|
Total |
||
|
Executive Team |
|
|
|
|
|
|
||
|
|
|
- |
$ |
205 |
$ |
- |
||
|
Construction Operations Team |
|
|
|
|
|
|
||
|
Project Director |
Exyte |
3,880 |
$ |
206.85 |
$ |
802,578 |
||
Xxx Xxxx |
Exyte |
|
|
|
|
|
|||
Project Manager |
Exyte |
4,340 |
$ |
206.85 |
$ |
897,729 |
|||
Xxxx Xxxxx |
Exyte |
|
|
|
|
|
|||
MEP CM 1 - Process |
Exyte |
3,600 |
$ |
148.75 |
$ |
535,500 |
|||
Xxxxxx Xxxxxxxx |
|
|
|
|
|
|
|||
MEP CM 2 - Mechanical |
Exyte |
3,640 |
$ |
148.75 |
$ |
541,450 |
|||
Xxxxx Xxxxxxxxx - Lotus |
|
|
|
|
|
|
|||
MEP CM 3 - Electrical/ELVS |
Exyte |
3,720 |
$ |
148.75 |
$ |
553,350 |
|||
Xxxx Xxxxxxxx |
|
|
|
|
|
|
|||
MEP CM 4 - ELVS. (LSS/I&C/FMCS) |
Exyte |
3,320 |
$ |
148.75 |
$ |
493,850 |
|||
Xxxx Xxxxxxx |
|
|
|
|
|
|
|||
General Super |
Exyte |
3,440 |
$ |
171.25 |
$ |
589,100 |
|||
Xxxxx Xxxxxxx |
|
|
|
|
|
|
|||
MV/ELECT SI 1 |
Exyte |
3,480 |
$ |
136.85 |
$ |
476,238 |
|||
Xxxxx Xxxxxxx |
Exyte |
|
|
|
|
|
|||
Electrical SI 2 |
Exyte |
- |
$ |
136.85 |
$ |
- |
|||
I&C Support - Removed 19OCT |
Exyte |
|
|
|
|
|
|||
CA SI - 3 Code Support Super |
Exyte |
2,520 |
$ |
136.85 |
$ |
344,862 |
|||
TBD |
Exyte |
|
|
|
|
|
|||
Project Eng 1 |
Exyte |
4,120 |
$ |
106.80 |
$ |
440,016 |
|||
Xxxxxx Xxxxx |
Exyte |
|
|
|
|
|
|||
Project Eng 3 |
Exyte |
3,400 |
$ |
106.80 |
$ |
363,120 |
|||
Xxxx Xxxxxx / Xxx Xxxxxxxx |
Exyte |
|
|
|
|
|
|||
EHS |
Office |
|
|
|
|
|
|
||
|
Office Admin/Doc Lead |
Exyte |
4,496 |
$ |
78.75 |
$ |
354,060 |
||
Xxxxxx Xxxxxx / Xxxxx Xxxxxx |
|
|
|
|
|
|
|||
Office Admin Support |
Exyte |
3,600 |
$ |
78.75 |
$ |
283,500 |
|||
Xxxxxxxx Xxxx |
|
|
|
|
|
|
|||
EHS |
|
|
|
|
|
|
|
||
|
EHS Manager |
Exyte |
152 |
$ |
171.25 |
$ |
26,030 |
||
Xxxx Xxxxxx |
|
|
|
|
|
|
|||
EHS Field |
Exyte |
3,680 |
$ |
97.90 |
$ |
360,272 |
|||
Xxxxxx XxXxxxx |
|
|
|
|
|
|
Exhibit 1 - Page 12 of 14 March 1, 2019 |
CONFIDENTIAL |
. |
|
EHS Adm |
Exyte |
3,280 |
$ |
55.00 |
$ |
180,400 |
Xxxxxxx Xxxxxxx |
|
|
|
|
|
|
|
Project |
Commercial Team |
|
|
|
|
|
|
|
|
Exyte |
- |
|
|
$ |
- |
Procurement |
|
|
|
|
|
|
|
Procurement Specialist |
Exyte |
1,840 |
$ |
137.00 |
$ |
252,080 |
|
Xxxxx Xxxxxxx |
|
|
$ |
0.00 |
|
|
|
Procurement Specialist |
Exyte |
1,640 |
$ |
137.00 |
$ |
224,680 |
|
Xxxxxx Xxxxxxx |
|
|
$ |
0.00 |
|
|
|
Estimating |
|
|
|
|
|
|
|
CSA Estimator |
Exyte |
440 |
$ |
143.85 |
$ |
63,294 |
|
Various |
|
|
|
|
|
|
|
MEP/Process Estimator |
Exyte |
440 |
$ |
143.85 |
$ |
63,294 |
|
Various |
|
|
|
|
|
|
|
Electrical Estimator |
Exyte |
440 |
$ |
124.95 |
$ |
54,978 |
|
Various |
|
|
|
|
|
|
|
Scheduling |
|
|
|
|
|
|
|
Scheduler |
Exyte |
2,200 |
$ |
143.85 |
$ |
316,470 |
|
Xx Xxxx |
|
|
|
|
|
|
|
Cost / Finance |
|
|
|
|
|
|
|
Assit PC |
Exyte |
640 |
$ |
93.45 |
$ |
59,808 |
|
Xxxxxx Xxx |
|
|
|
|
|
|
|
Assit PC |
Exyte |
2,040 |
$ |
93.45 |
$ |
190,638 |
|
Xxxxx Xxxxxxxx |
|
|
|
|
|
|
|
Assit PC |
Exyte |
1,680 |
$ |
93.45 |
$ |
156,996 |
|
Xxxxx Xxxxxxx |
|
|
|
|
|
|
|
Commerial Manager |
Exyte |
600 |
$ |
171.25 |
$ |
102,750 |
|
Xxxx Xxxxx - PM as of 6/15 |
|
|
|
|
|
|
|
Cost Control 1 |
Exyte |
3,960 |
$ |
107.10 |
$ |
424,116 |
|
Xxxxxx Xxxx |
|
|
|
|
|
|
|
Cost Control 2 |
|
680 |
$ |
112.30 |
$ |
76,364 |
|
Xxxxxxx Xxxxxxxx |
|
|
|
|
|
|
|
|
QAQC |
|
|
|
|
|
|
|
Commissioning Specialist |
Exyte |
- |
$ |
150.00 |
$ |
- |
Removed - Athenex Scope |
|
|
|
|
|
|
|
DC Asst |
Exyte |
- |
$ |
52.50 |
$ |
- |
|
Removed - Not Expect |
|
|
|
|
|
|
|
DC Department Lead |
Exyte |
428 |
$ |
93.75 |
$ |
40,125 |
|
Xxxxxx Xxxxx |
|
|
|
|
|
|
|
|
Total Labor |
|
71696 |
|
|
$ |
9,267,648 |
|
FULL TIME EQUIVALENTS (FTE) |
|
11.8 |
|
|
|
|
Hrs per month
Exyte Cost |
|
$ |
- |
$ |
- |
$ 9,267,648 |
PIke Cost |
|
|
|
|
|
$ 3,061,360 |
|
|
Total Labor $ 12,329,008 |
Exhibit 1 - Page 13 of 14 March 1, 2019 |
CONFIDENTIAL |
. |
Exhibit C - Xxxx XX Labor Forecast |
|
Hours & Costs Billed thru January 31, 2019 |
F-19 |
M-19 |
A-19 |
M-19 |
J-19 |
J-19 |
A-19 |
S-19 |
O-19 |
N-19 |
D-19 |
J-20 |
Forecasted Total Billing Hours thru March 19 |
|||||||||||||||||||||||
Title/Position |
Resource |
|
Hrly Billing Rate |
Total Hours thru 1/31/19 |
|
Total Billed thru 2/28/19 (costs thru 1/31/19) |
Month 16 |
Month 17 |
Month 18 |
Month 19 |
Month 20 |
Month 21 |
Month 22 |
Month 23 |
Month 21 |
Month 22 |
Month 23 |
Month 24 |
Hrly Billing Rate Effective 4/1/19 |
Hours (2018 Rates) |
Hours (2019 Rates) |
|
Total Incurred & Forecasted Billing |
||||||||||||||
Executive Team |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||||||||||||||
Project Executive |
PIKE |
$ |
205 |
175.00 |
$ |
35,875 |
16 |
16 |
16 |
16 |
16 |
16 |
16 |
16 |
16 |
16 |
16 |
16 |
213.06 |
32.00 |
160 |
$ |
76,525 |
||||||||||||||
Construction Operations Team |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
- |
|
- |
|
|
||||||||||||||
Project Director (Xxxxxx X) |
XXXX |
$ |
205 |
2,444.00 |
$ |
501,020 |
173 |
173 |
173 |
173 |
173 |
173 |
173 |
173 |
173 |
173 |
173 |
173 |
213.06 |
346.00 |
1,730 |
$ |
940,544 |
||||||||||||||
General Superintendent (Xxx X) |
XXXX |
$ |
135 |
1,920.00 |
$ |
259,200 |
173 |
173 |
173 |
173 |
173 |
173 |
173 |
173 |
173 |
173 |
173 |
173 |
155.25 |
346.00 |
1,730 |
$ |
574,493 |
||||||||||||||
Site Superintendent (Xxxx X) |
XXXX |
$ |
100 |
2,050.00 |
$ |
205,000 |
000 |
000 |
173 |
173 |
173 |
173 |
173 |
173 |
173 |
173 |
173 |
173 |
125.00 |
346.00 |
1,730 |
$ |
455,850 |
||||||||||||||
Building Superintendent (Xxxx X) |
XXXX |
$ |
100 |
192.00 |
$ |
19,200 |
173 |
173 |
173 |
173 |
173 |
173 |
173 |
173 |
173 |
173 |
173 |
173 |
125.00 |
346.00 |
1,730 |
$ |
270,050 |
||||||||||||||
Project Engineer (Ikea & Xxx) |
XXXX |
$ |
65 |
1,702.00 |
$ |
110,630 |
346 |
346 |
346 |
346 |
346 |
346 |
346 |
346 |
346 |
346 |
346 |
346 |
85.00 |
692.00 |
3,460 |
$ |
449,710 |
||||||||||||||
EHS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
- |
|
- |
|
|
||||||||||||||
Field Safety |
PIKE |
$ |
85 |
24.00 |
$ |
2,040 |
|
|
|
|
|
|
|
|
|
|
|
|
- |
|
- |
$ |
2,040 |
||||||||||||||
Commercial Team |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
- |
|
- |
|
|
||||||||||||||
Procurement |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
- |
|
- |
|
|
||||||||||||||
Procurement Specialist |
PIKE |
$ |
100 |
1,839.00 |
$ |
183,900 |
20 |
10 |
|
|
|
|
|
|
|
|
|
|
115.00 |
30.00 |
- |
$ |
186,900 |
||||||||||||||
Estimating |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
- |
|
- |
|
|
||||||||||||||
CSA Estimator |
PIKE |
$ |
100 |
1,459.00 |
$ |
145,900 |
|
|
|
|
|
|
|
|
|
|
|
|
- |
|
- |
$ |
145,900 |
||||||||||||||
Cost / Finance |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
- |
|
- |
|
|
||||||||||||||
Cost Accountant (Xxxx & Xxxx) |
XXXX |
$ |
65 |
375.00 |
$ |
24,375 |
40 |
40 |
40 |
40 |
40 |
40 |
40 |
40 |
40 |
40 |
40 |
40 |
85.00 |
80.00 |
400 |
$ |
63,575 |
||||||||||||||
Cost Engineer (Xxxxxx) |
XXXX |
$ |
95 |
974.00 |
$ |
92,530 |
173 |
173 |
173 |
173 |
173 |
173 |
173 |
173 |
173 |
173 |
173 |
173 |
110.31 |
346.00 |
1,730 |
$ |
316,236 |
||||||||||||||
Doc Control 2 (Xxxxxxx) |
XXXX |
$ |
55 |
2,132.00 |
$ |
117,260 |
173 |
173 |
173 |
173 |
173 |
173 |
173 |
173 |
173 |
173 |
173 |
173 |
96.25 |
346.00 |
1,730 |
$ |
302,803 |
||||||||||||||
Misc. Shared Support Services |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
- |
|
|
|
|
||||||||||||||
Scheduler (Xxxx?) |
XXXX |
$ |
109 |
1,165.50 |
$ |
127,040 |
85 |
85 |
85 |
85 |
85 |
85 |
85 |
85 |
85 |
85 |
85 |
85 |
128.62 |
170.00 |
850 |
$ |
254,897 |
||||||||||||||
Total Labor |
|
|
|
16,451.50 |
$ |
1,823,970 |
1545 |
1535 |
1525 |
1525 |
1525 |
1525 |
1525 |
1525 |
1525 |
1525 |
1525 |
1525 |
|
|
15,250 |
$ |
4,039,521 |
||||||||||||||
|
|
|
|
|
|
|
|
|
|||||||||||||||||||||||||||||
FULL TIME EQUIVALENTS (FTE) |
|
|
9 |
9 |
8.80
9 |
8.80
9 |
8.80
9 |
8.80
9 |
8.80
9 |
8.80
9 |
8.80
9 |
8.80
9 |
8.80
9 |
8.80 |
|
Exhibit 1 - Page 14 of 14 March 1, 2019 |
CONFIDENTIAL |
. |
Athenex GMP Specificatio |
Exhibit 2 (p. 1 of 5) |
Name |
Rev |
Set Name |
Issuance Date |
|
01 10 10 |
General Requirements |
0 |
Div. 1 Specs |
11/1/2018 |
01 21 00 |
Allowances |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
01 30 00 |
Administrative Requirements |
0 |
Div. 1 Specs |
11/1/2018 |
01 33 00 |
Submittal Procedures |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
01 40 00 |
Quality Requirements |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
01 42 00 |
References |
0 |
Div. 1 Specs |
11/1/2018 |
01 45 33 |
Code-Required Special Inspections and Procedures |
0 |
Div. 1 Specs |
11/1/2018 |
01 50 00 |
Temporary Facilities and Controls |
0 |
Div. 1 Specs |
11/1/2018 |
01 58 13 |
Temporary Project Signage |
0 |
Div. 1 Specs |
11/1/2018 |
01 60 00 |
Product Requirements |
0 |
Div. 1 Specs |
11/1/2018 |
01 73 00 |
Execution |
0 |
Div. 1 Specs |
11/1/2018 |
01 74 19 |
Construction Waste Management and Disposal |
0 |
Div. 1 Specs |
11/1/2018 |
01 74 19ESD |
ESD Waste Management |
NA |
Div. 1 Specs |
11/1/2018 |
01 77 00 |
Closeout Procedures |
0 |
Div. 1 Specs |
11/1/2018 |
01 78 23 |
Operation and Maintenance Data |
0 |
Div. 1 Specs |
11/1/2018 |
01 78 39 |
Project Record Documents |
0 |
Div. 1 Specs |
11/1/2018 |
01 79 00 |
Demonstration and Training |
0 |
Div. 1 Specs |
11/1/2018 |
01 80 00 |
BIM Standards |
0 |
Div. 1 Specs |
11/1/2018 |
01 91 13 |
General Commissioning Requirements |
0 |
Div. 1 Specs |
11/1/2018 |
02 41 19 |
Selective Demolition |
0 |
IFC Specs |
4/23/2018 |
03 30 00 |
Cast-In-Place Concrete-Civil |
0 |
IFC Specs |
4/23/2018 |
03 30 00 |
Cast-In-Place Concrete-Structural |
0 |
IFC Specs |
4/23/2018 |
03 30 20 |
Concrete Slab on Grade |
0 |
IFC Specs |
4/23/2018 |
03 30 25 |
Concrete Slan on Deck |
1 |
BOD Issue |
2/8/2018 |
04 20 00 |
Unit Masonry |
A |
BOD Issue |
2/8/2018 |
04 43 13 16 |
Adhered Stone Masonry Veneer |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
05 12 00 |
Structural Steel Framing |
A |
BOD Issue |
2/8/2018 |
05 30 00 |
Metal Decking |
A |
BOD Issue |
2/8/2018 |
05 40 00 |
Cold-Formed Metal Framing |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
05 50 00 |
Metal Fabrications |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
05 51 13 |
Metal Pan Stairs |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
05 51 19 |
Metal Grating Stairs |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
05 52 13 |
Pipe and Tube Railings |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
05 72 13 |
Clean Room Equipment Platform & Stairs |
0 |
PQ007-9&11 |
9/7/2018 |
05 73 13 |
Glazed Decorative Metal Railings |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
06 10 53 |
Miscellaneous Rough Carpentry |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
06 16 00 |
Sheathing |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
06 41 16 |
Plastic-Laminate-Faced Architectural Cabinets |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
07 13 26 |
Self-Adhering Sheet Waterproofing |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
07 14 16 |
Cold Fluid Applied Water Proofing |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
07 21 00 |
Thermal Insulation |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
07 21 19 |
Foamed-in-Place Insulation |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
07 27 26 |
Fluid-Applied Membrane Air Barriers |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
07 42 13 19 |
Insulated Metal Wall Panels |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
07 54 19 |
Polyvinyl-Chloride (PVC) Roofing |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
07 62 00 |
Sheet Metal Flashing and Trim |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
07 81 00 |
Applied Fireproofing |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
07 84 13 |
Penetration Firestopping |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
07 84 43 |
Joint Firestopping |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
07 91 00 |
Preformed Joint Seals |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
07 92 00 |
Joint Sealants |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
08 11 13 |
Hollow Metal Doors and Frames |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
08 11 19 |
Stainless-Steel Doors and Frames |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
08 31 13 |
Access Doors and Frames |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
08 33 23 |
Overhead Coiling Doors |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
08 33 23 13 |
High Performance Overhead Coiling Fabric Doors |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
08 41 13 |
Aluminum-Framed Entrances and Storefronts |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
08 44 13 |
Glazed Aluminum Curtain Walls |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
08 71 00 |
Door Hardware |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
08 80 00 |
Glazing |
2 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
08 91 19 |
Fixed Louvers |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
09 21 16 23 |
Gypsum Board Shaft Wall Assemblies |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
09 22 16 |
Non-Structural Metal Framing |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
09 29 00 |
Gypsum Board |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
09 30 13 |
Ceramic Tiling |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
09 30 23 |
Glass Mosaic Tiling |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
09 51 13 |
Acoustical Panel Ceilings |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
09 54 23 |
Linear Multi-Box Metal Ceilings |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
09 65 13 |
Resilient Base and Accessories |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
09 65 19 |
Resilient Tile Flooring |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
09 65 36 |
Static-Control Resilient Flooring |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
09 65 66 |
Resilient Athletic Flooring |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
09 67 23 |
Resinous Flooring |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
09 68 13 |
Tile Carpeting |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
09 70 00 |
Wall Finishes |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
1/30/2019 |
CONFIDENTIAL |
. |
Athenex GMP Specificatio |
Exhibit 2 (p. 2 of 5) |
Spec No. |
Name |
Rev |
Set Name |
Issuance Date |
09 91 23 |
Interior Painting |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
10 21 13 14 |
Stainless-Steel Toilet Compartments |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
10 21 13 17 |
Phenolic-Core Toilet Compartments |
A |
Issue for Bid |
10/12/2018 |
10 22 39 |
Folding Panel Partitions |
1 |
IFC Package |
12/7/2018 |
10 26 00 |
Wall and Door Protection |
0 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
10 44 13 |
Fire Protection Cabinets |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
10 44 16 |
Fire Extinguishers |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
10 51 13 |
Metal Lockers |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
10 56 13 |
Metal Storage Shelving |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
11 05 13 |
Common Motor Requirements for Equipment |
0 |
Issue for Bid |
8/15/2018 |
11 13 13 |
Loading Dock Bumpers |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
11 13 16 |
Loading Dock Seals and Shelters |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
11 13 19 |
Master Control Panels |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
11 13 19 01 |
Stationary Loading Dock Equipment |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
11 53 13 |
Laboratory Fume Hoods |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
12 24 13 |
Roller Window Shades |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
12 35 53 13 |
Metal Laboratory Casework |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
12 48 16 |
Entrance Floor Grilles |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
13 00 00 |
Clean Room Pre-engineered Modular Wall and Ceiling System |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
13 21 26 |
Cold Storage Rooms |
0 |
Issue for Bid |
10/12/2018 |
13 27 00 |
Vaults |
A |
Core and Shell |
6/29/2018 |
14 21 23 16 |
Machine Room-Less Electric Traction Passenger Elevators |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
14 24 13 |
Hydraulic Freight Elevators |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
21 05 13 |
Common Motor Requirements for Fire-Suppression Equipment |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
21 05 17 |
Sleeves and Sleeve Seals fir Fire-Supression Piping |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
21 05 18 |
Escutcheons for Fire-Suppression Piping |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
21 05 23 |
General-Duty Valves for Fire Protection Piping |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
21 05 29 |
Hangers & Supports for Fire Suppression Piping & Equipment |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
21 05 53 |
Identification for Fire-Suppression Piping and Equipment |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
21 11 00 |
Facility Fire-Suppression Water-Service Piping |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
21 11 19 |
Fire Department Cpnnections |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
21 12 00 |
Fire-Suppression Standpipes |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
21 13 13 |
Wet-Pipe Sprinkler Systems |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
21 13 16 |
Dry-Pipe Spinkler Systems |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
21 22 00 |
Clean-Agent Fire-Suppression Systems |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
21 31 16 |
Diesel-Drive, Fire Pump |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
21 34 13 |
Pressure-mainetance Pumps |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
21 39 00 |
Controllers for Fire-Pump Drivers |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
21 44 00 |
Fire Protection Water Storage Tanks |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
22 05 13 |
Common Motor Requirements for Plumbing Equipment |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
22 05 16 |
Expansion Fittings and Loops for Plumbing Piping |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
22 05 17 |
Sleeves And Sleeve Seals for Plumbing Piping |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
22 05 18 |
Escutcheons for Plumbing Piping |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
22 05 19 |
Meters and Gages for Plumbing Piping |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
22 05 23 12 |
Ball Valves for Plumbing Piping |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
22 05 23 13 |
Butterfly Valves for Plumbing Piping |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
22 05 23 14 |
Check Valves for Plumbing Piping |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
22 05 23 15 |
Gate Valves for Plumbing Piping |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
22 05 29 |
Hangers and Supports for Plumbing Piping and Equipment |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
22 05 53 |
Identification for Plumbing Piping and Equipment |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
22 07 19 |
Plumbing Piping Insulation |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
22 11 13 |
Facility Water Distribution Piping |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
22 11 13CPL |
Facility Water Distribution Piping |
0 |
IFC Specs |
4/23/2018 |
22 11 16 |
Domestic Water Piping |
0 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
22 11 16 01 |
Domestic Water Piping |
1 |
Pricing Issue |
8/31/2018 |
22 11 17 |
Gray-Water Piping |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
22 11 19 |
Domestic Water Piping Specialties |
0 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
22 11 19 01 |
Domestic Water Piping Specialties |
1 |
Pricing Issue |
8/31/2018 |
22 11 23 13 |
Domestic-Water Packaged Booster Pumps |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
22 11 23 21 |
Inline, Domestic-Water Pipes |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
22 13 13 |
Facility Sanitary Sewers |
0 |
Pricing Issue |
8/31/2018 |
22 13 16 |
Sanitary Waste and Vent Piping |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
22 13 19 |
Sanitary Waste Piping Specialties |
0 |
Pricing Issue |
8/31/2018 |
22 13 19 01 |
Sanitary Waste Piping Specialties |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
22 14 13 |
Facility Storm Drainage Piping |
0 |
Pricing Issue |
8/31/2018 |
22 14 13 01 |
Facility Storm Drainage |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
22 14 23 |
Storm Drainage Piping Specialties |
0 |
Pricing Issue |
8/31/2018 |
22 14 23 01 |
Storm Drainage Piping Specialties |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
22 14 29 |
Sump Pumps |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
22 31 00 |
Domestic Water Softeners |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
22 32 00 |
Grey-Water Harvesting Equipment & Filtration System |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
22 33 00 |
Electric Domestic Water Heaters |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
22 35 00 |
Domestic-Water Heat Exchangers |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
22 42 13 13 |
Commercial Water Closets |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
22 42 13 16 |
Commercial Urinals |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
1/30/2019 |
CONFIDENTIAL |
. |
Athenex GMP Specificatio |
Exhibit 2 (p. 3 of 5) |
Spec No. |
Name |
Rev |
Set Name |
Issuance Date |
22 42 16 13 |
Commercial Lavatories |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
22 42 16 16 |
Commercial Sinks |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
22 42 23 |
Commerical Showers |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
22 45 00 |
Emergency Plumbing Fixtures |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
22 47 16 |
Pressure Water Coolers |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
22 61 13 |
Compressed-Air Piping for Laboratory and Healthcare Facilities |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
22 63 14 |
Compressed Gas Piping for Laboratory and Pharmaceutical Facilities |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
22 66 00 |
Chemical-Waste Systems for Laboratory and Healthcare Facilities |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 05 13 |
Common Motor Requirements for Equipment |
B |
Issue for Bid |
10/12/2018 |
23 05 16 |
Expansion Fittings and Loops for HVAC Piping |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 05 17 |
Sleeves and Sleeve Seals for HVAC Piping |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 05 18 |
Escutcheons For HVAC Piping |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 05 19 |
Meters and Gages for HVAC Piping |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 05 23 |
General-Duty Valves for HVAC Piping |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 05 29 |
Hangers and Supports for HVAC Piping and Equipment |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 05 48 |
Vibration and Seismic Controls for Piping and Equipment |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 05 53 |
Identification for HVAC and Piping and Equipment |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 05 93 |
Testing, Adjusting, and Balancing for HVAC |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 07 00 |
Equipment, Vessels, Piping, and Duct Insulation |
0 |
PQ007-9&11 |
9/7/2018 |
23 07 13 |
Duct Insulation |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 07 16 |
HVAC Equipment Insulation |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 07 19 |
HVAC Piping Insulation |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 09 23 |
Building Management System (BMS) |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 09 23 01 |
BMS Instrumentation for HVAC Controls |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 09 23 11 |
Control Valves |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 09 23 12 |
Control Dampers |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 09 93 11 |
Sequence of Operations for HVAC DDC |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 11 23 |
Facility Natural-Gas Piping |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 21 13 |
Hydronic Piping |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 21 23 |
Hydronic Pumps |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 22 13 |
Steam and Condensate Heating Piping |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 25 00 |
HVAC Water Treatment |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 31 13 |
Metal Ducts |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 31 19 16 |
Manufactured HVAC Outdoor Air Intake Plenum Casings |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 33 00 |
Air Duct Accessories |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 34 16 |
Centrifugal HVAC Fans |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 34 23 01 |
HVAC Power Ventilators |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 34 33 |
Air Curtains |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 36 00 |
Air Terminal Units |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 37 13 |
Diffusers, Registers, and Grilles |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 37 23 |
HVAC Gravity Ventilators |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 41 33 |
High-Efficiency Particulate Filtration |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 51 00 |
Breechings, Xxxxxxxx, and Stacks |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 52 39 |
Firetube Boilers |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 53 16 |
Deaerator and Surge Tank |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 53 18 |
Boiler Blowdown Equipment |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 57 00 |
Heat Exchangers for HVAC |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 57 10 |
Unfired Steam Generators |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 64 16 |
Centrifugal Water Chillers |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 65 00 |
Cooling Towers |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 73 13 01 |
Indoor Central-Station Air-Handling Units |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 73 13 19 |
Indoor Custom Air Handling Units |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 74 00 |
Air Rotation Units |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 74 33 |
Dedicated Outdoor-Air Units |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 81 23 03 |
Computer Room Air Conditioners, Console units |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 82 16 |
Air Coils |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 82 19 |
Fan Coil Units |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 82 29 |
Radiators |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 82 36 |
Finned-Tube Radiation Heaters |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
23 82 39 |
Unit Heaters |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
26 00 01 |
Electrical Work General |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
26 04 45 |
Elevator Control Switches |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
26 05 13 |
Medium-Voltage Cables |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
26 05 19 |
Low-Voltage Electrical Power Conductors and Cables |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
26 05 26 |
Grounding and Bonding for Electrical Systems |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
26 05 29 |
Hangers and Supports for Electrical Systems |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
26 05 33 |
Raceway and Boxes for Electrical Systems |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
26 05 36 |
Cable Trays for Electrical Systems |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
26 05 43 |
Underground Ducts and Raceways for Electrical Systems |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
26 05 44 |
Sleeves and Sleeve Seals for Electrical Raceways and Cabling |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
26 05 53 |
Identification for Electrical Systems |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
26 05 73 |
Arc-Flash Hazard Analysis |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
26 05 85 |
Electrical Requirements for Packaged Equipment |
0 |
PQ007-9&11 |
9/7/2018 |
26 08 00 |
Commissioning of Electrical Systems |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
26 09 13 |
Electrical Power Monitoring and Control |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
1/30/2019 |
CONFIDENTIAL |
. |
Athenex GMP Specificatio |
Exhibit 2 (p. 4 of 5) |
Spec No. |
Name |
Rev |
Set Name |
Issuance Date |
26 09 23 |
Lighting Control Devices |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
26 11 01 |
115kV Substation with Seconday Switchgear |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
26 11 16 11 |
Secondary Unit Substations with Switchgear Secondary |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
26 22 13 |
Low-Voltage Distribution Transformers |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
26 24 13 |
Switchboards |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
26 24 16 |
Panelboards |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
26 25 00 |
Enclosed Bus Assemblies |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
26 27 13 |
Electricity Metering |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
26 27 26 |
Wiring Devices |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
26 28 13 |
Fuses |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
26 28 16 |
Enclosed Switches and Circuit Breakers |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
26 29 13 03 |
Enclosed Controllers |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
26 29 23 |
Variable-Frequency Motor Controllers |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
26 32 13 13 |
Engine Generators |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
26 33 53 |
Static Uninterruptible Power Supply |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
26 36 00 |
Transfer Switches |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
26 41 13 |
Lightning Protection for Structures |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
26 51 19 |
LED Interior Lighting |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
26 52 13 |
Emergency and Exit Lighting |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
26 56 19 |
Exterior Lighting |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
26 58 00 |
Heat Tracing for HVAc Piping |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
28 05 37 11 |
Bi-Directional Amplifiers |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
28 31 11 |
Digital, Addressable Fire-Alarm System |
1 |
Bulletin0020-IFCPermitIssue |
12/14/2018 |
31 10 00 |
Site Clearing |
0 |
IFC Specs |
4/23/2018 |
31 20 00 |
Earth Moving |
0 |
IFC Specs |
4/23/2018 |
31 23 01 |
Excavation Backfill and Compaction Building Areas |
0 |
IFC Specs |
4/23/2018 |
31 23 16 |
Excavation |
0 |
IFC Specs |
4/23/2018 |
31 23 19 |
Dewatering |
0 |
IFC Specs |
4/23/2018 |
31 23 23 |
Soil Compaction |
0 |
IFC Specs |
4/23/2018 |
31 25 00 |
Erosion and Sedimentation Control |
0 |
IFC Specs |
4/23/2018 |
31 50 00 |
Evacuation Support and Protection |
0 |
IFC Specs |
4/23/2018 |
32 12 16 |
Asphalt Paving |
0 |
IFC Specs |
4/23/2018 |
32 13 13 |
Concrete Paving |
0 |
IFC Specs |
4/23/2018 |
32 17 23 |
Pavement Markings |
0 |
IFC Specs |
4/23/2018 |
32 31 13 |
Chain Link Fences and Gates |
0 |
IFC Specs |
4/23/2018 |
32 32 23 |
Segmental Retaining Walls |
0 |
IFC Specs |
4/23/2018 |
32 92 00 |
Turf and Grasses |
0 |
IFC Specs |
4/23/2018 |
33 05 00 |
Common Work Results for Utilities |
0 |
IFC Specs |
4/23/2018 |
33 41 00 |
Storm Utility Drainage Piping |
0 |
IFC Specs |
4/23/2018 |
33 46 00 |
Subdrainage |
0 |
IFC Specs |
4/23/2018 |
33 93 00 |
Storm-Sanitary Manholes |
0 |
IFC Specs |
4/23/2018 |
40 05 13 74 |
PVC and CPVC Piping |
0 |
Issue for Bid |
10/12/2018 |
40 05 13 77 |
PP Piping |
A |
BOD Issue |
2/8/2018 |
40 53 10 |
Piping Fabrication, Installation, and Testing |
0 |
Issue for Bid |
1/11/2018 |
40 53 10.01_dat |
Process Piping Data Sheet |
1 |
Issue for Bid |
10/12/2018 |
40 53 10.02_dat |
Process Valve Data Sheet |
1 |
Issue for Bid |
10/12/2018 |
40 53 10.11 |
Copper Tubing |
0 |
Pricing Issue |
8/31/2018 |
40 53 10.20 |
Stainless Steel Piping |
0 |
PQ007-9&11 |
9/7/2018 |
40 53 10.21 |
Stainless Steel Tubing |
1 |
PQ007-9&11 |
9/7/2018 |
40 53 10.30 |
Carbon Steel Pipe |
0 |
Pricing Issue |
8/31/2018 |
40 53 10.77 |
Polypropylene Pipe |
B |
Pricing Issue |
8/31/2018 |
40 61 13 |
Process Control Syste, (PCS) Specification |
B |
A101 Bid Package Addendum |
10/24/2018 |
40 90 00_01 |
Process Instrument List |
B |
A101 Bid Package Addendum |
10/24/2018 |
40 90 00_02 |
Process Control System Input/Output List |
B |
A101 Bid Package Documents |
10/4/2018 |
40 90 00_03 |
Environment Monitoring System Input.Output List |
B |
A101 Bid Package Addendum |
10/24/2018 |
40 90 10 |
Instrumentation & Control Components Furnished with Equipment |
A |
PQ007-9&11 |
9/7/2018 |
40 90 11.01 |
Pressure Indicator Transmitter (Sanitary) Data Sheet |
A |
A101 Bid Package Documents |
10/4/2018 |
40 90 11.02 |
Pressure Indicator Transmitter (Standard) Data Sheet |
A |
A101 Bid Package Documents |
10/4/2018 |
40 90 11.03 |
Differential Pressure indicator Transmitter Data Sheet |
A |
A101 Bid Package Documents |
10/4/2018 |
40 90 15.07_OFCA |
Sequence of Operation, Oil-free Compressed Air |
0 |
PQ007-9&11 |
9/7/2018 |
40 90 15.08_PW1 |
Sequence of Operation, Process Waste 1 |
A |
PQ0013-0018 |
9/20/2018 |
40 90 15.09_PW2 |
Sequence of Operation, Process Waste 2 |
A |
PQ0013-0018 |
9/20/2018 |
40 90 20.01 |
Temperature Transmitter with RTD (Standard Specification) |
A |
A101 Bid Package Documents |
10/4/2018 |
40 90 20.02 |
Temperature Transmitter with RTD (Sanitary Specification) |
A |
A101 Bid Package Documents |
10/4/2018 |
40 90 20.04 |
Environment Monitoring System (EMS) Specification |
B |
A101 Bid Package Addendum |
10/24/2018 |
40 90 30.01 |
Level Indicator Transmitter (D/P Type) Data Sheet |
A |
A101 Bid Package Documents |
10/4/2018 |
40 90 31.01 |
Guided Wave Radar Level Indicator Transmitter Data Sheet |
A |
A101 Bid Package Documents |
10/4/2018 |
40 90 50_01 |
Weight Transmitter with Load Cells Specification |
A |
Issue for Bid |
10/12/2018 |
40 90 50_02 |
Weight scale with Transmitter Specifications (Floor Scale) |
A |
Issue for Bid |
10/12/2018 |
40 90 50_03 |
Weight Scale Transmitter Specifications (Bench Scale) |
A |
Issue for Bid |
10/12/2018 |
42 10 10 |
Heat Exchangers |
0 |
Pricing Issue |
8/31/2018 |
42 10 10.01 _dat |
Heat Exchanger Data Sheet |
0 |
Pricing Issue |
8/31/2018 |
43 12 10 |
Clean Dry Air System |
A |
PQ007-9&11 |
9/7/2018 |
43 12 10 01 _dat |
Clean Dry Air System Data Sheets |
A |
PQ007-9&11 |
9/7/2018 |
43 12 10 01_SIT |
Clean Dry Air System Submittal, Inspection and Testing (SIT) Form |
A |
PQ007-9&11 |
9/7/2018 |
1/30/2019 |
CONFIDENTIAL |
. |
Athenex GMP Specificatio |
Exhibit 2 (p. 5 of 5) |
Spec No. |
Name |
Rev |
Set Name |
Issuance Date |
43 21 00 |
Process Pumps |
0 |
Issue for Bid |
10/12/2018 |
43 21 00.01_dat |
Centrifugal Pump Data Sheets |
0 |
Pricing Issue |
8/31/2018 |
43 21 00.06_dat |
AODD Pump Data Sheets |
0 |
Pricing Issue |
8/31/2018 |
43 21 00.07_dat |
Waste Transfer Unit Data Sheets |
0 |
PQ0013-0018 |
9/20/2018 |
43 21 00.07_sit |
Waste Transfer Unit Submittal, Inspection, and Testing (SIT) Form |
0 |
PQ0013-0018 |
9/20/2018 |
43 41 16 |
Plastic Tanks |
0 |
PQ0013-0018 |
9/20/2018 |
43 41 16.01 _dat |
Plastic Tanks Data Sheet |
0 |
Process Spec Review II- 1 of 2 |
8/1/2018 |
45 53 01 01 |
General Requirements for Biopharm Equipment |
0 |
PQ0013-0018 |
9/20/2018 |
45 53 01 10 |
Submittals, Inspections, and Testing Requirements |
0 |
PQ0013-0018 |
9/20/2018 |
45 53 12 01 |
Biopharm Centrifugal Pump |
0 |
PQ0013-0018 |
9/20/2018 |
45 53 12 03_dat |
Peristaltic Pump Data Sheet |
A |
Pricing Issue |
8/31/2018 |
45 53 12 03_SIT |
Peristaltic Pump Submittals, Inspection, and Testing (SIT) Form |
A |
Pricing Issue |
8/31/2018 |
45 53 12.03 |
Peristaltic Pump |
A |
Pricing Issue |
8/31/2018 |
45 53 15 01 |
Biopharm Vessels |
0 |
PQ0013-0018 |
9/20/2018 |
45 53 15 01._SIT |
Biopharm Vessels Submittals, Inspection, and Testing (SIT) Form |
A |
PQ007-9&11 |
9/7/2018 |
45 53 15 01.dat |
Biopharm Vessels Data Sheet |
1 |
PQ007-9&11 |
9/7/2018 |
45 53 17 11 |
Biopharm Magnetic Drive Mixer |
A |
PQ007-9&11 |
9/7/2018 |
45 53 17 11_dat |
Biopharm Magnetic Drive Mixer Datasheet |
A |
PQ007-9&11 |
9/7/2018 |
45 53 19 01_SIT |
Transfer Panels Submittals, Inspection, and Testing (SIT) Form |
A |
PQ007-9&11 |
9/7/2018 |
45 53 19 05 |
Utility Panels |
A |
PQ007-9&11 |
9/7/2018 |
45 53 19 05._SIT |
Utility Panels Submittals, Inspection, and Testing (SIT) Form |
A |
PQ007-9&11 |
9/7/2018 |
45 53 19 05.dat |
Utility Panels Data Sheet |
1 |
PQ007-9&11 |
9/7/2018 |
45 53 19.01 |
Transfer Panels |
A |
PQ007-9&11 |
9/7/2018 |
45 53 19.01.dat |
Transfer Panels Data Sheet |
A |
PQ007-9&11 |
9/7/2018 |
45 53 19.21 |
Mix-Proof Valve Manifold |
0 |
PQ0013-0018 |
9/20/2018 |
45 53 19.21_dat |
Mix-Proof Valve Manifold Data Sheet |
0 |
PQ0013-0018 |
9/20/2018 |
45 53 19.21_SIT |
Mix-Proof Valve Manifold Submittals, Inspection, and Testing (SIT) Form |
0 |
PQ0013-0018 |
9/20/2018 |
45 53 21 01 |
Biopharm Shell and Tube Heat Exchangers |
0 |
PQ0013-0018 |
9/20/2018 |
45 53 21 01.dat |
Biopharm Shell and Tube Heat Exchangers Data Sheet |
A |
Process Spec Review II- 1 of 2 |
8/1/2018 |
45 53 21 01_SIT |
Biopharm Shell and Tube Heat Exchangers Submittals, Inspection, and Testing (SIT) For |
A |
Process Spec Review II- 1 of 2 |
8/1/2018 |
45 53 21 51 |
Temperature Control Unit Skid Assembly |
A |
PQ007-9&11 |
9/7/2018 |
45 53 21 51_SIT |
Temperature Control Unit Skid Assembly Submittals, Inspection, and Testing (SIT) Form |
A |
PQ007-9&11 |
9/7/2018 |
45 53 21.16 |
Biopharm Point of Use Heat Exchanger |
0 |
Pricing Issue |
8/31/2018 |
45 53 21.16_dat |
Biopharm Point of Use Heat Exchanger Data Sheet |
0 |
Pricing Issue |
8/31/2018 |
45 53 21.16_SIT |
Biopharm Point of Use Heat Exchanger Submittals, Inspection, and Testing (SIT) Form |
0 |
Pricing Issue |
8/31/2018 |
00 00 00.00.00_dat |
Temperature Control Unit Skid Assembly Data Sheet |
0 |
PQ007-9&11 |
9/7/2018 |
45 53 25 02 |
Hygenic Cartridge Filters |
1 |
PQ0013-0018 |
9/20/2018 |
45 53 25 02.dat |
Hygenic Cartridge Filters Data Sheet |
A |
Pricing Issue |
8/31/2018 |
45 53 25 02_SIT |
Hygenic Cartridge Filters Data Sheet Submittals, Inspection, and Testing (SIT) Form |
A |
Pricing Issue |
8/31/2018 |
45 53 54 11 |
GMP Parts Washer / Dryer |
0 |
PQ001-PQ003 |
8/10/2018 |
45 53 54 11_dat |
GMP Parts Washer / Dryer Data Sheet |
2 |
AddendumtoProcessSpecUpdates |
11/26/2018 |
45 53 54 11_SIT |
GMP Parts Washer / Dryer Data Sheet Submittals, Inspection, and Testing (SIT) Form |
0 |
PQ001-PQ003 |
8/10/2018 |
45 53 54.01 |
Clean in Place Skid |
0 |
PQ0013-0018 |
9/20/2018 |
45 53 54.01_dat |
Clean in Place Skid Data Sheet |
0 |
PQ0013-0018 |
9/20/2018 |
45 53 54.01_SIT |
Clean in Place Skid Submittals, Inspection, and Testing (SIT) Form |
0 |
PQ0013-0018 |
9/20/2018 |
45 53 55 01 |
GMP Autoclave |
0 |
PQ001-PQ003 |
8/10/2018 |
45 53 55 01_SIT |
GMP Autoclave Data Sheet Submittals, Inspection, and Testing (SIT) Form |
0 |
PQ001-PQ003 |
8/10/2018 |
45 53 55.01 dat |
GMP Autoclave Data Sheet |
0 |
PQ001-PQ003 |
8/10/2018 |
45 53 61 22 |
WFI Vapor Compression Still |
0 |
PQ005-PQ006 |
8/20/2018 |
45 53 61 22.dat |
WFI Vapor Compression Still Data Sheet |
0 |
PQ005-PQ006 |
8/20/2018 |
45 53 61 22_SIT |
WFI Vapor Compression Still Submittals, Inspection, and Testing (SIT) Form |
0 |
PQ005-PQ006 |
8/20/2018 |
45 53 61.31 |
Pure Steam Generator |
0 |
PQ001-PQ003 |
8/10/2018 |
45 53 61.31_dat |
Pure Steam Generator Data Sheet |
0 |
PQ001-PQ003 |
8/10/2018 |
45 53 61.31_SIT |
Pure Steam Generator Submittals, Inspection, and Testing (SIT) Form |
0 |
PQ001-PQ003 |
8/10/2018 |
45 53 61.41 |
Compendial Water Storage and Distribution |
0 |
PQ005-PQ006 |
8/20/2018 |
45 53 61.41_dat |
Compendial Water Storage and Distribution Data Sheet |
1 |
PQ005-PQ006 |
8/20/2018 |
45 53 61.41_SIT |
Compendial Water Storage and Distribution Submittals, Inspection, and Testing (SIT) Fo |
0 |
PQ005-PQ006 |
8/20/2018 |
45 53 65 16 |
Water Pretreatment Skid |
0 |
PQ005-PQ006 |
8/20/2018 |
45 53 65 16.dat |
Water Pretreatment Skid Data Sheet |
0 |
PQ005-PQ006 |
8/20/2018 |
45 53 65 16_SIT |
Water Pretreatment Skid Submittals, Inspection, and Testing (SIT) Form |
0 |
PQ005-PQ006 |
8/20/2018 |
45 53 97.60 |
pH Neutralization System |
0 |
PQ0013-0018 |
9/20/2018 |
45 53 97.60_dat |
pH Neutralization System_Data Sheet |
0 |
PQ0013-0018 |
9/20/2018 |
45 53 97.60_SIT |
pH Neutralization System Submittals, Inspection, and Testing (SIT) Form |
0 |
PQ0013-0018 |
9/20/2018 |
1/30/2019 |
CONFIDENTIAL |
. |
Athenex GMP Drawing List |
Exhibit 3 (p. 1 of 20) |
Sheet Name |
Rev |
Set Name |
Issuance Date |
|
1-CS-001 |
GENERAL PROJECT COVER SHEET - VOLUME 1 |
2 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-CS-002 |
GENERAL PROJECT DRAWING LIST - VOLUME 1 |
2 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-CS-003 |
GENERAL PROJECT COVER SHEET - VOLUME 2 |
2 |
Bulletin0021-MechanicalUpdates |
Dec 14, 2018 12:00 AM |
1-CS-004 |
GENERAL PROJECT DRAWING LIST - VOLUME 2 |
2 |
Bulletin0021-MechanicalUpdates |
Dec 14, 2018 12:00 AM |
1-CS-005 |
GENERAL PROJECT COVER SHEET - VOLUME 3 |
2 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-CS-006 |
GENERAL PROJECT DRAWING LIST - VOLUME 3 |
2 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-CS-007 |
GENERAL PROJECT COVER SHEET - VOLUME 4 |
2 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-CS-008 |
GENERAL PROJECT DRAWING LIST - VOLUME 4 |
2 |
Bulletin0024-Electrical |
Jan 11, 2019 12:00 AM |
1-CS-010 |
GENERAL PROJECT SITE AND BUILDING LOCATION PLANS |
2 |
Bulletin0024-Electrical |
Jan 11, 2019 12:00 AM |
1/13/2019
Athenex GMP Drawing List |
Exhibit 3 (p. 2 of 20) |
Sheet Name |
Rev |
Set Name |
Issuance Date |
|
1-G-010 |
GENERAL PHASING DIAGRAM - FIRST FLOOR |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-G-020 |
GENERAL PHASING DIAGRAM - SECOND FLOOR |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-G-100 |
GENERAL BUILDING CODE ANALYSIS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-G-110 |
GENERAL LIFE SAFETY AND BUILDING CODE COMPLIANCE PLANS - FIRST |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-G-115 |
GENERAL LIFE SAFETY AND BUILDING CODE COMPLIANCE PLANS - |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-G-120 |
GENERAL LIFE SAFETY AND BUILDING CODE COMPLIANCE PLANS - SECOND |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-G-130 |
GENERAL TRAVEL DISTANCE DIAGRAM - FIRST FLOOR NORTH |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-G-131 |
GENERAL TRAVEL DISTANCE DIAGRAM - FIRST FLOOR SOUTH |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-G-132 |
GENERAL TRAVEL DISTANCE DIAGRAM - SECOND FLOOR NORTH |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-G-133 |
GENERAL TRAVEL DISTANCE DIAGRAM - SECOND FLOOR SOUTH |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-G-310 |
GENERAL SECOND FLOOR FRAMING PLAN - FIREPROOFING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-G-320 |
GENERAL ROOF FRAMING PLAN - FIREPROOFING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1/13/2019
Athenex GMP Drawing List |
Exhibit 3 (p. 3 of 20) |
Sheet Name |
Rev |
Set Name |
Issuance Date |
|
C-000 |
GENERAL NOTES, LEGEND AND SHEET LAYOUT |
0 |
Bulletin 0006 - R10 |
Sep 12, 2018 12:00 AM |
C-100 |
EXISTING CONDITIONS DEMOLITION SITE PLAN |
- |
Bulletin 0006 - R10 |
Sep 12, 2018 12:00 AM |
C-200 |
OVERALL SITE PLAN |
14 |
Bulletin 0022 - Struct & Civil |
Jan 3, 2019 12:00 AM |
C-201 |
PROPOSED SITE PLAN |
14 |
Bulletin 0022 - Struct & Civil |
Jan 3, 2019 12:00 AM |
C-202 |
PROPOSED SITE PLAN |
14 |
Bulletin 0022 - Struct & Civil |
Jan 3, 2019 12:00 AM |
C-203 |
PROPOSED GRADING PLAN |
12 |
Bulletin 0015 - Civil Update |
Nov 1, 2018 12:00 AM |
C-204 |
PROPOSED GRADING PLAN |
12 |
Bulletin 0014 - Civil & Structural |
Oct 29, 2018 12:00 AM |
C-205 |
PROPOSED UTILITY PLAN |
12 |
Bulletin 0014 - Civil & Structural |
Oct 29, 2018 12:00 AM |
C-206 |
PROPOSED UTILITY PLAN |
12 |
Bulletin 0014 - Civil & Structural |
Oct 29, 2018 12:00 AM |
C-207 |
PROPOSED UTILITY PLAN |
0 |
Bulletin 0006 - R10 |
Sep 12, 2018 12:00 AM |
C-208 |
PROPOSED SANITARY SEWER SITE PLAN AND PROFILE VIEW |
0 |
Bulletin 0006 - R10 |
Sep 12, 2018 12:00 AM |
C-209 |
PROPOSED PERIMETER DRIVEWAY ALIGNMENT |
0 |
Bulletin 0006 - R10 |
Sep 12, 2018 12:00 AM |
C-210 |
PROPOSED PERIMETER DRIVEWAY PROFILES |
0 |
Bulletin 0006 - R10 |
Sep 12, 2018 12:00 AM |
C-211 |
PROPOSED STORM MANAGEMENT FACILITY PONDS |
0 |
Bulletin 0006 - R10 |
Sep 12, 2018 12:00 AM |
C-212 |
PROPOSED LIGHTING PLAN |
- |
Civil-Addendum Info_R7 |
Mar 8, 2018 12:00 AM |
C-300 |
GENERAL NOTES, LEGEND AND SHEET LAYOUT |
0 |
Civil-FrozenScope/Town |
Jan 19, 2018 12:00 AM |
C-301 |
MISCELLANEOUS DETAILS |
0 |
Bulletin 0006 - R10 |
Sep 12, 2018 12:00 AM |
C-302 |
MISCELLANEOUS DETAILS |
12 |
Bulletin 0014 - Civil & Structural |
Oct 29, 2018 12:00 AM |
C-303 |
MISCELLANEOUS DETAILS |
11 |
Bulletin 0011 |
Oct 12, 2018 12:00 AM |
C-304 |
MISCELLANEOUS DETAILS |
0 |
Bulletin 0006 - R10 |
Sep 12, 2018 12:00 AM |
C-305 |
MAINTENANCE AND PROTECTION OF TRAFFIC |
0 |
Bulletin 0006 - R10 |
Sep 12, 2018 12:00 AM |
C-306 |
LANDSCAPE DETAILS |
0 |
Bulletin 0006 - R10 |
Sep 12, 2018 12:00 AM |
Survey |
Topographic Survey |
J |
Civil-Site Plan Submission_R5 |
Feb 9, 2018 12:00 AM |
1/13/2019
Athenex GMP Drawing List |
Exhibit 3 (p. 4 of 21) |
Sheet No. |
Sheet Name |
Rev |
Set Name |
Issuance Date |
1-S-101 |
STRUCTURAL GENERAL NOTES |
1 |
Bulletin 0018 - Structural Updates |
Nov 28, 2018 12:00 AM |
1-S-102 |
STRUCTURAL GENERAL NOTES CONTINUED |
0 |
Structural Steel Issue |
May 23, 2018 12:00 AM |
1-S-103 |
STRUCTURAL SCHEDULE OF SPECIAL INSPECTIONS FOR BUILDING |
0 |
Structural Steel Issue |
May 23, 2018 12:00 AM |
1-S-104 |
STRUCTURAL SECOND FLOOR FRAMING PLAN - DESIGN LOADS |
1 |
Structural Steel Issue |
May 23, 2018 12:00 AM |
1-S-105 |
STRUCTURAL ROOF PLAN - DESIGN LOADS |
1 |
Structural Steel Issue |
May 23, 2018 12:00 AM |
1-S-106 |
STRUCTURAL FRAMING PLAN STEEL AND DECK PAINTING |
0 |
Structural Steel Issue |
May 23, 2018 12:00 AM |
1-S-210A |
STRUCTURAL FOUNDATION PLAN - SECTOR A |
9 |
Bulletin 0018 - Structural Updates |
Nov 28, 2018 12:00 AM |
1-S-210B |
STRUCTURAL FOUNDATION PLAN - SECTOR B |
4 |
Bulletin 0007 - Structural Revisions |
Jul 27, 2018 12:00 AM |
1-S-210C |
STRUCTURAL FOUNDATION PLAN - SECTOR C |
5 |
Bulletin 0018 - Structural Updates |
Nov 28, 2018 12:00 AM |
1-S-210D |
STRUCTURAL FOUNDATION PLAN - SECTOR D |
7 |
Bulletin 0018 - Structural Updates |
Nov 28, 2018 12:00 AM |
1-S-210E |
STRUCTURAL FOUNDATION PLAN - SECTOR E |
5 |
Bulletin 0018 - Structural Updates |
Nov 28, 2018 12:00 AM |
1-S-210F |
STRUCTURAL FOUNDATION PLAN - SECTOR F |
3 |
Bulletin 0007 - Structural Revisions |
Jul 27, 2018 12:00 AM |
1-S-210G |
STRUCTURAL FOUNDATION PLAN - SECTOR G |
5 |
Bulletin 0010 - Structural Updates |
Sep 20, 2018 12:00 AM |
1-S-210H |
STRUCTURAL FOUNDATION PLAN - SECTOR H |
7 |
Bulletin 0010 - Structural Updates |
Sep 20, 2018 12:00 AM |
1-S-210J |
STRUCTURAL FOUNDATION PLAN - SECTOR J |
9 |
Bulletin 0018 - Structural Updates |
Nov 28, 2018 12:00 AM |
1-S-211 |
STRUCTURAL FOUNDATION PLAN - EQUIPMENT YARD |
1 |
Bulletin 0016 - Structural Revisions |
Nov 9, 2018 12:00 AM |
1-S-212 |
STRUCTURAL FOUNDATION PLAN - TRUCK RAMPS |
0 |
Bulletin 0016 - Structural Revisions |
Nov 9, 2018 12:00 AM |
1-S-214A |
STRUCTURAL FIRST FLOOR KNEE WALL PLAN - SECTOR A |
0 |
Bulletin 0018 - Structural Updates |
Nov 28, 2018 12:00 AM |
1-S-215 |
STRUCTURAL INTERSTITIAL FLOOR FRAMING PLAN |
2 |
Bulletin 0008 - Structural Revisions |
Aug 15, 2018 12:00 AM |
1-S-220A |
STRUCTURAL SECOND FLOOR FRAMING PLAN - SECTOR A |
6 |
Bulletin 0023 - Structural Updates Sector A |
Jan 09, 2019 12:00AM |
1-S-220B |
STRUCTURAL SECOND FLOOR FRAMING PLAN - SECTOR B |
3 |
Bulletin 0018 - Structural Updates |
Nov 28, 2018 12:00 AM |
1-S-220C |
STRUCTURAL SECOND FLOOR FRAMING PLAN - SECTOR C |
3 |
Bulletin 0018 - Structural Updates |
Nov 28, 2018 12:00 AM |
1-S-220D |
STRUCTURAL SECOND FLOOR FRAMING PLAN - SECTOR D |
5 |
Bulletin 0022 - Struct & Civil Updates |
Jan 01, 2019 12:00AM |
1-S-220E |
STRUCTURAL SECOND FLOOR FRAMING PLAN - SECTOR E |
5 |
Bulletin 0022 - Struct & Civil Updates |
Jan 01, 2019 12:00AM |
1-S-220F |
STRUCTURAL SECOND FLOOR FRAMING PLAN - SECTOR F |
3 |
Bulletin 0018 - Structural Updates |
Nov 28, 2018 12:00 AM |
1-S-220G |
STRUCTURAL SECOND FLOOR FRAMING PLAN - SECTOR G |
1 |
Bulletin 0018 - Structural Updates |
Nov 28, 2018 12:00 AM |
1-S-220H |
STRUCTURAL SECOND FLOOR FRAMING PLAN - SECTOR H |
3 |
Bulletin 0018 - Structural Updates |
Nov 28, 2018 12:00 AM |
1-S-220J |
STRUCTURAL SECOND FLOOR FRAMING PLAN - SECTOR J |
5 |
Bulletin 0022 - Struct & Civil Updates |
Jan 01, 2019 12:00AM |
1-S-221 |
STRUCTURAL PIPE RACK FRAMING PLAN |
2 |
Bulletin 0007 - Structural Revisions |
Jul 27, 2018 12:00 AM |
1-S-222 |
STRUCTURAL HUNG PIPE RACK FRAMING PLAN |
0 |
Bulletin 0005 - Foundation |
Jun 19, 2018 12:00 AM |
1-S-231 |
STRUCTURAL ROOF FRAMING PLAN - SECTOR A, B, E, F, G |
8 |
Bulletin 0022 - Struct & Civil Updates |
Jan 01, 2019 12:00AM |
1-S-232 |
STRUCTURAL ROOF FRAMING PLAN - SECTOR C, D, H, J |
5 |
Bulletin 0022 - Struct & Civil Updates |
Jan 01, 2019 12:00AM |
1-S-233 |
STRUCTURAL PARTIAL ROOF FRAMING PLANS |
6 |
Bulletin 0018 - Structural Updates |
Nov 28, 2018 12:00 AM |
1-S-234 |
STRUCTURAL LOBBY ROOF FRAMING PLAN AND SECTIONS |
4 |
Bulletin 0018 - Structural Updates |
Nov 28, 2018 12:00 AM |
1-S-235 |
STRUCTURAL VESTIBULE ROOF FRAMING PLAN AND SECTIONS |
2 |
Bulletin 0022 - Struct & Civil Updates |
Jan 01, 2019 12:00AM |
1-S-236 |
STRUCTURAL VESTIBULE ROOF FRAMING PLAN, SECTIONS AND DETAILS |
1 |
Bulletin 0018 - Structural Updates |
Nov 28, 2018 12:00 AM |
1-S-237 |
STRUCTURAL VESTIBULE ROOF FRAMING PLAN, SECTIONS AND DETAILS |
2 |
Bulletin 0023 - Structural Updates Sector A |
Jan 09, 2019 12:00AM |
1-S-301 |
STRUCTURAL FOUNDATION SECTIONS AND DETAILS |
4 |
Bulletin 0007 - Structural Revisions |
Jul 27, 2018 12:00 AM |
1-S-302 |
STRUCTURAL FOUNDATION SECTIONS AND DETAILS |
3 |
Bulletin 0005 - Foundation |
Jun 19, 2018 12:00 AM |
1-S-303 |
STRUCTURAL FOUNDATION SECTIONS AND DETAILS |
5 |
Bulletin 0010 - Structural Updates |
Sep 20, 2018 12:00 AM |
1-S-304 |
STRUCTURAL FOUNDATION SECTIONS AND DETAILS |
7 |
Bulletin 0018 - Structural Updates |
Nov 28, 2018 12:00 AM |
1-S-401 |
STRUCTURAL CMU WALL PLAN - SECTOR A,B,E,F,G |
1 |
Bulletin 0022 - Struct & Civil Updates |
Jan 01, 2019 12:00AM |
1-S-402 |
STRUCTURAL CMU WAL PLAN - SECTOR C,D,H,J |
1 |
Bulletin 0022 - Struct & Civil Updates |
Jan 01, 2019 12:00AM |
1-S-403 |
STRUCTURAL MASONRY WALL SECTIONS |
1 |
Bulletin 0022 - Struct & Civil Updates |
Jan 01, 2019 12:00AM |
1-S-404 |
STRUCTURAL MASONRY WALL SECTIONS AND DETAILS |
0 |
Bulletin 0018 - Structural Updates |
Nov 28, 2018 12:00 AM |
1-S-501 |
STRUCTURAL BRACED FRAME ELEVATIONS |
2 |
Bulletin 0008 - Structural Revisions |
Aug 15, 2018 12:00 AM |
1-S-502 |
STRUCTURAL BRACED FRAME ELEVATIONS |
2 |
Bulletin 0012 - Structural Updates |
Oct 3, 2018 12:00 AM |
1-S-503 |
STRUCTURAL COLUMN SCHEDULE |
1 |
Bulletin 0005 - Foundation |
Jun 19, 2018 12:00 AM |
1-S-504 |
STRUCTURAL BASE PLATE DETAILS AND SCHEDULES |
1 |
Bulletin 0010 - Structural Updates |
Sep 20, 2018 12:00 AM |
1-S-505 |
STRUCTURAL FRAMING SECTIONS AND DETAILS |
3 |
Bulletin 0018 - Structural Updates |
Nov 28, 2018 12:00 AM |
1-S-506 |
STRUCTURAL EXTERIOR WALL FRAMING ELEVATIONS |
1 |
Bulletin 0013 - Girt Framing at Sector E |
Oct 22, 2018 12:00 AM |
1-S-507 |
STRUCTURAL EXTERIOR WALL FRAMING SECTIONS AND DETAILS |
0 |
Bulletin 0007 - Structural Revisions |
Jul 27, 2018 12:00 AM |
1-S-508 |
STRUCTURAL EXTERIOR WALL FRAMING SECTIONS AND DETAILS |
2 |
Bulletin 0007 - Structural Revisions |
Jul 27, 2018 12:00 AM |
1-S-509 |
STRUCTURAL FRAMING SECTIONS AND DETAILS |
4 |
Bulletin 0018 - Structural Updates |
Nov 28, 2018 12:00 AM |
1-S-510 |
STRUCTURAL FRAMING SECTIONS AND DETAILS |
2 |
Bulletin 0022 - Struct & Civil Updates |
Jan 01, 2019 12:00AM |
1-S-511 |
STRUCTURAL EXTERIOR WALL FRAMING SECTIONS AND DETAILS |
0 |
Bulletin 0009 - Structural Revisions |
Aug 29, 2018 12:00 AM |
1-S-512 |
STRUCTURAL EXTERIOR WALL FRAMING SECTIONS AND DETAILS |
3 |
Bulletin 0018 - Structural Updates |
Nov 28, 2018 12:00 AM |
1-S-513 |
STRUCTURAL FRAMING SECTIONS AND DETAILS |
2 |
Bulletin 0018 - Structural Updates |
Nov 28, 2018 12:00 AM |
1-S-514 |
STRUCTURAL FRAMING SECTIONS AND DETAILS |
2 |
Bulletin 0022 - Struct & Civil Updates |
Jan 01, 2019 12:00AM |
1-S-515 |
STRUCTURAL LOBBY STAIR FRAMING PLAN, SECTIONS AND DETAILS |
0 |
Bulletin 0012 - Structural Updates |
Oct 3, 2018 12:00 AM |
1-S-516 |
STRUCTURAL FRAMING SECTIONS AND DETAILS |
1 |
Bulletin 0022 - Struct & Civil Updates |
Jan 01, 2019 12:00AM |
1-S-517 |
STRUCTURAL FRAMING SECTIONS AND DETAILS |
0 |
Bulletin 0017 - Structural Update |
Nov 13, 2018 12:00 AM |
1-S-518 |
STRUCTURAL FRAMING SECTIONS AND DETAILS |
0 |
Bulletin 0023 - Structural Updates Sector A |
Jan 09, 2019 12:00AM |
Athenex GMP Drawing List |
Exhibit 3 (p. 5 of 21) |
Sheet No. |
Sheet Name |
Rev |
Set Name |
Issuance Date |
1-A-000 |
ARCHITECTURAL FLOOR PLAN NOTES, LEGENDS, AND ABBREVIATIONS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-100 |
ARCHITECTURAL SITE PLAN |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-210 |
ARCHITECTURAL FIRST FLOOR PLAN - EDGE OF SLAB |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-211 |
ARCHITECTURAL FIRST FLOOR PLAN - BUILDING ENVELOPE |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-212 |
ARCHITECTURAL FIRST FLOOR PLAN - BUILDING ENVELOPE - NORTH |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-213 |
ARCHITECTURAL FIRST FLOOR PLAN - BUILDING ENVELOPE - SOUTH |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-214 |
ARCHITECTURAL FIRST FLOOR PLAN |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-214 Defer |
ARCHITECTURAL FIRST FLOOR PLAN 1-A-214_RJ_Notes_25OCT18 |
0 |
Deferred Scope Mark-up |
Oct 25, 2018 12:00 AM |
1-A-214A |
ARCHITECTURAL FIRST FLOOR PLAN - SECTOR A |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-214B |
ARCHITECTURAL FIRST FLOOR PLAN - SECTOR B |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-214C |
ARCHITECTURAL FIRST FLOOR PLAN - SECTOR C |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-214D |
ARCHITECTURAL FIRST FLOOR PLAN - SECTOR D |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-214E |
ARCHITECTURAL FIRST FLOOR PLAN - SECTOR E |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-214F |
ARCHITECTURAL FIRST FLOOR PLAN - SECTOR F |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-214G |
ARCHITECTURAL FIRST FLOOR PLAN - SECTOR G |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-214H |
ARCHITECTURAL FIRST FLOOR PLAN - SECTOR H |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-214J |
ARCHITECTURAL FIRST FLOOR PLAN - SECTOR J |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-215 |
ARCHITECTURAL INTERSTITIAL LEVEL ONE PLAN |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-215F |
ARCHITECTURAL INTERSTITIAL LEVEL ONE PLAN - SECTOR F |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-215H |
ARCHITECTURAL INTERSTITIAL LEVEL ONE PLAN - SECTOR H |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-215J |
ARCHITECTURAL INTERSTITIAL LEVEL ONE PLAN - SECTOR J |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-220 |
ARCHITECTURAL SECOND FLOOR PLAN - EDGE OF SLAB |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-221 |
ARCHITECTURAL SECOND FLOOR PLAN - BUILDING ENVELOPE |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-222 |
ARCHITECTURAL SECOND FLOOR PLAN - BUILDING ENVELOPE - NORTH |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-223 |
ARCHITECTURAL SECOND FLOOR PLAN - BUILDING ENVELOPE - SOUTH |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-224 |
ARCHITECTURAL SECOND FLOOR PLAN |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-224 Defer |
ARCHITECTURAL FIRST FLOOR PLAN 1-A-224_RJ_Notes_22OCT18 |
0 |
Deferred Scope Mark-up |
Oct 22, 2018 12:00 AM |
1-A-224A |
ARCHITECTURAL SECOND FLOOR PLAN - SECTOR A |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-224B |
ARCHITECTURAL SECOND FLOOR PLAN - SECTOR B |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-224C |
ARCHITECTURAL SECOND FLOOR PLAN - SECTOR C |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-224D |
ARCHITECTURAL SECOND FLOOR PLAN - SECTOR D |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-224E |
ARCHITECTURAL SECOND FLOOR PLAN - SECTOR E |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-224F |
ARCHITECTURAL SECOND FLOOR PLAN - SECTOR F |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-224G |
ARCHITECTURAL SECOND FLOOR PLAN - SECTOR G |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-224H |
ARCHITECTURAL SECOND FLOOR PLAN - SECTOR H |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-224J |
ARCHITECTURAL SECOND FLOOR PLAN - SECTOR J |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-225H |
ARCHITECTURAL INTERSTITIAL LEVEL TWO PLAN - SECTOR H |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-230 |
ARCHITECTURAL ROOF PLAN |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-231 |
ARCHITECTURAL ROOF PLANS - LOBBY, STAIRS AND ENTRANCE CANOPIES |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-301 |
ARCHITECTURAL EXTERIOR ELEVATIONS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-302 |
ARCHITECTURAL ENLARGED EXTERIOR ELEVATIONS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-310 |
ARCHITECTURAL METAL PANEL TYPE PLAN DIAGRAM |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-311 |
ARCHITECTURAL METAL PANEL TYPE 1 LAYOUT |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-311A |
ARCHITECTURAL METAL PANEL TYPE 1 LAYOUT |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-312 |
ARCHITECTURAL METAL PANEL TYPE 2 LAYOUT |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-313 |
ARCHITECTURAL METAL PANEL TYPE 3 LAYOUT |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-314 |
ARCHITECTURAL METAL PANEL TYPE 3 LAYOUT |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-320 |
ARCHITECTURAL CURTAIN WALL TYPES |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-321 |
ARCHITECTURAL CURTAIN WALL TYPES |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-322 |
ARCHITECTURAL CURTAIN WALL DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-323 |
ARCHITECTURAL CURTAIN WALL DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-324 |
ARCHITECTURAL CURTAIN WALL DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-325 |
ARCHITECTURAL STOREFRONT TYPES AND DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-326 |
ARCHITECTURAL LOUVER TYPES AND DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-327 |
ARCHITECTURAL EXTERIOR DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-400 |
ARCHITECTURAL STAIR PLANS AND SECTIONS - AS1 & BS1 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-401 |
ARCHITECTURAL STAIR PLANS AND SECTION - DS1 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-402 |
ARCHITECTURAL STAIR PLANS AND SECTION - DS2 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-403 |
ARCHITECTURAL STAIR PLANS AND SECTION - ES1 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-404 |
ARCHITECTURAL STAIR PLANS AND SECTION - ES2 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-405 |
ARCHITECTURAL STAIR PLANS AND SECTION - HS1 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-406 |
ARCHITECTURAL STAIR PLANS AND SECTION - JS1 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-407 |
ARCHITECTURAL STAIR PLANS AND SECTION - JS2 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-408 |
ARCHITECTURAL STAIR PLANS AND SECTIONS - GROUND FLOOR |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-409 |
ARCHITECTURAL STAIR PLANS, SECTIONS AND DETAILS - EXTERIOR STAIRS AND |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-410 |
ARCHITECTURAL STAIR AND RAIL DETAILS |
0 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-411 |
ARCHITECTURAL STAIR PLANS AND SECTIONS - INTERSTITIAL LEVEL & SECOND FLOOR |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-412 |
ARCHITECTURAL STAIR AND RAIL DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-420 |
ARCHITECTURAL ENLARGED LOBBY PLANS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-421 |
ARCHITECTURAL LOBBY STAIR SECTIONS AND DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-422 |
ARCHITECTURAL ENLARGED LOBBY REFLECTIVE CEILING PLAN & DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-430 |
ARCHITECTURAL PASSENGER ELEVATOR PLANS, SECTIONS AND DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-431 |
ARCHITECTURAL FREIGHT ELEVATOR PLANS, SECTIONS AND DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-432 |
ARCHITECTURAL ELEVATOR DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-440 |
ARCHITECTURAL ENLARGED VESTIBULE PLANS, SECTIONS AND DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-450 |
ARCHITECTURAL ENLARGED TOILET ROOM PLANS AND ELEVATIONS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-451 |
ARCHITECTURAL ENLARGED TOILET ROOM PLANS AND ELEVATIONS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-452 |
ARCHITECTURAL ENLARGED TOILET ROOM PLANS AND ELEVATIONS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-453 |
ARCHITECTURAL ENLARGED TOILET ROOM PLANS AND ELEVATIONS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-454 |
ARCHITECTURAL ENLARGED TOILET ROOM PLANS, ELEVATIONS AND SCHEDULE |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
Athenex GMP Drawing List |
Exhibit 3 (p. 6 of 20) |
Sheet No. |
Sheet Name |
Rev |
Set Name |
Issuance Date |
1-A-460 |
ARCHITECTURAL ENLARGED LOCKER ROOM PLANS AND ELEVATIONS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-461 |
ARCHITECTURAL ENLARGED LOCKER ROOM PLANS AND ELEVATIONS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-462 |
ARCHITECTURAL ENLARGED LOCKER ROOM PLANS AND ELEVATIONS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-470 |
ARCHITECTURAL ENLARGED GOWNING ROOM PLANS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-471 |
ARCHITECTURAL ENLARGED GOWNING ROOM PLANS, ELEVATION AND SCHEDULE |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-480 |
ARCHITECTURAL ENLARGED DENSITY STORAGE PLANS AND ELEVATIONS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-500 |
ARCHITECTURAL LAB STANDARDS AND DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-501 |
ARCHITECTURAL LAB STANDARDS AND DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-502 |
ARCHITECTURAL OVERHEAD UTILITY PANELS DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-510 |
ARCHITECTURAL ENLARGED LAB FLOOR PLANS AND ELEVATIONS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-511 |
ARCHITECTURAL ENLARGED LAB FLOOR PLANS AND ELEVATIONS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-512 |
ARCHITECTURAL ENLARGED LAB FLOOR PLANS AND ELEVATIONS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-513 |
ARCHITECTURAL ENLARGED LAB FLOOR PLANS AND ELEVATIONS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-514 |
ARCHITECTURAL ENLARGED LAB FLOOR PLANS AND ELEVATIONS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-515 |
ARCHITECTURAL ENLARGED LAB, STORAGE FLOOR PLANS AND ELEVATIONS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-614 |
ARCHITECTURAL FIRST FLOOR REFLECTED CEILING PLAN |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-614A |
ARCHITECTURAL FIRST FLOOR REFLECTED CEILING PLAN - SECTOR A |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-614B |
ARCHITECTURAL FIRST FLOOR REFLECTED CEILING PLAN - SECTOR B |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-614C |
ARCHITECTURAL FIRST FLOOR REFLECTED CEILING PLAN - SECTOR C |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-614D |
ARCHITECTURAL FIRST FLOOR REFLECTED CEILING PLAN - SECTOR D |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-614E |
ARCHITECTURAL FIRST FLOOR REFLECTED CEILING PLAN - SECTOR E |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-614F |
ARCHITECTURAL FIRST FLOOR REFLECTED CEILING PLAN - SECTOR F |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-614G |
ARCHITECTURAL FIRST FLOOR REFLECTED CEILING PLAN - SECTOR G |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-614H |
ARCHITECTURAL FIRST FLOOR REFLECTED CEILING PLAN - SECTOR H |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-614J |
ARCHITECTURAL FIRST FLOOR REFLECTED CEILING PLAN - SECTOR J |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-624 |
ARCHITECTURAL SECOND FLOOR REFLECTED CEILING PLAN |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-624A |
ARCHITECTURAL SECOND FLOOR REFLECTED CEILING PLAN - SECTOR A |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-624B |
ARCHITECTURAL SECOND FLOOR REFLECTED CEILING PLAN - SECTOR B |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-624C |
ARCHITECTURAL SECOND FLOOR REFLECTED CEILING PLAN - SECTOR C |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-624D |
ARCHITECTURAL SECOND FLOOR REFLECTED CEILING PLAN - SECTOR D |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-624E |
ARCHITECTURAL SECOND FLOOR REFLECTED CEILING PLAN - SECTOR E |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-624F |
ARCHITECTURAL SECOND FLOOR REFLECTED CEILING PLAN - SECTOR F |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-624G |
ARCHITECTURAL SECOND FLOOR REFLECTED CEILING PLAN - SECTOR G |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-624H |
ARCHITECTURAL SECOND FLOOR REFLECTED CEILING PLAN - SECTOR H |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-624J |
ARCHITECTURAL SECOND FLOOR REFLECTED CEILING PLAN - SECTOR J |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-710 |
ARCHITECTURAL PARTITION TYPES |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-712 |
ARCHITECTURAL PARTITION DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-713 |
ARCHITECTURAL PARTITION DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-714 |
ARCHITECTURAL PARTITION DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-715 |
ARCHITECTURAL WALL PROTECTION AND PARTITION DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-720 |
ARCHITECTURAL DOOR SCHEDULE AND DETAILS - BUILDING ENVELOPE |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-721 |
ARCHITECTURAL DOOR SCHEDULE - SECTOR A |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-722 |
ARCHITECTURAL DOOR SCHEDULE - SECTOR B, C, D |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-723 |
ARCHITECTURAL DOOR SCHEDULE - SECTOR E, F, G |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-724 |
ARCHITECTURAL DOOR SCHEDULE - SECTOR H |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-725 |
ARCHITECTURAL DOOR SCHEDULE - SECTOR J |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-726 |
ARCHITECTURAL DOOR DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-727 |
ARCHITECTURAL DOOR DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-728 |
ARCHITECTURAL INTERIOR STOREFRONT SYSTEM ELEVATIONS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-730 |
ARCHITECTURAL INTERIOR DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-731 |
ARCHITECTURAL INTERIOR DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-740 |
ARCHITECTURAL FINISH SCHEDULE |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-741 |
ARCHITECTURAL FINISH SCHEDULE |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-742 |
ARCHITECTURAL FINISH LEGEND AND DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-750 |
ARCHITECTURAL FIRST FLOOR FINISH PLAN - SECTOR A |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-751 |
ARCHITECTURAL FIRST FLOOR FINISH PLAN - SECTOR D, E, F, J |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-752 |
ARCHITECTURAL SECOND FLOOR FINISH PLAN - SECTOR A, H |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-760 |
ARCHITECTURAL FIRST FLOOR FURNITURE PLAN |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-761 |
ARCHITECTURAL FIRST FLOOR FURNITURE PLAN - SECTOR A |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-762 |
ARCHITECTURAL FIRST FLOOR FURNITURE PLAN - SECTOR D, E, F, G, J |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-770 |
ARCHITECTURAL SECOND FLOOR FURNITURE PLAN |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-771 |
ARCHITECTURAL SECOND FLOOR FURNITURE PLAN - SECTOR A, D, H |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-810 |
ARCHITECTURAL WALL SECTIONS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-811 |
ARCHITECTURAL WALL SECTIONS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-812 |
ARCHITECTURAL WALL SECTIONS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-813 |
ARCHITECTURAL WALL SECTIONS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-814 |
ARCHITECTURAL WALL SECTIONS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-815 |
ARCHITECTURAL WALL SECTIONS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-816 |
ARCHITECTURAL WALL SECTIONS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-817 |
ARCHITECTURAL WALL SECTIONS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-818 |
ARCHITECTURAL WALL SECTIONS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-820 |
ARCHITECTURAL WALL SECTION DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-821 |
ARCHITECTURAL WALL SECTION DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-822 |
ARCHITECTURAL WALL SECTION DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-823 |
ARCHITECTURAL WALL SECTION DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-824 |
ARCHITECTURAL WALL SECTION DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-825 |
ARCHITECTURAL WALL SECTION DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-827 |
ARCHITECTURAL WALL SECTION DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-830 |
ARCHITECTURAL EXTERIOR PLAN DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-831 |
ARCHITECTURAL EXTERIOR PLAN DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
Athenex GMP Drawing List |
Exhibit 3 (p. 7 of 20) |
Athenex GMP Drawing List
Sheet No. |
Sheet Name |
Rev |
Set Name |
Issuance Date |
1-A-832 |
ARCHITECTURAL EXTERIOR PLAN DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-833 |
ARCHITECTURAL EXTERIOR PLAN DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-834 |
ARCHITECTURAL EXTERIOR PLAN DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-835 |
ARCHITECTURAL EXTERIOR PLAN DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-841 |
ARCHITECTURAL ROOF DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-911 |
ARCHITECTURAL INTERIOR WALL SECTIONS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-920 |
ARCHITECTURAL MILLWORK DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-921 |
ARCHITECTURAL MILLWORK DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-922 |
ARCHITECTURAL MILLWORK DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-923 |
ARCHITECTURAL MILLWORK DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-924 |
ARCHITECTURAL INTERIOR ELEVATIONS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-925 |
ARCHITECTURAL INTERIOR ELEVATIONS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-A-940 |
ARCHITECTURAL INTERIOR SIGNAGE DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
Athenex GMP Drawing List |
Exhibit 3 (p. 8 of 20) |
Sheet Name |
Rev |
Set Name |
Issuance Date |
|
1-M-001 |
MECHANICAL COVER SHEET |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-011 |
MECHANICAL FIRST FLOOR PLAN - AHU ZONING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-011A |
MECHANICAL FIRST FLOOR PLAN - SECTOR A - AHU ZONING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-011B |
MECHANICAL FIRST FLOOR PLAN - SECTOR B - AHU ZONING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-011C |
MECHANICAL FIRST FLOOR PLAN - SECTOR C - AHU ZONING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-011D |
MECHANICAL FIRST FLOOR PLAN - SECTOR D - AHU ZONING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-011E |
MECHANICAL FIRST FLOOR PLAN - SECTOR E - AHU ZONING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-011F |
MECHANICAL FIRST FLOOR PLAN - SECTOR F - AHU ZONING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-011G |
MECHANICAL FIRST FLOOR PLAN - SECTOR G - AHU ZONING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-011H |
MECHANICAL FIRST FLOOR PLAN - SECTOR H - AHU ZONING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-011J |
MECHANICAL FIRST FLOOR PLAN - SECTOR J - AHU ZONING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-012 |
MECHANICAL SECOND FLOOR PLAN - AHU ZONING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-012A |
MECHANICAL SECOND FLOOR PLAN - SECTOR A - AHU ZONING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-012D |
MECHANICAL SECOND FLOOR PLAN - SECTOR D - AHU ZONING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-012H |
MECHANICAL SECOND FLOOR PLAN - SECTOR H - AHU ZONING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-012J |
MECHANICAL SECOND FLOOR PLAN - SECTOR J - AHU ZONING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-021 |
MECHANICAL FIRST FLOOR PLAN - EXHAUST ZONING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-021A |
MECHANICAL FIRST FLOOR PLAN - SECTOR A - EXHAUST ZONING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-021C |
MECHANICAL FIRST FLOOR PLAN - SECTOR C - EXHAUST ZONING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-021D |
MECHANICAL FIRST FLOOR PLAN - SECTOR D - EXHAUST ZONING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-021E |
MECHANICAL FIRST FLOOR PLAN - SECTOR E - EXHAUST ZONING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-021F |
MECHANICAL FIRST FLOOR PLAN - SECTOR F - EXHAUST ZONING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-021G |
MECHANICAL FIRST FLOOR PLAN - SECTOR G - EXHAUST ZONING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-021H |
MECHANICAL FIRST FLOOR PLAN - SECTOR H - EXHAUST ZONING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-021J |
MECHANICAL FIRST FLOOR PLAN - SECTOR J - EXHAUST ZONING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-022 |
MECHANICAL SECOND FLOOR PLAN - EXHAUST ZONING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-022A |
MECHANICAL SECOND FLOOR PLAN - SECTOR A - EXHAUST ZONING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-022B |
MECHANICAL SECOND FLOOR PLAN - SECTOR B - EXHAUST ZONING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-022D |
MECHANICAL SECOND FLOOR PLAN - SECTOR D - EXHAUST ZONING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-022E |
MECHANICAL SECOND FLOOR PLAN - SECTOR E - EXHAUST ZONING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-022H |
MECHANICAL SECOND FLOOR PLAN - SECTOR H - EXHAUST ZONING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-022J |
MECHANICAL SECOND FLOOR PLAN - SECTOR J - EXHAUST ZONING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-031A |
MECHANICAL FIRST FLOOR PLAN - SECTOR A - PRESSURIZATION |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-031B |
MECHANICAL FIRST FLOOR PLAN - SECTOR B - PRESSURIZATION |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-031C |
MECHANICAL FIRST FLOOR PLAN - SECTOR C - PRESSURIZATION |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-031D |
MECHANICAL FIRST FLOOR PLAN - SECTOR D - PRESSURIZATION |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-031F |
MECHANICAL FIRST FLOOR PLAN - SECTOR F - PRESSURIZATION |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-031G |
MECHANICAL FIRST FLOOR PLAN - SECTOR G - PRESSURIZATION |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-031H |
MECHANICAL FIRST FLOOR PLAN - SECTOR H - PRESSURIZATION |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-031J |
MECHANICAL FIRST FLOOR PLAN - SECTOR J - PRESSURIZATION |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-032D |
MECHANICAL SECOND FLOOR PLAN - SECTOR D - PRESSURIZATION |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-032H |
MECHANICAL SECOND FLOOR PLAN - SECTOR H - PRESSURIZATION |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-032J |
MECHANICAL SECOND FLOOR PLAN - SECTOR J - PRESSURIZATION |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-210 |
MECHANICAL FIRST FLOOR PLAN - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-210A1 |
MECHANICAL FIRST FLOOR PLAN - SECTOR A1 - DUCTWORK |
2 |
Bulletin 0021 - Mechanical Updates |
Dec 18, 2018 12:00 AM |
1-M-210A2 |
MECHANICAL FIRST FLOOR PLAN - SECTOR A2 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-210A3 |
MECHANICAL FIRST FLOOR PLAN - SECTOR A3 - DUCTWORK |
2 |
Bulletin 0021 - Mechanical Updates |
Dec 18, 2018 12:00 AM |
1-M-210A4 |
MECHANICAL FIRST FLOOR PLAN - SECTOR A4 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-210B1 |
MECHANICAL FIRST FLOOR PLAN - SECTOR B1 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-210B2 |
MECHANICAL FIRST FLOOR PLAN - SECTOR B2 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-210C1 |
MECHANICAL FIRST FLOOR PLAN - SECTOR C1 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-210C2 |
MECHANICAL FIRST FLOOR PLAN - SECTOR C2 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-210C4 |
MECHANICAL FIRST FLOOR PLAN - SECTOR C4 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-210D1 |
MECHANICAL FIRST FLOOR PLAN - SECTOR D1 - DUCTWORK |
2 |
Bulletin 0021 - Mechanical Updates |
Dec 18, 2018 12:00 AM |
1-M-210D2 |
MECHANICAL FIRST FLOOR PLAN - SECTOR D2 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-210D3 |
MECHANICAL FIRST FLOOR PLAN - SECTOR D3 - DUCTWORK |
2 |
Bulletin 0021 - Mechanical Updates |
Dec 18, 2018 12:00 AM |
1-M-210D4 |
MECHANICAL FIRST FLOOR PLAN - SECTOR D4 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-210D5 |
MECHANICAL FIRST FLOOR PLAN - SECTOR D5 - DUCTWORK |
2 |
Bulletin 0021 - Mechanical Updates |
Dec 18, 2018 12:00 AM |
1-M-210D6 |
MECHANICAL FIRST FLOOR PLAN - SECTOR D6 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-210E1 |
MECHANICAL FIRST FLOOR PLAN - SECTOR E1 - DUCTWORK |
2 |
Bulletin 0021 - Mechanical Updates |
Dec 18, 2018 12:00 AM |
1-M-210E2 |
MECHANICAL FIRST FLOOR PLAN - SECTOR E2 - DUCTWORK |
2 |
Bulletin 0021 - Mechanical Updates |
Dec 18, 2018 12:00 AM |
1-M-210F1 |
MECHANICAL FIRST FLOOR PLAN - SECTOR F1 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-210F2 |
MECHANICAL FIRST FLOOR PLAN - SECTOR F2 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-210F3 |
MECHANICAL FIRST FLOOR PLAN - SECTOR F3 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-210F4 |
MECHANICAL FIRST FLOOR PLAN - SECTOR F4 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-210G1 |
MECHANICAL FIRST FLOOR PLAN - SECTOR G1 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-210G2 |
MECHANICAL FIRST FLOOR PLAN - SECTOR G2 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-210H1 |
MECHANICAL FIRST FLOOR PLAN - SECTOR H1 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-210H2 |
MECHANICAL FIRST FLOOR PLAN - SECTOR H2 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-210H3 |
MECHANICAL FIRST FLOOR PLAN - SECTOR H3 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-210H4 |
MECHANICAL FIRST FLOOR PLAN - SECTOR H4 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-210J1 |
MECHANICAL FIRST FLOOR PLAN - SECTOR J1 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-210J2 |
MECHANICAL FIRST FLOOR PLAN - SECTOR J2 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-210J3 |
MECHANICAL FIRST FLOOR PLAN - SECTOR J3 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-210J4 |
MECHANICAL FIRST FLOOR PLAN - SECTOR J4 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-220 |
MECHANICAL SECOND FLOOR PLAN - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-220A1 |
MECHANICAL SECOND FLOOR PLAN - SECTOR A1 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-220A2 |
MECHANICAL SECOND FLOOR PLAN - SECTOR A2 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-220A3 |
MECHANICAL SECOND FLOOR PLAN - SECTOR A3 - DUCTWORK |
2 |
Bulletin 0021 - Mechanical Updates |
Dec 18, 2018 12:00 AM |
1-M-220B1 |
MECHANICAL SECOND FLOOR PLAN - SECTOR B1 - DUCTWORK |
2 |
Bulletin 0021 - Mechanical Updates |
Dec 18, 2018 12:00 AM |
1-M-220B2 |
MECHANICAL SECOND FLOOR PLAN - SECTOR B2 - DUCTWORK |
2 |
Bulletin 0021 - Mechanical Updates |
Dec 18, 2018 12:00 AM |
1-M-220C1 |
MECHANICAL SECOND FLOOR PLAN - SECTOR C1 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-220C2 |
MECHANICAL SECOND FLOOR PLAN - SECTOR C2 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-220C3 |
MECHANICAL SECOND FLOOR PLAN - SECTOR C3 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-220C4 |
MECHANICAL SECOND FLOOR PLAN - SECTOR C4 - DUCTWORK |
2 |
Bulletin 0021 - Mechanical Updates |
Dec 18, 2018 12:00 AM |
1-M-220D2 |
MECHANICAL SECOND FLOOR PLAN - SECTOR D2 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1/13/2019
Athenex GMP Drawing List |
Exhibit 3 (p. 9 of 20) |
1-M-220D3 |
MECHANICAL SECOND FLOOR PLAN - SECTOR D3 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-220D4 |
MECHANICAL SECOND FLOOR PLAN - SECTOR D4 - DUCTWORK |
2 |
Bulletin 0021 - Mechanical Updates |
Dec 18, 2018 12:00 AM |
1-M-220D5 |
MECHANICAL SECOND FLOOR PLAN - SECTOR D5 - DUCTWORK |
2 |
Bulletin 0021 - Mechanical Updates |
Dec 18, 2018 12:00 AM |
1-M-220D6 |
MECHANICAL SECOND FLOOR PLAN - SECTOR D6 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-220E1 |
MECHANICAL SECOND FLOOR PLAN - SECTOR E1 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-220E2 |
MECHANICAL SECOND FLOOR PLAN - SECTOR E2 - DUCTWORK |
2 |
Bulletin 0021 - Mechanical Updates |
Dec 18, 2018 12:00 AM |
1-M-220F1 |
MECHANICAL SECOND FLOOR PLAN - SECTOR F1 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-220F2 |
MECHANICAL SECOND FLOOR PLAN - SECTOR F2 - DUCTWORK |
2 |
Bulletin 0021 - Mechanical Updates |
Dec 18, 2018 12:00 AM |
1-M-220F3 |
MECHANICAL SECOND FLOOR PLAN - SECTOR F3 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-220F4 |
MECHANICAL SECOND FLOOR PLAN - SECTOR F4 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-220G1 |
MECHANICAL SECOND FLOOR PLAN - SECTOR G1 - DUCTWORK |
2 |
Bulletin 0021 - Mechanical Updates |
Dec 18, 2018 12:00 AM |
1-M-220G2 |
MECHANICAL SECOND FLOOR PLAN - SECTOR G2 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-220H1 |
MECHANICAL SECOND FLOOR PLAN - SECTOR H1 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-220H2 |
MECHANICAL SECOND FLOOR PLAN - SECTOR H2 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-220H3 |
MECHANICAL SECOND FLOOR PLAN - SECTOR H3 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-220H4 |
MECHANICAL SECOND FLOOR PLAN - SECTOR H4 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-220J1 |
MECHANICAL SECOND FLOOR PLAN - SECTOR J1 - DUCTWORK |
2 |
Bulletin 0021 - Mechanical Updates |
Dec 18, 2018 12:00 AM |
1-M-220J2 |
MECHANICAL SECOND FLOOR PLAN - SECTOR J2 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-220J3 |
MECHANICAL SECOND FLOOR PLAN - SECTOR J3 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-220J4 |
MECHANICAL SECOND FLOOR PLAN - SECTOR J4 - DUCTWORK |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-230 |
MECHANICAL ROOF PLAN |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-310 |
MECHANICAL FIRST FLOOR PLAN - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-310A1 |
MECHANICAL FIRST FLOOR PLAN - SECTOR A1 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-310A2 |
MECHANICAL FIRST FLOOR PLAN - SECTOR A2 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-310A3 |
MECHANICAL FIRST FLOOR PLAN - SECTOR A3 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-310A4 |
MECHANICAL FIRST FLOOR PLAN - SECTOR A4 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-310B1 |
MECHANICAL FIRST FLOOR PLAN - SECTOR B1 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-310B2 |
MECHANICAL FIRST FLOOR PLAN - SECTOR B2 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-310C1 |
MECHANICAL FIRST FLOOR PLAN - SECTOR C1 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-310C2 |
MECHANICAL FIRST FLOOR PLAN - SECTOR C2 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-310C3 |
MECHANICAL FIRST FLOOR PLAN - SECTOR C3 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-310C4 |
MECHANICAL FIRST FLOOR PLAN - SECTOR C4 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-310D1 |
MECHANICAL FIRST FLOOR PLAN - SECTOR D1 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-310D2 |
MECHANICAL FIRST FLOOR PLAN - SECTOR D2 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-310D3 |
MECHANICAL FIRST FLOOR PLAN - SECTOR D3 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-310D4 |
MECHANICAL FIRST FLOOR PLAN - SECTOR D4 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-310D5 |
MECHANICAL FIRST FLOOR PLAN - SECTOR D5 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-310D6 |
MECHANICAL FIRST FLOOR PLAN - SECTOR D6 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-310E1 |
MECHANICAL FIRST FLOOR PLAN - SECTOR E1 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-310E2 |
MECHANICAL FIRST FLOOR PLAN - SECTOR E2 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-310F1 |
MECHANICAL FIRST FLOOR PLAN - SECTOR F1 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-310F2 |
MECHANICAL FIRST FLOOR PLAN - SECTOR F2 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-310F3 |
MECHANICAL FIRST FLOOR PLAN - SECTOR F3 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-310F4 |
MECHANICAL FIRST FLOOR PLAN - SECTOR F4 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-310G1 |
MECHANICAL FIRST FLOOR PLAN - SECTOR G1 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-310G2 |
MECHANICAL FIRST FLOOR PLAN - SECTOR G2 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-310H1 |
MECHANICAL FIRST FLOOR PLAN - SECTOR H1 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-310H2 |
MECHANICAL FIRST FLOOR PLAN - SECTOR H2 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-310H3 |
MECHANICAL FIRST FLOOR PLAN - SECTOR H3 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-310H4 |
MECHANICAL FIRST FLOOR PLAN - SECTOR H4 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-310J1 |
MECHANICAL FIRST FLOOR PLAN - SECTOR J1 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-310J2 |
MECHANICAL FIRST FLOOR PLAN - SECTOR J2 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-310J3 |
MECHANICAL FIRST FLOOR PLAN - SECTOR J3 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-310J4 |
MECHANICAL FIRST FLOOR PLAN - SECTOR J4 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-320 |
MECHANICAL SECOND FLOOR PLAN - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-320A1 |
MECHANICAL SECOND FLOOR PLAN - SECTOR A1 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-320A2 |
MECHANICAL SECOND FLOOR PLAN - SECTOR A2 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-320A3 |
MECHANICAL SECOND FLOOR PLAN - SECTOR A3 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-320B1 |
MECHANICAL SECOND FLOOR PLAN - SECTOR B1 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-320B2 |
MECHANICAL SECOND FLOOR PLAN - SECTOR B2 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-320C1 |
MECHANICAL SECOND FLOOR PLAN - SECTOR C1 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-320C2 |
MECHANICAL SECOND FLOOR PLAN - SECTOR C2 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-320C3 |
MECHANICAL SECOND FLOOR PLAN - SECTOR C3 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-320C4 |
MECHANICAL SECOND FLOOR PLAN - SECTOR C4 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-320D3 |
MECHANICAL SECOND FLOOR PLAN - SECTOR D3 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-320D4 |
MECHANICAL SECOND FLOOR PLAN - SECTOR D4 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-320D5 |
MECHANICAL SECOND FLOOR PLAN - SECTOR D5 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-320D6 |
MECHANICAL SECOND FLOOR PLAN - SECTOR D6 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-320E1 |
MECHANICAL SECOND FLOOR PLAN - SECTOR E1 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-320E2 |
MECHANICAL SECOND FLOOR PLAN - SECTOR E2 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-320F1 |
MECHANICAL SECOND FLOOR PLAN - SECTOR F1 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-320F2 |
MECHANICAL SECOND FLOOR PLAN - SECTOR F2 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-320F3 |
MECHANICAL SECOND FLOOR PLAN - SECTOR F3 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-320F4 |
MECHANICAL SECOND FLOOR PLAN - SECTOR F4 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-320G1 |
MECHANICAL SECOND FLOOR PLAN - SECTOR G1 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-320G2 |
MECHANICAL SECOND FLOOR PLAN - SECTOR G2 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-320H1 |
MECHANICAL SECOND FLOOR PLAN - SECTOR H1 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-320H2 |
MECHANICAL SECOND FLOOR PLAN - SECTOR H2 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-320H3 |
MECHANICAL SECOND FLOOR PLAN - SECTOR H3 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-320H4 |
MECHANICAL SECOND FLOOR PLAN - SECTOR H4 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-320J1 |
MECHANICAL SECOND FLOOR PLAN - SECTOR J1 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-320J3 |
MECHANICAL SECOND FLOOR PLAN - SECTOR J3 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-320J4 |
MECHANICAL SECOND FLOOR PLAN - SECTOR J4 - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-401 |
MECHANICAL ENLARGED FIRST FLOOR PLAN - EQUIPMENT YARD |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-402 |
MECHANICAL ENLARGED SECOND FLOOR PLAN - PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-403 |
MECHANICAL ENLARGED ROOF PLAN |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-411 |
MECHANICAL SECTIONS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-412 |
MECHANICAL SECTIONS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1/13/2019
Athenex GMP Drawing List |
Exhibit 3 (p. 10 of 20) |
1-M-413 |
MECHANICAL SECTIONS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-414 |
MECHANICAL SECTIONS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-415 |
MECHANICAL SECTIONS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-416 |
MECHANICAL DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-417 |
MECHANICAL DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-418 |
MECHANICAL DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-419 |
MECHANICAL SECTIONS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-501 |
MECHANICAL AIR FLOW DIAGRAM - AHU 100, 110, 120, 130, 140, 150 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-502 |
MECHANICAL AIR FLOW DIAGRAM - EF-100, 110, 120, 130, 300, 310, 200, 210, 220, |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-520 |
MECHANICAL AIR FLOW DIAGRAM - AHU 230 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-521 |
MECHANICAL AIR FLOW DIAGRAM - AHU 231 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-522 |
MECHANICAL AIR FLOW DIAGRAM - AHU 233 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-523 |
MECHANICAL AIR FLOW DIAGRAM - AHU 241 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-524 |
MECHANICAL AIR FLOW DIAGRAM - AHU 243, 245, 247, 249 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-525 |
MECHANICAL AIR FLOW DIAGRAM - AHU 250 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-526 |
MECHANICAL AIR FLOW DIAGRAM - AHU 251 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-527 |
MECHANICAL AIR FLOW DIAGRAM - AHU 260 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-528 |
MECHANICAL AIR FLOW DIAGRAM - AHU 262, 264 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-530 |
MECHANICAL AIR FLOW DIAGRAM - AHU 300 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-531 |
MECHANICAL AIR FLOW DIAGRAM - AHU 300 (CONTINUED), 302 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-532 |
MECHANICAL AIR FLOW DIAGRAM - AHU 301 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-533 |
MECHANICAL AIR FLOW DIAGRAM - AHU 301 (CONTINUED) |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-540 |
MECHANICAL AIR FLOW DIAGRAM - AHU 401, 402, 403, 420 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-541 |
MECHANICAL AIR FLOW DIAGRAM - IQC LAB |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-542 |
MECHANICAL AIR FLOW DIAGRAM - AHU 430, 500 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-550 |
MECHANICAL AIR FLOW DIAGRAM - AHU 510 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-551 |
MECHANICAL AIR FLOW DIAGRAM - AHU 520 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-552 |
MECHANICAL AIR FLOW DIAGRAM - AHU 541 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-553 |
MECHANICAL AIR FLOW DIAGRAM - AHU 540 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-554 |
MECHANICAL AIR FLOW DIAGRAM - AHU 540 (CONTINUED) |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-555 |
MECHANICAL AIR FLOW DIAGRAM - AHU 550, 551 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-556 |
MECHANICAL AIR FLOW DIAGRAM - AHU 570, 571, 580 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-557 |
MECHANICAL AIR FLOW DIAGRAM - MECHANICAL AND ELECTRICAL ROOMS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-558 |
MECHANICAL AIR FLOW DIAGRAM - FAN COIL UNITS AND MISCELLANEOUS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-601 |
MECHANICAL PIPING DIAGRAM - CONDENSER WATER SYSTEM |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-602 |
MECHANICAL PIPING DIAGRAM - PRIMARY CHILLED WATER SYSTEM |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-611 |
MECHANICAL PIPING DIAGRAM - PRIMARY CHILLED WATER SYSTEM |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-621 |
MECHANICAL PIPING DIAGRAM - SECONDARY CHILLED WATER SYSTEM |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-631 |
MECHANICAL PIPING DIAGRAM - PROCESS CHILLED WATER SYSTEM |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-641 |
MECHANICAL PIPING DIAGRAM - PROCESS CONDENSER WATER SYSTEM |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-651 |
MECHANICAL PIPING DIAGRAM - BOILER 401 - STEAM GENERATION |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-652 |
MECHANICAL PIPING DIAGRAM - BOILER 401 - FUEL SYSTEM |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-653 |
MECHANICAL PIPING DIAGRAM - BOILER 402 - STEAM GENERATION |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-654 |
MECHANICAL PIPING DIAGRAM - BOILER 402 - FUEL SYSTEM |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-655 |
MECHANICAL PIPING DIAGRAM - BOILER 403 - STEAM GENERATION |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-656 |
MECHANICAL PIPING DIAGRAM - BOILER 403 - FUEL SYSTEM |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-657 |
MECHANICAL PIPING DIAGRAM - SURGE TANK ST-401 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-658 |
MECHANICAL PIPING DIAGRAM - DEAERATOR DA-401 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-659 |
MECHANICAL PIPING DIAGRAM - BOILER BLOWDOWN SYSTEMS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-661 |
MECHANICAL PIPING DIAGRAM - STEAM DISTRIBUTION |
2 |
Bulletin 0021 - Mechanical Updates |
Dec 18, 2018 12:00 AM |
1-M-662 |
MECHANICAL PIPING DIAGRAM - STEAM DISTRIBUTION |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-663 |
MECHANICAL PIPING DIAGRAM - STEAM DISTRIBUTION |
2 |
Bulletin 0021 - Mechanical Updates |
Dec 18, 2018 12:00 AM |
1-M-664 |
MECHANICAL PIPING DIAGRAM - STEAM DISTRIBUTION |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-671 |
MECHANICAL PIPING DIAGRAM - HEATING HOT WATER SYSTEM |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-681 |
MECHANICAL PIPING DIAGRAM - GLYCOL HEATING HOT WATER SYSTEM - |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-682 |
MECHANICAL PIPING DIAGRAM - GLYCOL HEATING HOT WATER SYSTEM - |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-691 |
MECHANICAL HUMIDIFICATION STEAM SYSTEM - DISTRIBUTION |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-701 |
MECHANICAL DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-702 |
MECHANICAL DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-703 |
MECHANICAL DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-704 |
MECHANICAL DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-705 |
MECHANICAL DETAILS |
2 |
Bulletin 0021 - Mechanical Updates |
Dec 18, 2018 12:00 AM |
1-M-706 |
MECHANICAL DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-707 |
MECHANICAL DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-708 |
MECHANICAL DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-709 |
MECHANICAL DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-720 |
MECHANICAL DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-721 |
MECHANICAL DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-722 |
MECHANICAL DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-801 |
MECHANICAL SCHEDULES |
2 |
Bulletin 0021 - Mechanical Updates |
Dec 18, 2018 12:00 AM |
1-M-802 |
MECHANICAL SCHEDULES |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-803 |
MECHANICAL SCHEDULES |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-804 |
MECHANICAL SCHEDULES |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-805 |
MECHANICAL SCHEDULES |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-810 |
MECHANICAL SCHEDULES |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-811 |
MECHANICAL SCHEDULES |
2 |
Bulletin 0021 - Mechanical Updates |
Dec 18, 2018 12:00 AM |
1-M-812 |
MECHANICAL SCHEDULES |
2 |
Bulletin 0021 - Mechanical Updates |
Dec 18, 2018 12:00 AM |
1-M-901 |
MECHANICAL I&C COVER SHEET |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-902 |
MECHANICAL I&C DIAGRAM - BMS NETWORK RISER |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-910 |
MECHANICAL I&C DIAGRAM - TYPICAL CENTRAL AIR SYSTEMS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-920 |
MECHANICAL I&C DIAGRAM - TYPICAL AIR SYSTEMS GMP AREAS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-921 |
MECHANICAL I&C DIAGRAM - TYPICAL AIR SYSTEMS GMP AREAS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-922 |
MECHANICAL I&C DIAGRAM - TYPICAL TERMINAL AIR SYSTEMS GMP AREAS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-923 |
MECHANICAL I&C DIAGRAM - TYPICAL TERMINAL AIR SYSTEMS GMP AREAS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-924 |
MECHANICAL I&C DIAGRAM - TYPICAL TERMINAL AIR SYSTEMS GMP AREAS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-925 |
MECHANICAL I&C DIAGRAM - TYPICAL TERMINAL AIR SYSTEMS GMP AREAS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-926 |
MECHANICAL I&C DIAGRAM - TYPICAL TERMINAL AIR SYSTEMS GMP AREAS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-927 |
MECHANICAL I&C DIAGRAM - TYPICAL TERMINAL AIR SYSTEMS GMP AREAS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1/13/2019
Athenex GMP Drawing List |
Exhibit 3 (p. 11 of 20) |
1-M-928 |
MECHANICAL I&C DIAGRAM - TYPICAL TERMINAL AIR SYSTEMS GMP AREAS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-930 |
MECHANICAL I&C DIAGRAM - TYPICA AIR SYSTEMS OFFICE AREAS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-931 |
MECHANICAL I&C DIAGRAM - TYPICAL TERMINAL AIR SYSTEMS OFFICE AREAS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-932 |
MECHANICAL I&C DIAGRAM - TYPICAL TERMINAL AIR SYSTEMS OFFICE AREAS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-933 |
MECHANICAL I&C DIAGRAM - TYPICAL TERMINAL AIR SYSTEMS OFFICE AREAS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-940 |
MECHANICAL I&C DIAGRAM - TYPICAL AIR SYSTEMS WAREHOUSE AREAS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-941 |
MECHANICAL I&C DIAGRAM - TYPICAL SUPPORT AIR SYSTEM AREAS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-942 |
MECHANICAL I&C DIAGRAM - TYPICAL SUPPORT AIR SYSTEM AREAS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-943 |
MECHANICAL I&C DIAGRAM - TYPICAL SUPPORT AIR SYSTEM AREAS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-950 |
MECHANICAL I&C DIAGRAM - AIR SYSTEMS SPINE CORRIDOR AREA |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-951 |
MECHANICAL I&C DIAGRAM - AIR SYSTEMS LAB SUPPORT AREAS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-952 |
MECHANICAL I&C DIAGRAM - TYPICAL TERMINAL CHEMISTRY LAB AIR SYSTEMS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-953 |
MECHANICAL I&C DIAGRAM - CHEMISTRY LAB AIR SYSTEMS SUPPORT AREAS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-954 |
MECHANICAL I&C DIAGRAM - TYPICAL AIR SYSTEMS SUPPORT AREAS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-955 |
MECHANICAL I&C DIAGRAM - TYPICAL TERMINAL AIR SYSTEMS SUPPORT |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-956 |
MECHANICAL I&C DIAGRAM - TYPICAL AIR SYSTEMS SUPPORT AREAS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-957 |
MECHANICAL I&C DIAGRAM - TYPICAL TERMINAL AIR SYSTEMS SUPPORT |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-958 |
MECHANICAL I&C DIAGRAM - TYPICAL TERMINAL AIR SYSTEMS SUPPORT |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-959 |
MECHANICAL I&C DIAGRAM - CHILLER ROOM TERMINAL AIR SYSTEMS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-960 |
MECHANICAL I&C DIAGRAM - FAN COIL UNIT CONTROLS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-961 |
MECHANICAL I&C DIAGRAM - MISCELLANEOUS MONITORING AND CONTROLS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-970 |
MECHANICAL I&C DIAGRAM - CONDENSER WATER SYSTEM - GENERATION |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-971 |
MECHANICAL I&C DIAGRAM - CONDENSER WATER SYSTEM - DISTRIBUTION |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-972 |
MECHANICAL I&C DIAGRAM - PRIMARY CHILLED WATER SYSTEM |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-973 |
MECHANICAL I&C DIAGRAM - PROCESS CHILLED WATER SYSTEM |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-974 |
MECHANICAL I&C DIAGRAM - SECONDARY CHILLED WATER SYSTEM |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-975 |
MECHANICAL I&C DIAGRAM - PROCESS CONDENSER WATER SYSTEM |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-980 |
MECHANICAL I&C DIAGRAM - BOILER PLANT CONTROLS NETWORK INTERFACE |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-981 |
MECHANICAL I&C DIAGRAM - BOILER 401, 402, & 403 - STEAM GENERATION |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-982 |
MECHANICAL I&C DIAGRAM - BOILER 401, 402, & 403 - FUEL SYSTEM |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-983 |
MECHANICAL I&C DIAGRAM - SURGE TANK ST-401 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-984 |
MECHANICAL I&C DIAGRAM - DEAERATOR DA-401 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-985 |
MECHANICAL I&C DIAGRAM - HEATING HOT WATER SYSTEM |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-M-986 |
MECHANICAL I&C DIAGRAM - GLYCOL HEATING HOT WATER SYSTEM |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1/13/2019
Athenex GMP Drawing List |
Exhibit 3 (p. 12 of 20) |
Sheet Name |
Rev |
Set Name |
Issuance Date |
|
1-E-000 |
ELECTRICAL COVER SHEET |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-001 |
ELECTRICAL SITE PLAN - LIGHTING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-002 |
ELECTRICAL SITE PLAN - POWER |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-002A |
ELECTRICAL SITE PLAN - POWER |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-003 |
ELECTRICAL SITE PLAN - GROUNDING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-004 |
ELECTRICAL SITE PLAN - 115KV SUBSTATION |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-005 |
ELECTRICAL SITE PLAN - 115KV SUBSTATION - GROUNDING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-210A |
ELECTRICAL FIRST FLOOR PLAN - SECTOR A - LIGHTING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-210B |
ELECTRICAL FIRST FLOOR PLAN - SECTOR B - LIGHTING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-210C |
ELECTRICAL FIRST FLOOR PLAN - SECTOR C - LIGHTING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-210D |
ELECTRICAL FIRST FLOOR PLAN - SECTOR D - LIGHTING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-210E |
ELECTRICAL FIRST FLOOR PLAN - SECTOR E - LIGHTING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-210F |
ELECTRICAL FIRST FLOOR PLAN - SECTOR F - LIGHTING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-210G |
ELECTRICAL FIRST FLOOR PLAN - SECTOR G - LIGHTING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-210H |
ELECTRICAL FIRST FLOOR PLAN - SECTOR H - LIGHTING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-210J |
ELECTRICAL FIRST FLOOR PLAN - SECTOR J - LIGHTING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-215F |
ELECTRICAL INTERSTITIAL FLOOR PLAN - SECTOR F - LIGHTING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-215H |
ELECTRICAL INTERSTITIAL FLOOR PLAN - SECTOR H - LIGHTING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-215J |
ELECTRICAL INTERSTITIAL FLOOR PLAN - SECTOR J - LIGHTING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-220A |
ELECTRICAL SECOND FLOOR PLAN - SECTOR A - LIGHTING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-220B |
ELECTRICAL SECOND FLOOR PLAN - SECTOR B - LIGHTING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-220C |
ELECTRICAL SECOND FLOOR PLAN - SECTOR C - LIGHTING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-220D |
ELECTRICAL SECOND FLOOR PLAN - SECTOR D - LIGHTING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-220E |
ELECTRICAL SECOND FLOOR PLAN - SECTOR E - LIGHTING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-220F |
ELECTRICAL SECOND FLOOR PLAN - SECTOR F - LIGHTING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-220G |
ELECTRICAL SECOND FLOOR PLAN - SECTOR G - LIGHTING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-220H |
ELECTRICAL SECOND FLOOR PLAN - SECTOR H - LIGHTING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-220J |
ELECTRICAL SECOND FLOOR PLAN - SECTOR J - LIGHTING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-310A |
ELECTRICAL FIRST FLOOR PLAN - SECTOR A - POWER |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-310B |
ELECTRICAL FIRST FLOOR PLAN - SECTOR B - POWER |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-310C |
ELECTRICAL FIRST FLOOR PLAN - SECTOR C - POWER |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-310D |
ELECTRICAL FIRST FLOOR PLAN - SECTOR D - POWER |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-310E |
ELECTRICAL FIRST FLOOR PLAN - SECTOR E - POWER |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-310F |
ELECTRICAL FIRST FLOOR PLAN - SECTOR F - POWER |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-310G |
ELECTRICAL FIRST FLOOR PLAN - SECTOR G - POWER |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-310H |
ELECTRICAL FIRST FLOOR PLAN - SECTOR H - POWER |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-310J |
ELECTRICAL FIRST FLOOR PLAN - SECTOR J - POWER |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-315F |
ELECTRICAL INTERSTITIAL FLOOR PLAN - SECTOR F - POWER |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-315H |
ELECTRICAL INTERSTITIAL FLOOR PLAN - SECTOR H - POWER |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-315J |
ELECTRICAL INTERSTITIAL FLOOR PLAN - SECTOR J - POWER |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-320A |
ELECTRICAL SECOND FLOOR PLAN - SECTOR A - POWER |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-320B |
ELECTRICAL SECOND FLOOR PLAN - SECTOR B - POWER |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-320C |
ELECTRICAL SECOND FLOOR PLAN - SECTOR C - POWER |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-320D |
ELECTRICAL SECOND FLOOR PLAN - SECTOR D - POWER |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-320E |
ELECTRICAL SECOND FLOOR PLAN - SECTOR E - POWER |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-320F |
ELECTRICAL SECOND FLOOR PLAN - SECTOR F - POWER |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-320G |
ELECTRICAL SECOND FLOOR PLAN - SECTOR G - POWER |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-320H |
ELECTRICAL SECOND FLOOR PLAN - SECTOR H - POWER |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-320J |
ELECTRICAL SECOND FLOOR PLAN - SECTOR J - POWER |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-330 |
ELECTRICAL ROOF PLAN - NORTH - POWER & SYSTEMS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-331 |
ELECTRICAL ROOF PLAN - SOUTH - POWER & SYSTEMS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-410A |
ELECTRICAL FIRST FLOOR PLAN - SECTOR A - FIRE ALARM AND SYSTEMS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-410B |
ELECTRICAL FIRST FLOOR PLAN - SECTOR B - FIRE ALARM AND SYSTEMS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-410C |
ELECTRICAL FIRST FLOOR PLAN - SECTOR C - FIRE ALARM AND SYSTEMS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-410D |
ELECTRICAL FIRST FLOOR PLAN - SECTOR D - FIRE ALARM AND SYSTEMS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-410E |
ELECTRICAL FIRST FLOOR PLAN - SECTOR E - FIRE ALARM AND SYSTEMS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-410F |
ELECTRICAL FIRST FLOOR PLAN - SECTOR F - FIRE ALARM AND SYSTEMS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-410G |
ELECTRICAL FIRST FLOOR PLAN - SECTOR G - FIRE ALARM AND SYSTEMS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-410H |
ELECTRICAL FIRST FLOOR PLAN - SECTOR H - FIRE ALARM AND SYSTEMS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-410J |
ELECTRICAL FIRST FLOOR PLAN - SECTOR J - FIRE ALARM AND SYSTEMS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-411 |
ELECTRICAL FIRST FLOOR PLAN - NORTH - RACEWAY |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-412 |
ELECTRICAL FIRST FLOOR PLAN - SOUTH - RACEWAY |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-415F |
ELECTRICAL INTERSTITIAL FLOOR PLAN - SECTOR F - FIRE ALARM AND |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-415H |
ELECTRICAL INTERSTITIAL FLOOR PLAN - SECTOR H - FIRE ALARM AND |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-415J |
ELECTRICAL INTERSTITIAL FLOOR PLAN - SECTOR J - FIRE ALARM AND |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-420A |
ELECTRICAL SECOND FLOOR PLAN - SECTOR A - FIRE ALARM AND |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-420B |
ELECTRICAL SECOND FLOOR PLAN - SECTOR B - FIRE ALARM AND |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-420C |
ELECTRICAL SECOND FLOOR PLAN - SECTOR C - FIRE ALARM AND |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-420D |
ELECTRICAL SECOND FLOOR PLAN - SECTOR D - FIRE ALARM AND |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-420E |
ELECTRICAL SECOND FLOOR PLAN - SECTOR E - FIRE ALARM AND |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-420F |
ELECTRICAL SECOND FLOOR PLAN - SECTOR F - FIRE ALARM AND |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-420G |
ELECTRICAL SECOND FLOOR PLAN - SECTOR G - FIRE ALARM AND |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-420H |
ELECTRICAL SECOND FLOOR PLAN - SECTOR H - FIRE ALARM AND |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1/13/2019
Athenex GMP Drawing List |
Exhibit 3 (p. 13 of 20) |
Sheet No. |
Sheet Name |
Rev |
Set Name |
Issuance Date |
1-E-420J |
ELECTRICAL SECOND FLOOR PLAN - SECTOR J - FIRE ALARM AND |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-421 |
ELECTRICAL SECOND FLOOR PLAN - NORTH - RACEWAY |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-422 |
ELECTRICAL SECOND FLOOR PLAN - SOUTH - RACEWAY |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-501 |
ELECTRICAL SINGLE LINE DIAGRAM - UTILITY SUBSTATION |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-502 |
ELECTRICAL SINGLE LINE DIAGRAM - RELAY SCHEME |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-503 |
ELECTRICAL SINGLE LINE DIAGRAM - SECTOR D - MECH CUP |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-504 |
ELECTRICAL SINGLE LINE DIAGRAM - SECTOR D - MECH CUP |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-505 |
ELECTRICAL SINGLE LINE DIAGRAM - SECTOR D - PROCESS CUP |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-506 |
ELECTRICAL SINGLE LINE DIAGRAM - SECTOR D - PROCESS CUP |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-507 |
ELECTRICAL SINGLE LINE DIAGRAM - SECTOR D - PROCESS CUP |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-508 |
ELECTRICAL SINGLE LINE DIAGRAM - SECTOR D - PROCESS CUP |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-509 |
ELECTRICAL SINGLE LINE DIAGRAM - SECTOR J - PROCESS 1 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-510 |
ELECTRICAL SINGLE LINE DIAGRAM - SECTOR J - PROCESS 1 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-511 |
ELECTRICAL SINGLE LINE DIAGRAM - SECTOR J - PROCESS 1 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-512 |
ELECTRICAL SINGLE LINE DIAGRAM - SECTOR J - PROCESS 1 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-513 |
ELECTRICAL SINGLE LINE DIAGRAM - SECTOR E - ADMIN PROCESS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-514 |
ELECTRICAL SINGLE LINE DIAGRAM - SECTOR E - ADMIN PROCESS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-515 |
ELECTRICAL SINGLE LINE DIAGRAM - SECTOR E - ADMIN PROCESS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-516 |
ELECTRICAL SINGLE LINE DIAGRAM - SECTOR B - PROCESS 2 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-517 |
ELECTRICAL SINGLE LINE DIAGRAM - SECTOR B - PROCESS 2 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-518 |
ELECTRICAL SINGLE LINE DIAGRAM - SECTOR B - PROCESS 2 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-600 |
ELECTRICAL ENLARGED PLANS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-601 |
ELECTRICAL ENLARGED PLANS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-602 |
ELECTRICAL ENLARGED PLANS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-603 |
ELECTRICAL ENLARGED PLANS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-604 |
ELECTRICAL ENLARGED PLANS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-605 |
ELECTRICAL ENLARGED PLANS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-606 |
ELECTRICAL ENLARGED PLANS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-607 |
ELECTRICAL ENLARGED PLANS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-701 |
ELECTRICAL DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-701A |
ELECTRICAL DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-702 |
ELECTRICAL DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-703 |
ELECTRICAL DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-704 |
ELECTRICAL DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-705 |
ELECTRICAL DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-706 |
ELECTRICAL DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-707 |
ELECTRICAL DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-708 |
ELECTRICAL DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-709 |
ELECTRICAL DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-710 |
ELECTRICAL HAZARDOUS BOUNDARY DIAGRAM |
0 |
Bulletin0024-Electrical |
Jan 11, 2019 12:00 AM |
1-E-801 |
ELECTRICAL SCHEDULES |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-802 |
ELECTRICAL SCHEDULES |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-803 |
ELECTRICAL SCHEDULES |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-804 |
ELECTRICAL SCHEDULES |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-805 |
ELECTRICAL SCHEDULES |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-806 |
ELECTRICAL SCHEDULES |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-807 |
ELECTRICAL SCHEDULES |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-808 |
ELECTRICAL SCHEDULES |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-809 |
ELECTRICAL SCHEDULES |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-810 |
ELECTRICAL SCHEDULES |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-811 |
ELECTRICAL SCHEDULES |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-812 |
ELECTRICAL SCHEDULES |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-813 |
ELECTRICAL SCHEDULES |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-814 |
ELECTRICAL SCHEDULES |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-815 |
ELECTRICAL SCHEDULES |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-816 |
ELECTRICAL SCHEDULES |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-901 |
ELECTRICAL WIRING DIAGRAMS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-902 |
ELECTRICAL WIRING DIAGRAMS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-903 |
ELECTRICAL WIRING DIAGRAMS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-904 |
ELECTRICAL WIRING DIAGRAMS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-905 |
ELECTRICAL WIRING DIAGRAMS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-E-906 |
ELECTRICAL WIRING DIAGRAMS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1/13/2019
Athenex GMP Drawing List |
Exhibit 3 (p. 14 of 20) |
Sheet Name |
Rev |
Set Name |
Issuance Date |
|
1-P-000 |
PLUMBING COVER SHEET |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-200 |
PLUMBING UNDERGROUND PLAN - UTILITY PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-210 |
PLUMBING FIRST FLOOR - UTILITY PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-210A |
PLUMBING FIRST FLOOR PLAN - SECTOR A - UTILITY PIPING |
2 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-210B |
PLUMBING FIRST FLOOR PLAN - SECTOR B - UTILITY PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-210C |
PLUMBING FIRST FLOOR PLAN - SECTOR C - UTILITY PIPING |
2 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-210D |
PLUMBING FIRST FLOOR PLAN - SECTOR D - UTILITY PIPING |
2 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-210E |
PLUMBING FIRST FLOOR PLAN - SECTOR E - UTILITY PIPING |
2 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-210F |
PLUMBING FIRST FLOOR PLAN - SECTOR F - UTILITY PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-210G |
PLUMBING FIRST FLOOR PLAN - SECTOR G - UTILITY PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-210H |
PLUMBING FIRST FLOOR PLAN - SECTOR H - UTILITY PIPING |
2 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-210J |
PLUMBING FIRST FLOOR PLAN - SECTOR J - UTILITY PIPING |
2 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-220 |
PLUMBING SECOND FLOOR PLAN - UTILITY PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-220A |
PLUMBING SECOND FLOOR PLAN - SECTOR A - UTILITY PIPING |
2 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-220B |
PLUMBING SECOND FLOOR PLAN - SECTOR B - UTILITY PIPING |
2 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-220C |
PLUMBING SECOND FLOOR PLAN - SECTOR C - UTILITY PIPING |
2 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-220D |
PLUMBING SECOND FLOOR PLAN - SECTOR D - UTILITY PIPING |
2 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-220E |
PLUMBING SECOND FLOOR PLAN - SECTOR E - UTILITY PIPING |
2 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-220F |
PLUMBING SECOND FLOOR PLAN - SECTOR F - UTILITY PIPING |
2 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-220G |
PLUMBING SECOND FLOOR PLAN - SECTOR G - UTILITY PIPING |
2 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-220H |
PLUMBING SECOND FLOOR PLAN - SECTOR H - UTILITY PIPING |
2 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-220J |
PLUMBING SECOND FLOOR PLAN - SECTOR J - UTILITY PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-300 |
PLUMBING UNDERGROUND PLAN |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-300A |
PLUMBING UNDERGROUND PLAN - SECTOR A |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-300B |
PLUMBING UNDERGROUND PLAN - SECTOR B |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-300C |
PLUMBING UNDERGROUND PLAN - SECTOR C |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-300D |
PLUMBING UNDERGROUND PLAN - SECTOR D |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-300E |
PLUMBING UNDERGROUND PLAN - SECTOR E |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-300F |
PLUMBING UNDERGROUND PLAN - SECTOR F |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-300G |
PLUMBING UNDERGROUND PLAN - SECTOR G |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-300H |
PLUMBING UNDERGROUND PLAN - SECTOR H |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-300J |
PLUMBING UNDERGROUND PLAN - SECTOR J |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-310 |
PLUMBING FIRST FLOOR PLAN - DRAINAGE PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-310A |
PLUMBING FIRST FLOOR PLAN - SECTOR A - DRAINAGE PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-310B |
PLUMBING FIRST FLOOR PLAN - SECTOR B - DRAINAGE PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-310C |
PLUMBING FIRST FLOOR PLAN - SECTOR C - DRAINAGE PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-310D |
PLUMBING FIRST FLOOR PLAN - SECTOR D - DRAINAGE PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-310E |
PLUMBING FIRST FLOOR PLAN - SECTOR E - DRAINAGE PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-310F |
PLUMBING FIRST FLOOR PLAN - SECTOR F - DRAINAGE PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-310G |
PLUMBING FIRST FLOOR PLAN - SECTOR G - DRAINAGE PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-310H |
PLUMBING FIRST FLOOR PLAN - SECTOR H - DRAINAGE PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-310J |
PLUMBING FIRST FLOOR PLAN - SECTOR J - DRAINAGE PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-320 |
PLUMBING SECOND FLOOR PLAN - DRAINAGE PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-320A |
PLUMBING SECOND FLOOR PLAN - SECTOR A - DRAINAGE PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-320B |
PLUMBING SECOND FLOOR PLAN - SECTOR B - DRAINAGE PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-320C |
PLUMBING SECOND FLOOR PLAN - SECTOR C - DRAINAGE PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-320D |
PLUMBING SECOND FLOOR PLAN - SECTOR D - DRAINAGE PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-320E |
PLUMBING SECOND FLOOR PLAN - SECTOR E - DRAINAGE PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-320F |
PLUMBING SECOND FLOOR PLAN - SECTOR F - DRAINAGE PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-320G |
PLUMBING SECOND FLOOR PLAN - SECTOR G - DRAINAGE PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-320H |
PLUMBING SECOND FLOOR PLAN - SECTOR H - DRAINAGE PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-320J |
PLUMBING SECOND FLOOR PLAN - SECTOR J - DRAINAGE PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-330 |
PLUMBING ROOF PLAN - DRAINAGE PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-420 |
PLUMBING ENLARGED PLANS |
2 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-421 |
PLUMBING ENLARGED PLANS |
2 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-422 |
PLUMBING ENLARGED PLANS |
2 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-423 |
PLUMBING EXTERIOR FLOOR PLAN - UTILITY PIPING |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-430 |
PLUMBING ENLARGED PLANS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-431 |
PLUMBING ENLARGED PLANS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-510 |
PLUMBING DOMESTIC WATER FLOW DIAGRAM |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-511 |
PLUMBING DOMESTIC WATER FLOW DIAGRAM |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-512 |
PLUMBING DOMESTIC WATER FLOW DIAGRAM |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-513 |
PLUMBING DOMESTIC WATER FLOW DIAGRAM |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-514 |
PLUMBING GREY WATER FLOW DIAGRAM |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-515 |
PLUMBING NON-POTABLE WATER FLOW DIAGRAM |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-520 |
PLUMBING TEPID WATER FLOW DIAGRAM |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-521 |
PLUMBING TEPID WATER FLOW DIAGRAM |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-522 |
PLUMBING TEPID WATER FLOW DIAGRAM |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-530 |
PLUMBING PROCESS WATER FLOW DIAGRAM |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1/13/2019
Athenex GMP Drawing List |
Exhibit 3 (p. 15 of 20) |
Sheet No. |
Sheet Name |
Rev |
Set Name |
Issuance Date |
1-P-531 |
PLUMBING PROCESS WATER FLOW DIAGRAM |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-540 |
PLUMBING SANITARY RISER DIAGRAM |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-541 |
PLUMBING SANITARY RISER DIAGRAM |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-542 |
PLUMBING SANITARY RISER DIAGRAM |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-543 |
PLUMBING SANITARY RISER DIAGRAM |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-550 |
PLUMBING STORMWATER RISER DIAGRAM |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-551 |
PLUMBING STORMWATER RISER DIAGRAM |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-552 |
PLUMBING STORMWATER RISER DIAGRAM |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-553 |
PLUMBING STORMWATER RISER DIAGRAM |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-560 |
PLUMBING PROCESS WASTE RISER DIAGRAM - PW1 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-561 |
PLUMBING PROCESS WASTE RISER DIAGRAM - PW1 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-570 |
PLUMBING PROCESS WASTE RISER DIAGRAM - PW2 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-571 |
PLUMBING PROCESS WASTE RISER DIAGRAM - PW2 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-572 |
PLUMBING PROCESS WASTE RISER DIAGRAM - PW2 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-573 |
PLUMBING PROCESS WASTE RISER DIAGRAM - PW2 |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-580 |
PLUMBING NATURAL GAS FLOW DIAGRAM |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-701 |
PLUMBING DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-702 |
PLUMBING DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-703 |
PLUMBING DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-704 |
PLUMBING DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-705 |
PLUMBING DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-706 |
PLUMBING DETAILS |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-801 |
PLUMBING SCHEDULES |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-802 |
PLUMBING SCHEDULES |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-P-803 |
PLUMBING SCHEDULES |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
2-P-300 |
PLUMBING DRAINAGE PLAN |
|
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1/13/2019
Athenex GMP Drawing List |
Exhibit 3 (p. 16 of 20) |
Sheet Name |
Rev |
Set Name |
Issuance Date |
|
1-FP-000 |
FIRE PROTECTION COVER SHEET |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-FP-010 |
FIRE PROTECTION FIRST FLOOR ZONING PLAN |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-FP-010A |
FIRE PROTECTION FIRST FLOOR PLAN - SECTOR A - DENSITY PLAN |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-FP-010B |
FIRE PROTECTION FIRST FLOOR PLAN - SECTOR B - DENSITY PLAN |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-FP-010C |
FIRE PROTECTION FIRST FLOOR PLAN - SECTOR C - DENSITY PLAN |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-FP-010D |
FIRE PROTECTION FIRST FLOOR PLAN - SECTOR D - DENSITY PLAN |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-FP-010E |
FIRE PROTECTION FIRST FLOOR PLAN - SECTOR E - DENSITY PLAN |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-FP-010F |
FIRE PROTECTION FIRST FLOOR PLAN - SECTOR F - DENSITY PLAN |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-FP-010G |
FIRE PROTECTION FIRST FLOOR PLAN - SECTOR G - DENSITY PLAN |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-FP-010H |
FIRE PROTECTION FIRST FLOOR PLAN - SECTOR H - DENSITY PLAN |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-FP-010J |
FIRE PROTECTION FIRST FLOOR PLAN - SECTOR J - DENSITY PLAN |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-FP-015 |
FIRE PROTECTION INTERSTITIAL ZONING PLAN |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-FP-015F |
FIRE PROTECTION INTERSTITIAL FLOOR PLAN - SECTOR F - DENSITY PLAN |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-FP-015H |
FIRE PROTECTION INTERSTITIAL FLOOR PLAN - SECTOR H - DENSITY PLAN |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-FP-015J |
FIRE PROTECTION INTERSTITIAL FLOOR PLAN - SECTOR J - DENSITY PLAN |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-FP-020 |
FIRE PROTECTION SECOND FLOOR ZONING PLAN |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-FP-020A |
FIRE PROTECTION SECOND FLOOR PLAN - SECTOR A - DENSITY PLAN |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-FP-020B |
FIRE PROTECTION SECOND FLOOR PLAN - SECTOR B - DENSITY PLAN |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-FP-020C |
FIRE PROTECTION SECOND FLOOR PLAN - SECTOR C - DENSITY PLAN |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-FP-020D |
FIRE PROTECTION SECOND FLOOR PLAN - SECTOR D - DENSITY PLAN |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-FP-020E |
FIRE PROTECTION SECOND FLOOR PLAN - SECTOR E - DENSITY PLAN |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-FP-020F |
FIRE PROTECTION SECOND FLOOR PLAN - SECTOR F - DENSITY PLAN |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-FP-020G |
FIRE PROTECTION SECOND FLOOR PLAN - SECTOR G - DENSITY PLAN |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-FP-020H |
FIRE PROTECTION SECOND FLOOR PLAN - SECTOR H - DENSITY PLAN |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-FP-020J |
FIRE PROTECTION SECOND FLOOR PLAN - SECTOR J - DENSITY PLAN |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-FP-200 |
FIRE PROTECTION UNDERGROUND PLAN |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-FP-210 |
FIRE PROTECTION FIRST FLOOR PLAN - SPRINKLER |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-FP-210A |
FIRE PROTECTION FIRST FLOOR PLAN - SECTOR A - SPRINKLER |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-FP-210B |
FIRE PROTECTION FIRST FLOOR PLAN - SECTOR B - SPRINKLER |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-FP-210C |
FIRE PROTECTION FIRST FLOOR PLAN - SECTOR C - SPRINKLER |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-FP-210D |
FIRE PROTECTION FIRST FLOOR PLAN - SECTOR D - SPRINKLER |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-FP-210E |
FIRE PROTECTION FIRST FLOOR PLAN - SECTOR E - SPRINKLER |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-FP-210F |
FIRE PROTECTION FIRST FLOOR PLAN - SECTOR F - SPRINKLER |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-FP-210G |
FIRE PROTECTION FIRST FLOOR PLAN - SECTOR G - SPRINKLER |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-FP-210H |
FIRE PROTECTION FIRST FLOOR PLAN - SECTOR H - SPRINKLER |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-FP-210J |
FIRE PROTECTION FIRST FLOOR PLAN - SECTOR J - SPRINKLER |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-FP-215 |
FIRE PROTECTION INTERSTITIAL FLOOR PLAN - SPRINKLER |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-FP-215F |
FIRE PROTECTION INTERSTITIAL FLOOR PLAN - SECTOR F - SPRINKLER |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-FP-215H |
FIRE PROTECTION INTERSTITIAL FLOOR PLAN - SECTOR H - SPRINKLER |
1 |
Bulletin0020-IFCPermitIssue |
Dec 14, 2018 12:00 AM |
1-FP-215J |
FIRE PROTECTION INTERSTITIAL FLOOR PLAN - SECTOR J - SPRINKLER |