May 22, 1997
ADDENDUM 1
to
Specification
of
22,000 m3 Ethylene Gas Carriers
Hull Numbers 2245/2246/2247/2248/2249
Between
Cambridge Petroleum Transport Corporation Inc. and
Cambridge Partners L.L.C. as Investment Bank
(The Buyer)
and
Jiangnan Shipyard (Group) Co., Ltd.
(The Builder)
Dated: January 19, 1997
It has been mutually agreed between the Buyer and the Builder that
notwithstanding what has been previously agreed and at no additional cost to the
Buyer, the Specification has been amended as follows:
PAGE SECTION PARA. SUBJECT
---- ------- ---- -------
1-2 1.4 2 The ship will be designed to comply with the requirements of
Germanischer Xxxxx to get the following class:
Class: GL + 100 A5 E "Liquefied Gas Carrier Type 2G" + MC E AUT INERT
"or equal ABSDNV, LR" is deleted
1-2 1.4 In addition to the regulations specified in Section 1.4, the Vessels
must also comply with the following regulations:
o Rules and Regulations of the Classification Society.
o Rules and Regulations of the Flag State.
o IBC Code - for the range of cargoes that the Vessels are
designed to carry.
o International Convention for Prevention of Collision at Sea
1972 (COLREG) with Amendments 1981, 1987 and 1989.
o International Telecommunication and Radio Regulations
1985/86 with annexes and revisions.
o U.S. Coast Guard Regulations for Foreign Flagged Vessels
Navigating in U.S. Waters.
o Regulations of the International Labour Organisation (ILO - Convention)
- ILO 92/133 to be satisfied.
Page 1
PAGE SECTION PARA. SUBJECT
---- ------- ---- -------
o IEC Compliance for Electrical Installations.
o IMO Resolution A468 (XII) Noise Level on Board.
o ISO Guidelines Vibration in Merchant Ships.
o SITCO Requirements.
1-3 1.5 3 After "fore peak ballast tank" add: "Water
ballast tank and fuel deep tank (fuel stowage)
including HFO overflow tank and pump room".
1-6 1.7 * Add "Wherever possible all electric supply and control
cables to the main deck, cargo system and forecastle to be
run inside the top side wing tanks to minimise amount of
cabling and cable trays on deck."
1-7 1.10 3 Add at the end of the paragraph "Every effort should be made
to keep the trim when loaded with VCM to the minimum".
1-8 1.13 2 Delete and replace with "In accordance with the Shipbuilding
Contract clauses 7(b) and 7(c), the Seller (Builder) shall
at his own expense dispatch its representative(s) to attend
the gas trial as witness" and "Seller (builder) shall pay
all costs of its own representatives and of the
Classification Society and shall arrange at their expense
for the supplier to send at least one representative to the
gas trial"
1-16 1.15 2 Delete and replace with "Should there be any inconsistency
between the Specification and GA plan or other Contract
drawing, the Specification will govern unless otherwise
specifically agreed. If any inconsistency is found between
the Hull, Machinery and Electrical Specification, the
description of the Specification which governs the
installation of the equipment shall prevail"
1-17 1.16.3 The following Certificates must also be presented to the
Owner on delivery of the Vessel:
o Classification Certificates
o Safety Radio Telegraphy Certificate
o Safety Equipment Certificate
o Record of Safety Equipment
o IMO Certificate of Fitness for Regulated Cargo
o Suez Canal Tonnage Certificate
o Navigation Lights Certificate - including Suez Canal Navigation Regulations
o The Builder will submit the preliminary Trim and Stability Booklet
including the provisional certificate issued by Class at delivery.
Approved final booklets including the experiment will he provided
later when finalised.
Page 2
PAGE SECTION PARA. SUBJECT
---- ------- ---- -------
o Compass Adjustment Certificate.
o All other Certificates for Equipment, Castings, forgings etc... original plus
one copy of each.
1-17 1.16.4 5 Delete and replace with "Each vessel will be provided with a full
set of instruction books and drawings".
1-18 1.16.5 2 Delete and replace with "One set of drawings on transparencies
will be provided to each vessel"
1-21 1.20 2 Note: Fitted carpets in officers accommodation is shipyard supply.
2-2 2.6 Add additional paragraph after paragraph 2 "In order to
preserve the condition of the cargo tanks and cargo
compartments, the Builder will be arranged the necessary
piping and control devices to keep the compartments under a
positive pressure with dry air supplied from the TGE dry air
system. The Builder will also arrange a supply of Nitrogen
on deck adjacent to each cargo compartment which can be
connected by flexible hose in case of need"
2-3 2.8 The Builder will modify the arrangement as currently shown
on the GA plan to allow unencumbered access along the length
of the cargo tanks in each hold in way of the top of the
ballast tanks
3-4 Paint Add after the tables: "The paint specification will be
Tables reviewed with selected paint supplier to ensure coating is
suitable for long term service in all locations".
4-1 4.2 1 Second sentence should read "Both windlass will be equipped
with a wildcat, two detachable drums and a warping head"
Third sentence delete "auto tensioning device"
5 Delete and replace with "Each windless/mooring winch will have
a separate hydraulic pump. Each hydraulic pump to be fitted
with a crossover connection in case of pump failure."
4-2 4.3 1 Delete "auto tensioning device"
4 Delete the second sentence and replace with "Each mooring winch
will have a separate hydraulic pump. Each hydraulic pump to be
fitted with a crossover connection in case of pump failure. Oil
cooler, if any, and relevant accessories will be located in the
hydraulic room".
4.1 4.2 1 Add to the end of the first paragraph "However the drums for the
Page 3
PAGE SECTION PARA. SUBJECT
---- ------- ---- -------
windlass are to be designed to accommodate Atlas rope of
equivalent size to 30mm wire."
4-2 4.3 1 Add to the end of the first paragraph "However the drums for the
mooring winches are to be designed to accommodate Atlas rope of
equivalent size to 30mm wire."
4-2 4.3 6 Delete "7 lines" and insert "8 lines".
4-3 4.6 Life Revise lifeboat capacity to "25 persons"
Boat
Life Revise each aft life raft capacity to "25 persons"
Rafts Revise forward life raft capacity to "6 persons"
Misc. Revise lifejacket capacity to "27 persons"
Ships Note: Ships crane can be mounted either on the port or
Crane starboard side to maximise design flexibility for handling
stores and engine spares, etc.
E/R Add after last paragraph "If the Engine room crane and the
crane provisions crane do not overlap, the intervening distance
should be flat, with no obstructions, so that heavy
equipment can be easily manoeuvred between the lifting
points on a trolley or similar device. Failing which, an
auxiliary lifting arrangement should be provided to bridge
the gap between the cranes."
4-6 4-10 4 Should read "muster station"
5-1 5.1.1 7 Add at the end of the paragraph "Ballast pump remote stop
and start buttons together with remote pressure sensor to be
mounted on the same console"
5-8 5.10.1 1 Add at the end of the first paragraph "Recirculation will be
provided by way of extractors in the accommodation alleyways".
5 Add "The A/C compressors and condensers will be located inside
the engine room and in the case of a fresh water central
cooling system being fitted, the condensers will be fresh water
cooled."
6 Delete and replace with "One air conditioning unit will consist
of a mixing section, air filter, fan, steam heater, cooler and
humidifier. The A/C unit will be installed in the A/C room on
the first accommodation deck, aft".
5-10 5.12 3 Note Ventilation in the electric motor room will be designed such
Page 4
PAGE SECTION PARA. SUBJECT
---- ------- ---- -------
that the maximum operating temperature is kept below 45
degrees Celsius with an ambient temperature of 35 degrees
Celsius.
5.12 5.14 1 Add after the first paragraph "Drain pipes should be
electrically trace heated".
5.12 5.15 3 Delete and replace with "HFO and steam pipes will be insulated
throughout the system, including the pipe tunnel".
6-4 6.5 The layout of the accommodation is amended as follows:
"Accommodation Deck 3
Captain Apartment 1 bunk
Chief Engineer Apartment 1 bunk
Chief Officer Apartment 1 bunk
2nd Engineer Apartment 1 bunk
Owner/Pilot Cabin 1 bunk
Accommodation Deck 2
3rd Engineer Cabin 1 bunk
2nd Officer Cabin 1 bunk
Electrician Cabin 1 bunk
3rd Officer Cabin 1 bunk
Gas Engineer Cabin 1 bunk
Officers Day room
Accommodation Deck 1
Boatswain Cabin 1 bunk
AB Cabin 1 bunk
2 AB Cabin 1 double bunk
2 OS Cabin 1 double bunk
Fitter Cabin 1 bunk
2 Oiler Cabin 1 double bunk
Wiper Cabin 1 bunk
Xxxx Cabin 1 bunk
Xxxxxxx Cabin 1 bunk
Suez Cabin Cabin 3 double bunk
Basic Crew Compliment with 3 riding squad "25 Crew"
6-5 6.5 2 Amend life saving equipment to "25 persons"
3 Note: Accommodation description in the specification is
missing a lot of detail. Detailed accommodation plan will be
submitted to the Buyer by the Builder for approval. Builder
will make their best efforts to incorporate Buyer's
reasonable requirements
Note: Detailed cargo control room plan will be submitted to
the Buyer by the Builder for approval. Builder will make
their best efforts to incorporate Buyer's reasonable
requirements
Page 5
PAGE SECTION PARA. SUBJECT
---- ------- ---- -------
6.6 6.6 Add at the end "Builder to provide Buyer with
samples of materials and furniture intended for
accommodation outfit".
6-10 6.14 Add to the list "Adequate storage for books, manuals, ISO,
ISM documentation."
6-11 6.16 Add to the end of the section "Detailed bridge layout plan
will be submitted to the Buyer by the Builder for approval.
Builder will make their best efforts to incorporate Buyer's
reasonable requirements"
6-11 6.18 2 Amend Electric range suitable for "27 persons". Amend "Working
table of stainless steel". Add to the end "Compactor to be
provided by the Buyer and installed by the Builder"
6-12 6.19 First sentence delete and replace with: "One Pantry is to be
arranged adjacent to the galley to serve the officers mess
room".
6-13 6.20 Amend to "2 dryers"
Note: Drying room to be arranged next to the laundry as shown on the GA Plan.
6-13 6.21 Note: Customs store to be arranged as shown on GA plan.
6-13 6.22 Detailed layout of stores compartments together with
adequate racks, bins, lockers, shelving to be provided for
safe stowage of all provisions, spares and equipment to be
provided by the Builder for Buyer's approval. Builder will
make their best efforts to incorporate Buyer's reasonable
requirements
7-2 7.1.1 11 Note: Access hatch to the engine room at first accommodation
deck and poop decks to be as large as possible.
7-l1 7.1.3.5 Amend to "Minimum two boiler heavy fuel circulating pumps"
7-14 7.1.3.7 Amend to "Service air compressor will be screw type."
7-16 7.1.3.9 Note: The Incinerator is described in section 7-8-5 is to be
of suitable capacity to simultaneously burn all waste oil
(sludge) produced aboard the vessel.
7-17 7.1.3.9 Amend Sewage Treatment Device capacity to "25 persons per
day"
17-18 7.1.3.10 Amend to "Fuel oil and lub, oil tanks to be fitted with sounding
Page 6
PAGE SECTION PARA. SUBJECT
---- ------- ---- -------
pipes to the extent possible. If allowed by the rules
calibrated sight glasses with shutoffs to be considered
instead of float sounding. However magnetic floating type
will be provided for F.O. service and settling tanks instead
of sight glasses."
Amend to: "Main engine lub oil storage tank to be minimum
50% larger than the lub oil sump tank."
Gen. engine lub oil storage tank to be "as large as
possible"
7-20 7.1.4 1 Add to first paragraph "Owner's representative to be invited
to attend all shop trials. Any associated travel expenses to
be for Buyer's account"
7-25 7.3.6 7 Amend wording to "Net protector with cutter to be provided".
7-27 7.4.2.4 2 Amend to "2 - Fuel oil burning pump."
7-38 7.8.6 Should read - "The sewage treatment plant is to be fitted
with 1 discharge pump and 2 air blowers."
7-45 7.10.2.2 11 Should read - "All interior surfaces of the tanks and spaces etc."
7-47 7.10.3.1 7 Delete and replace with "The bunkers system is to be of the
enclosed type whereby any overflow from any tank is lead to
a overflow tank aft or forward. Overflow from the MDO
storage tank in the double bottom to be arranged with
overflow into the overflow tank also in the double bottom
with non return valve."
8 Add: "Level indicators for fuel oil storage, settling and
day tanks to be located in the ER Control Room".
7.54. 7.10.10 Heavy fuel oil purifier - should read - "simplex filter at
each pump"
Xxxxx tube lub oil pump - should read - "simplex filter at
each pump"
Lub oil pump for main engine should read - "simplex filter
at each pump"
11 Should read - "Velocities in pipe lines for sea water, fresh
water and lub oil are to be in accordance with engine makers
requirements"
7-57 7.11.1.1 14 Should read - "Brass name plates with engraved letters and
location numbers referring to pipes system drawings for all
valves pumps heat exchangers etc. . . ."
Page 7
PAGE SECTION PARA. SUBJECT
---- ------- ---- -------
7-64 7.12.1 Add after the first paragraph:
"Wherever tanks and/or bulkheads are required to be
insulated, the insulation is to be laid and secured inside a
steel frame with suitable sub divisions and covered with
0.7mm galvanised steel plate".
7-64 7.12.1 6 Delete and replace with "Exhaust piping in the funnel to be
insulated up to the penetration".
7-65 7.12.2.2 2 Add: "Insulation to be applied to steam pipes of 25mm and
below if the amount of such pipe is considered excessive."
7-65 7.12.2.3 1 Delete first sentence and insert "Cooling fresh water pipe in the
engine room not to be insulated. All sanitary water and fresh
water pipes in the accommodation to be insulated with Armafex
or other equivalent material."
7.66 7.12.2.5 2 Delete and replace with "Exhaust piping in the funnel to be
insulated up to the penetration".
7-66 7.12.4 1 Delete and replace with "Heavy fuel oil settling tanks, heavy fuel
oil service tanks (except the bottom surface of the tanks) to he
insulated with 40mm rock wool and covered with 0.7mm
galvanised steel sheet in the manner prescribed in Section 7.12.1."
7.67 7.12.4 1 Delete and replace with "The fuel oil tank facing the cargo hold to
be insulated."
7-67 7.12.5 2 Delete and replace with "Exhaust piping in the funnel to be
insulated up to the penetration and covered with galvanised steel
sheet."
7-71 7.13.5 1 Delete and replace with "C02 fire extinguishing system for main
engine to be provided".
7-71 7.13.7.2 2 Delete and replace with "If not directly serviced by the E/R crane
lifting beams to be provided for oil purifiers and turbocharger
rotors etc. . . ."
7-81 7 14.1 Extension alarms to be adjusted to "CE/2E/3E/GE/EE/OM/OD"
D Engine Telegraph - should read
"Receiver with reply transmitter
Main engine local emergency control station."
4 Add at the end of the paragraph "and ME local emergency control"
Page 8
PAGE SECTION PARA. SUBJECT
---- ------- ---- -------
station".
7-83 7.14.2 A Should read
"Program type remote control from wheel house"
"Manual type remote control from engine control room" etc...
7-97 7.14.4 A Amend to "Burner shall be electric ignition (initially)" etc....
8-1 8.1 4 Delete and replace with "Builder will provide samples of cable trays to buyer".
7 Add "Builder will provide Buyer with electrical load analysis as soon as it is available."
8-3 8.3 2 Delete and replace with "The E/DG set will be capable of working when the ship is heeled to an
angle of 22.5 degrees"
8-5 8.6 2 Should read "the box will be complete with standard components, instruments and phase indicator"
8-7 8.10 2 Add after second paragraph - "Each pump will have a separate starter box located close to the
pump"
8-9 8.12.1 1 Add "Telephone connection to be provided at the bunker station on deck. Builder to provide one (1)
portable telephone and install two (2) xxxx boxes at the bunker station"
8-9 8-12-2 Amend to "Sound powered telephone connecting W/H, ECR, M/E emergency control station and the
emergency steering station in the steering gear room".
8-13 8 13.7 Add "Fresh water wash system to be provided at the bridge windows"
All other terms to remain unchanged
For Buyer: For Builder:
Cambridge Petroleum Transport Jiangnan Shipyard (Group) Co. Ltd
Corporation Inc.
and
Cambridge Partners L.L.C. as Investment Bank
/s/ X. X. XXXXXXXX /s/ XXXX XXX MING
------------------------------ ---------------------
X. X. Xxxxxxxx - As Agent Only Xxxx Xxx Ming
Page 9
ADDENDUM 2
to
Specification
of
22,000 m3 Ethylene Gas Carriers
Hull Numbers 2245/2246/2247/2248/2249
Between
Cambridge Petroleum Transport Corporation Inc. and
Cambridge Partners L.L.C. as Investment Bank and
Navigator Holdings Ltd.
(The Buyer)
and
Jiangnan Shipyard (Group) Co., Ltd.
(The Builder)
Dated: January 19, 1997
It has been mutually agreed between the Buyer and the Builder that
notwithstanding what has been previously agreed and for an additional cost of
US$ 100,000 per vessel, which will be added to the contract price and payable on
delivery of each vessel, the Specification has been amended as follows:
1. The specified salt water engine room machinery cooling system
(including the air conditioning plant) will be replaced with a central
flesh water cooling system. The central fresh water cooling system
will consist of a short sea water cooling circuit (with 2 plate
coolers in parallel) - cooling a long fresh water cooling circuit
serving all machinery, coolers and heat exchangers in the engine room.
The short sea water cooling circuit including all valves and fittings
will be constructed of salt water resistant material such as cunife
(except main sea water line which to be galvanised steel pipe) and the
fresh water circuit of mild steel. All major coolers will be of plate
type with plates constructed of titanium on the salt water cooling
circuit and stainless steel on the fresh water circuit. The Builder
will endeavour to install a plate cooler as the auxiliary condenser
however if such plate condenser is not available the Builder will
install a suitable tube cooler. The Builder will provide the Buyer
with further details of the proposed arrangement for their approval.
2. The hull coating and cathodic protection system outlined in Section 3
of the specification is amended so that it will comply with the
requirements of Class for In Water Survey (IWS) and will provide that
the vessel need only drydock every 5 years for Class renewal and
recoating. Accordingly the Builder will provide an impressed current
system and all other requirements to meet Class requirements.
3 The Buyer will provide at his own expense a third compressor of 50% of
the design capacity (125KW - 107,500 X.xxx/hr) for the prescribed air
conditioning system in the accommodation. At no additional cost to the
Buyer, the Builder will install and arrange the three compressors in
the engine room so that any two of the three compressors can run the
system at any time with the third being in standby.
4. In order to safely operate the remote control ballast system from the
Cargo Control Room, the Builder will provide remote ballast pump start
and stop controls and appropriate suction/pressure gauges at the
ballast valve control station (mimic board).
5. The fuel oil transfer pumps prescribed in Section 7.10.3.1 shall be
rearranged such that the diesel oil transfer pump will be of the same
capacity as the heavy fuel oil transfer pump. In the event of the
failure of either pump they will be interchangeable for either fuel
system.
6. The Steam Generation Plant prescribed in Section 7.4 is amended to a
smoke tube composite boiler manufactured by Shazhou Boiler Works in
co-operation with Xxxxx. The Builder will provide the Buyer with
detailed drawings of the amended arrangement for approval. As the
composite boiler is now smoke tube type on both sides, the soot blower
prescribed in Section 7.4.2.4 is deleted.
7. Section 8.2 - Main Diesel generators - it is agreed that the structure
and number of bearings will be as per manufacturers standard.
All other terms to remain unchanged
For Buyer: For Builder:
Cambridge Petroleum Jiangnan Shipyard (Group) Co. Ltd
Transport Corporation Inc.
and
Cambridge Partners L.L.C. as
Investment Bank
and
Navigator Holdings Ltd.
/s/ X. X. XXXXXXXX /s/ XXXX XXX MING
----------------------------- ------------------------
X. X. Xxxxxxxx As Agent Only Xxxx Xxx Ming
January 23, 1998
ADDENDUM 3
to
Specification
of
22,000 m3 Ethylene Gas Carriers
Hull Numbers 2245/2246/2247/2248/2249
Between
Cambridge Petroleum Transport Corporation Inc. and
Cambridge Partners L.L.C. as Investment Bank and
Navigator Holdings Ltd.
(The Buyer)
and
Jiangnan Shipyard (Group) Co., Ltd.
(The Builder)
Dated: January 19, 1997
It has been mutually agreed between the Buyer and the Builder that
notwithstanding what has been previously agreed in the Specification and
Appendix 2 - item 3 thereto, the Builder will supply, install and arrange a
third compressor without condenser to the air conditioning system so that any
two of the three compressors can run the system at any time with the third being
in standby. The agreed incremental price is United States Dollars 15,000, which
will be added to the Contract Price and be payable on delivery of the Vessel.
All other terms to remain unchanged
For Buyer: For Builder:
Cambridge Petroleum Jiangnan Shipyard (Group) Co. Ltd.
Transport Corporation Inc.
and
Cambridge Partners L.L.C. as
Investment Bank
and
Navigator Holdings Ltd.
/s/ X. X. XXXXXXXX /s/ XXXX XXX MING
----------------------------- ------------------------
X. X. Xxxxxxxx As Agent Only Xxxx Xxx Ming
January 26, 1998
ADDENDUM 4
to
Specification
of
22,000 m3 Ethylene Gas Carriers
Hull Numbers 2245/2246/2247/2248/2249
Between
Cambridge Petroleum Transport Corporation Inc. and
Cambridge Partners L.L.C. as Investment Bank and
Navigator Holdings Ltd.
(The Buyer)
and
Jiangnan Shipyard (Group) Co., Ltd.
(The Builder)
Dated: January 19, 1997
During consultations between the Buyer and the Builder during the plan approval
process and subsequent to a review meeting at the Yard, it has been mutually
agreed that the scope of supply shall be amended to include the following items
with no change to the Contract price:
SPECIFICATION - SECTION 2.10 RUDDER
The upper bearing will be of simplified design incorporating a water lubricated
plastic xxxx. The xxxxxx stock will be fitted with a stainless steel liner in
way of stuffing box.
GENERAL ARRANGEMENT PLAN
Rooms under Forecastle Area to be rearranged:
o Bulkhead at frame 201 to be removed and replaced with a web frame creating
three large compartments.
o Starboard compartment to be redesignated Cargo Gear Room and to have access
directly to main deck. Compartment to be arranged with fixed supports for
storage of flexible cargo hoses and shelves for storage of reducers,
flanges spool pieces etc....
o Dry Powder plant to he relocated in Hydraulic Room subject to
reconfirmation by the Builder.
o Port side compartment to be designated as a Paint Store.
Forward HFO overflow tank
To be relocated away from bulkhead adjacent to salt water ballast tank and chain
lockers.
Main Deck
o Mooring bollards at port and starboard sides to be relocated outboard
o Deck house and stairs from poop deck to tween deck to be deleted. A 1200 mm
x 1000 xx xxxxx to be arranged close to aft bulkhead of accommodation to
port deck store. A single Builder's Standard access door to port deck store
to be arranged from engine room.
DRAWINGS AL - SHEETS 1 TO 1O ACCOMMODATION
The Builder will make their best efforts to rearrange the accommodation area in
the following fashion. Should the following arrangements not be practicable, the
Builder and the Buyer will discuss and agree alternative layouts.
Bridge Deck - 1/10
o The bridge will be arranged with an enclosed stairway with appropriate
light switching. The chart room and communications room will be segregated
from the wheelhouse area by partitioning walls with suitable openings
maximising the visability aft.
o A storage room of appropriate size for the fire fighting protective
clothing and other related equipment is to be arranged at the aft end of
the bridge or at another suitable location to be mutually agreed.
o Storage/filing cabinets to be arranged at the forward bulkheads to the
chart table and communications area. Adequate shelves for nautical, radio
and ships manuals to be arranged in chart room and communication room.
3rd Accommodation Deck - 2/10
o The ships office will be arranged with a 8 person conference table and two
work stations. The aft bulkhead will be fitted with filing cabinets with
shelves above for the housing the ships plans, manuals and papers.
Provision to be made for copying machine and computer work stations. Sink
to be arranged and provision made for coffee machine adjacent thereto.
o Credenza (low storage cupboards) to be installed along bulkhead behind
Captain's and Chief Engineer's desks. Provision to be made for the
installation of televisions on the credenzas. Book shelves to be arranged
above.
o Bath tubs in Captain and Chief Engineers bathrooms to be replaced with
showers.
o Captain and Chief Engineer day rooms to be reduced in length by 500 mm to
increase the size of the 2nd Officer's and 3rd Engineer's cabins
respectively.
o Chairs in Captain's and Chief Engineer's bedrooms to be relocated to their
day rooms. General wardrobes in all officers cabins to be increased in size
to 1200 mm x 600 mm. & all coffee tables in cabins to be oblong rather than
round.
2nd Accommodation Deck - 3/10
o Officer's lounge to be rearranged with a wet bar, bar stools and
refrigerator. Provision to be made for dart board supplied by the Buyer.
o Table to be removed from Chief Officer's and 2nd Engineer's bedrooms.
Credenzas to be arranged at front bulkhead of day rooms and provision to be
made to install television.
1st Accommodation Deck - 4/10
o 2 oiler cabins and 1 wiper cabin to be provided with double bunks/wardrobes
etc...for double occupancy
Main Deck - 5/10
o Crew mess room to be rearranged to seat 15 crew members - with sofa
seating at the bulkheads and chairs around oblong tables. Drinking fountain
to be installed.
o Crew lounge to be arranged with seating spaces for 15 crew.
o Ships cargo control room and deck office to be arranged across the
remaining forward part of the accommodation in one space - store & linen
store to be relocated. Means to close off the cargo control space from the
deck office to be provided. Deck office to be outfitted with a conference
table for 8 persons and work station. Provision to be made for a
photocopier, computer, printer etc....
o Officer's mess room to be arranged for 12 persons - with sofa seating at
bulkheads, two oblong dining tables and arm chairs.
o A duty mess room for 8 persons to be provided in the area previously
designated for storage of dry provisions outside galley. Drinking fountain
to be installed.
Tween Deck - 6/10
o Compressor Room to be rearranged on the port side and Engine Room Store to
be rearranged on the starboard side.
o Engine room store to be outfitted as per Buyer's sketch with 9 steel
storage lockers and shelving at the perimeter and at the centre isle.
Lifting rail to be provided.
o The size of the drying area within the laundry will be maximised.
o Beer store to be redesignated Bonded Store. Bonded Store room to be
redesignated Baggage Room. Baggage Room to be redesignated Linen Room.
o Builder will try to arrange suitable hatches to provide free passage of
complete alternators from auxiliary engine platform to main deck.
o Shower to be removed from changing area and an additional sink provided.
o The stores hatch 1100mm x 1400mm at frame 20 shall be arranged with a
raised coaming and hinged lid secured by wing nuts opening by crane or
chain block
All other terms to remain unchanged
For Buyer: For Builder:
Cambridge Petroleum Jiangnan Shipyard (Group) Co. Ltd.
Transport Corporation Inc.
and
Cambridge Partners L.L.C. as
Investment Bank
and
Navigator Holdings Ltd.
/s/ X. X. XXXXXXXX /s/ XXXX XXX MING
----------------------------- ------------------------
X. X. Xxxxxxxx As Agent Only Xxxx Xxx Ming
January 25, 1998
ADDENDUM 5
to
Specification
of
22,000 m3 Ethylene Gas Carriers
Hull Numbers 2245/2246/2247/2248/2249
Between
Cambridge Petroleum Transport Corporation Inc. and
Cambridge Partners L.L.C. as Investment Bank and
Navigator Holdings Ltd.
(The Buyer)
and
Jiangnan Shipyard (Group) Co., Ltd.
(The Builder)
Dated: January 19, 1997
During consultations between the Buyer and the Builder during the plan approval
process and subsequent to a review meeting at the Yard, it has been mutually
agreed that the scope of supply shall be amended to include the following items
with no change to the Contract price:
SPECIFICATION
Section 2.1 - General
It has been agreed that the framing of the outside shell in way of cargo holds
will be longitudinally framed rather than transverse framed, as prescribed in
the specification. Reinforced areas will be fitted at three locations on each
side to create stiffened tug pushing points as per the Outside Shell Expansion
Drawing.
Section 4.10 - Gratings on Deck
All gratings fitted on deck will be fabricated from reinforced glass fibre
rather than galvanised steel, as prescribed in the specification.
Section 5.1.1 & Appendix 2 - Remote Control Ballast Water System
The Builder will supply and install remote controlled valves throughout the
system with the exception of valves to the main sea water pump.
Section 7.1.3.5 - Preheating Pump for Main Engine Cooling Water System.
The Builder will supply and install a preheating pump, of appropriate size, for
the main engine cooling water system.
Section 7.2. 1 - Torsional Vibration Damper
The Builder will supply and install a "Xxxxxxxxxx" type torsional vibration
damper to remove the barred speed range.
Section 7.10.3 - Heavy Oil Treatment Unit
The designed Heavy Oil Treatment Unit will have sufficient capacity to supply 3
auxiliary diesel generators running in parallel at 65% of MCR and the main
engine running at 100% of MCR at the same time.
Section 7.10.3 - Harbour Fuel Oil Supply Pump
The Builder will supply and install a Harbour Fuel Oil Supply Pump of sufficient
capacity to supply 2 auxiliary diesel generators running at 100% of MCR or 3
auxiliary diesel generators running at 65% of MCR.
Section 8.1 & Appendix 1 - Cable Trays
Cable trays on deck to be of plastic coated steel.
Section 8.12 - Dead Man Alarm System
The Builder will supply and install a "Dead Man Alarm" system in the bridge
console.
APPENDIX 2
Central Cooling System
Each of the prescribed central coolers will be outfitted with the designed
maximum number of plates. The Builder will consult with Alpha Laval with a view
to adding an addition 56 plates to each cooler while maintaining the current
designed location. Should this not be practicable the Builder and Buyer will
discuss and agree an alternative arrangement.
Fresh Water Cooling System
The designed fresh water cooling system will have sufficient capacity to supply
3 auxiliary diesel generators running in parallel at 65% of MCR and the main
engine running at 100% of MCR at the same time.
Fresh Water Cooling Pumps
The builder will supply and install three fresh water cooling pumps of equal
size. The capacity of the pumps will be such that with any 2 pumps running in
parallel they will supply not less than 100% of the maximum required capacity of
the system.
All other terms to remain unchanged
For Buyer: For Builder:
Cambridge Petroleum Jiangnan Shipyard (Group) Co. Ltd.
Transport Corporation Inc.
and
Cambridge Partners L.L.C. as
Investment Bank
and
Navigator Holdings Ltd.
/s/ X. X. XXXXXXXX /s/ XXXX XXX MING
----------------------------- ------------------------
X. X. Xxxxxxxx As Agent Only Xxxx Xxx Ming
August 1, 1998
ADDENDUM 6
to
Specification
of
22,000 m3 Ethylene Gas Carriers
Hull Numbers 2245/2246/2247/2248/2249
Between
Cambridge Petroleum Transport Corporation Inc. and
Cambridge Partners L.L.C. as Investment Bank and
Navigator Holdings Ltd.
(The Buyer)
and
Jiangnan Shipyard (Group) Co., Ltd.
(The Builder)
Dated: January 19, 1997
It has been mutually agreed between the Buyer and the Builder that the Builder
will install a Cargo Head Condenser system designed by Tractobel Gas Engineering
GmbH. The Cargo Head Condenser will be capable maintaining the
temperature/pressure of a third grade of cargo carried in cargo tank No. 4.
The fitting of the Cargo Head Condenser will comprise the following increases to
the scope of supply for the Contracted gas system:
o One tank head condenser of shell and tube design (material: stainless
steel) which is to be installed near the dome of tank No. 4 in order
to liquefy the boil-off gases.
o Pipe connection to the refrigeration system (propylene cycle),
including all necessary instrumentation, valves, controls etc....
o Insulation of pipes
o Integration into the control and monitoring system.
o Erection works
The agreed price for the installation of the Cargo Head Condenser is US$ 24,000
(United States Dollars twenty four thousand) per vessel which will be added to
the Contract Price and payable on delivery of each Vessel.
All other terms to remain unchanged
For and on behalf of the Buyer: For and on behalf of the Builder:
Cambridge Petroleum Jiangnan Shipyard (Group) Co. Ltd.
Transport Corporation Inc.
and
Cambridge Partners L.L.C. as
Investment Bank
and
Navigator Holdings Ltd.
/s/ X. X. XXXXXXXX /s/ XXXX XXX MING
----------------------------- ------------------------
X. X. Xxxxxxxx As Agent Only Xxxx Xxx Ming
August 1, 1998
ADDENDUM 7
to
Specification
of
22,000 m3 Ethylene Gas Carriers
Hull Numbers 2245/2246/2247/2248/2249
Between
Cambridge Petroleum Transport Corporation Inc. and
Cambridge Partners L.L.C. as Investment Bank and
Navigator Holdings Ltd.
(The Buyer)
and
Jiangnan Shipyard (Group) Co., Ltd.
(The Builder)
Dated: January 19, 1997
After reviewing the gas plant model provide by TGE, it has been mutually agreed
between the Buyer and the Builder that the Builder will make the following
changes at no additional cost to the Buyer.
1. GANGWAY FROM ACCOMMODATION TO FORESHIP
The catwalk as described in Section 1.5 Page 1/3 has been deleted.
2. WAVE PROTECTION OF THE LPG VAPORISER (STARBOARD SIDE)
The Builder will supply and install a wave breaker to protect the starboard
side LPG vaporiser in accordance with the model.
3. DRY AIR AND NITROGEN PURGE CONNECTIONS TO THE CARGO HOLDS
The Builder will supply and fit a piping system, together with the
necessary flexible hoses, so that the cargo void spaces can be purged and
filled with either dried air or Nitrogen. The system will receive supply
of either dried air or Nitrogen from either the Inert Gas System or Dried
Air Systems driven off the PSA unit.
4. BUNKER LINES ON MAIN DECK
The Builder will supply and fit bunker manifolds adjacent to the cargo
manifolds - so that bunker hoses can be handled by the cargo hose handling
crane, as shown in the model.
5. SEA WATER COOLING LINES FOR THE GAS PLANT
The sea water cooling line overboard discharge lines will be arranged so
that they pass through the void spaces at the ends of the cargo holds. The
pipes will be constructed of sch. 120 hot galvanised pipe and connected
with flanges so that the pipes can be removed without hot work in case of
need. A hot galvanised penetration pieces (seachest type) will be supplied
and fitted at the outside shell.
The sea water cooling supply lines will be fitted on deck.
6. WINDOWS IN COMPRESSOR ROOM
The Builder will supply and fit A 60 type windows 600mm x 400mm between the
electric motor room and the compressor room in three locations in order
that the control panels for each unit can be effectively monitored.
7. FAN MOTORS ON TOP OF COMPRESSOR HOUSE
The Builder will ensure that the fan motors located on top of the
Compressor House will be adequately protected from weather and corrosion
damage.
All other terms to remain unchanged.
For and on behalf of the Buyer: For and on behalf of the Builder:
Cambridge Petroleum Jiangnan Shipyard (Group) Co. Ltd.
Transport Corporation Inc.
and
Cambridge Partners L.L.C. as
Investment Bank
and
Navigator Holdings Ltd.
/s/ X. X. XXXXXXXX /s/ XXXX XXX MING
----------------------------- ------------------------
X. X. Xxxxxxxx As Agent Only Xxxx Xxx Ming
August 1, 1998
ADDENDUM 8
to
Specification
of
22,000 m3 Ethylene Gas Carriers
Hull Numbers 2245/2246/2247/2248/2249
Between
Cambridge Petroleum Transport Corporation Inc. and
Cambridge Partners L.L.C. as Investment Bank and
Navigator Holdings Ltd.
(The Buyer)
and
Jiangnan Shipyard (Group) Co., Ltd.
(The Builder)
Dated: January 19, 1997
Having reviewed the Builders procedures for construction, insulation and
storage of cargo tanks, it has been mutually agreed between the Buyer and the
Builder that the Builder will make the following improvements in the
production process at no additional cost to the Buyer.
1. Tank Insulation
The Builder will construct weather proof shelters - consisting of a steel
frame adequately covered with fibreglass sheets at the top and sides - in
order that application of the insulation and cladding will be conducted in a
dry, weatherproof environment.
2. After final application of insulation and cladding and acceptance by both
Class and the Owners, the Builder will ensure that the tanks remain
adequately covered with either the shelters or canvas covers so that the tank
insulation and cladding is adequately protected from rain water during the
storage period prior to installation aboard the Vessel.
3. After installation aboard the Vessel the Builder will ensure that the tanks
are adequately protected from rainwater and mechanical damage during the
time prior to that the deck sections being installed and the cargo void
spaces being weather proof.
All other terms to remain unchanged.
For and on behalf of the Buyer: For and on behalf of the Builder:
Cambridge Petroleum Jiangnan Shipyard (Group) Co. Ltd.
Transport Corporation Inc.
and
Cambridge Partners L.L.C. as
Investment Bank
and
Navigator Holdings Ltd.
/s/ X. X. XXXXXXXX /s/ XXXX XXX MING
----------------------------- ------------------------
X. X. Xxxxxxxx As Agent Only Xxxx Xxx Ming
June 19, 1997
ADDENDUM 10
to
Specification
of
22,000 m3 Ethylene Gas Carriers
Hull Numbers 2245/2246/2247/2248/2249
Between
Cambridge Petroleum Transport Corporation Inc. and
Cambridge Partners L.L.C. as Investment Bank and
Navigator Holdings Ltd.
(The Buyer)
and
Jiangnan Shipyard (Group) Co., Ltd.
(The Builder)
Dated: January 19, 1997
It has been mutually agreed between the Buyer and the Builder that
notwithstanding what has been previously agreed, for an additional cost of
US$ 4,500 (United States Dollars Four Thousand Five Hundred) per vessel,
which will be added to the contract price and payable on to the Builder on
delivery of each vessel, the Specification has been amended as follows:
o The Builder with supply, arrange and install a Xxxx Xx Model SS200 waste
disposal unit of capacity 319 kg/meal as per the attached specification.
All other terms to remain unchanged
For Buyer: For Builder:
Cambridge Petroleum Jiangnan Shipyard (Group) Co. Ltd.
Transport Corporation Inc.
and
Cambridge Partners L.L.C. as
Investment Bank
and
Navigator Holdings Ltd.
/s/ X. X. XXXXXXXX /s/ XXXX XXX MING
----------------------------- ------------------------
X. X. Xxxxxxxx As Agent Only Xxxx Xxx Ming
August 1, 1998
ADDENDUM 1
to
Amended and Restated
Shipbuilding Contract
for
22,000 m3 Ethylene Gas Carriers
Hull Numbers 2245/2246/2247/2248/2249
Between
Navigator Holdings PLC
(The Buyer)
and
Jiangnan Shipyard (Group) Co., Ltd.
(The Builder)
Dated: June 26, 1997
After reviewing the initial stability calculations provided by the Builder dated
May 25, 1998, which is appended hereto, it has been mutually agreed between the
Buyer and the Builder that the Builder will strengthen the Vessel so that in
cases 25, 26, 30, 41, 49 and 57 the maximum allowed bending moments are not
exceeded.
To strengthen the Vessel so that cases 25, 26, 30, 41, 49 and 57 are within the
maximum allowed bending moments. the Builder estimates that it will be necessary
to increase the lightship weight by some 120 metric tons which will be done at
no additional expense to the Buyer.
The Buyer agrees that the maximum deficiency in the guaranteed Deadweight as
prescribed in Article III, Section 4(a) of the Amended and Restated Shipbuilding
Contract dated June 26, 1997 shall be increased from four hundred (400)
metric tons to five hundred and twenty (520) metric tons accordingly.
All other terms to remain unchanged
For and on behalf of Buyer: For and on behalf of Builder:
Navigator Holdings PLC. Jiangnan Shipyard (Group) Co. Ltd.
/s/ X. X. XXXXXXXX /s/ XXXX XXX MING
----------------------------- ------------------------
X. X. Xxxxxxxx As Agent Only Xxxx Xxx Ming