Balancing Authority Area Notification Sample Clauses
The Balancing Authority Area Notification clause requires parties to inform relevant stakeholders when there are changes or events affecting the designated balancing authority area. In practice, this means that if a party’s operations, such as generation or load, shift from one balancing authority area to another, or if there are disruptions impacting the area’s reliability, prompt notification must be provided to ensure all parties are aware. This clause ensures operational transparency and coordination, helping to maintain grid stability and compliance with regulatory requirements.
Balancing Authority Area Notification. At least three months before Initial Synchronization Date, the Interconnection Customer shall notify the CAISO and Participating TO in writing of the Balancing Authority Area in which the Large Generating Facility intends to be located. If the Interconnection Customer intends to locate the Large Generating Facility in a Balancing Authority Area other than the Balancing Authority Area within whose electrically metered boundaries the Large Generating Facility is located, and if permitted to do so by the relevant transmission tariffs, all necessary arrangements, including but not limited to those set forth in Article 7 and Article 8 of this LGIA, and remote Balancing Authority Area generator interchange agreements, if applicable, and the appropriate measures under such agreements, shall be executed and implemented prior to the placement of the Large Generating Facility in the other Balancing Authority Area.
Balancing Authority Area Notification. At least three months before Initial Synchronization Date, the Interconnection Customer shall notify the CAISO and Participating TO in writing of the Balancing Authority Area in which the Large Generating Facility intends to be located. If the Interconnection Customer
Balancing Authority Area Notification. At least nine months before Initial Synchronization Date, Customer shall notify Grant PUD in writing of the Balancing Authority Area in which the Generating Facility will be located. If Customer elects to locate the Generating Facility in a Balancing Authority Area other than the Balancing Authority Area in which the Generating Facility is physically located, and if permitted to do so by the relevant transmission tariffs and business practices, all necessary arrangements, including but not limited to those set forth in Section 7 and Section 8 of this Agreement, and remote Balancing Authority Area generator interchange agreements, if applicable, and the appropriate measures under such agreements, shall be executed and implemented prior to the placement of the Generating Facility in the other Balancing Authority Area.
Balancing Authority Area Notification. At least three months before Initial Synchronization Date, the Interconnection Customer shall notify the CAISO and Participating TO in writing of the Balancing Authority Area in which the Large Generating Facility intends to be located. If the Interconnection Customer intends to locate the Large Generating Facility in a Balancing Authority Area other than the Balancing Authority Area within whose electrically metered boundaries the Large Generating Facility is located, and if permitted to do so by the relevant transmission tariffs, all necessary arrangements, including but not limited to those set forth in Article 7 and Article 8 of
Balancing Authority Area Notification. At least four months before Initial Synchronization Date, Interconnection Customer shall notify Operating Agent in writing of the Balancing Authority Area in which the Generating Facility will be located. All necessary arrangements, including but not limited to those set forth in Article 7 and Article 8 of this Agreement, and Balancing Authority Area generator interchange agreements, if applicable, and the appropriate measures under such agreements, shall be executed and implemented prior to the placement of the Generating Facility in the selected Balancing Authority Area.
Balancing Authority Area Notification. At least three months before Initial Synchronization Date, Interconnection Customer shall notify JPP in writing of the Balancing Authority Area in which the Large Generating Facility will be located. All necessary arrangements, including but not limited to those set forth in Article 9 and Article 10 of this LGIA, and Balancing Authority Area generator interchange agreements, if applicable, and the appropriate measures under such agreements, shall be executed and implemented prior to the placement of the Large Generating Facility in the Balancing Authority Area.
Balancing Authority Area Notification. At least three months before Initial Synchronization Date, Interconnection Customer shall notify APS and the CAISO in writing of the Balancing Authority Area in which the Project will be located, if and as permitted by the relevant transmission tariffs, including the APS and CAISO Tariffs. All necessary arrangements, including but not limited to those set forth in Articles 7 and 8 of this Agreement, and remote Balancing Authority Area generator interchange agreements, if applicable, and the appropriate measures under such agreements, shall be executed and implemented prior to the placement of Project in the designated Balancing Authority Area.
Balancing Authority Area Notification. At least three months before Initial Synchronization Date, Interconnection Customer shall notify Transmission Provider in
Balancing Authority Area Notification. At least three months before Initial Synchronization
Balancing Authority Area Notification. At least three months before Initial