To the extent that a failure or inability of Supplier to meet a Contract Milestone is a direct result of a Force Majeure Event or Spark’s breach of contract or negligence, Supplier will be entitled to a reasonable extension of time for that Contract Milestone and any other Contract Milestones that are similarly affected.
Without limiting any other rights or remedies Spark may have, if a Stage fails its Acceptance Tests a second time after being resubmitted under clause 27.4(b), Supplier will be deemed to have missed a Contract Milestone and failed to remedy the delay within the Milestone Remedy Period, and Spark will be entitled to terminate under clause 26.4 accordingly.
If any extension of a Contract Milestone of Telecom exceeds twenty (20) days then the parties will negotiate in good faith a partial payment of the fees related to the affected Contract Milestone.
Without limiting any other rights or remedies Entelar may have, if a Stage fails its Acceptance Tests a second timeafter being resubmitted under clause 27.4(b), Supplier will be deemed to have missed a Contract Milestone and failed to remedy the delay within the Milestone Remedy Period, and Entelar will be entitled to terminate under clause 26.4 accordingly.
The US$ Denominated L/C shall be provided prior to receipt of the first US$ payment under the Milestone Payment Schedule of the Supply Contract, shall become effective upon Supplier's receipt of the first US$ payment under the Milestone Payment Schedule of the Supply Contract and shall be increased from time to time by (i) the United States dollar amounts received by Contractor from Owner under the EPC Contract Milestone Payment Schedule for Payment Milestones nos.
The Project Master Schedule will also include Contract Milestone dates (Exhibit A) and the Design/Builder's Baseline Schedule, and shall be utilized by the District and the Design/Builder to identify any coordination issues and/or conflicts with other Project team members under separate contract.
To the extent that a failure or inability of Supplier to meet a Contract Milestone is a direct result of a Force Majeure Event or Entelar’s breach of contract or negligence, Supplier will be entitled to a reasonable extension of time for that Contract Milestone and any other Contract Milestones that are similarly affected.
If such cooperation by SOIL CONTRACTOR, under this GC-48.1, causes a change in the Work affecting the Soil Contract Schedule, SOIL CONTRACTOR shall be entitled to an adjustment to the Soil Contract Milestone Dates if and to the extent permitted under General Condition 32, titled CHANGES.
For the purpose of observing the status of Motorola's performance of work, Motorola shall afford a limited number of Iridium's employees or designees, as approved by Motorola and subject to the Article herein entitled EXPORT REGULATIONS, access to those Contract Milestone activities specified in Exhibit A Progress Payments, Milestones and Deliverable at Motorola's and its first-tier subcontractor's facilities subject to such subcontractor's approval and on a non-interference basis.
To the extent that a Schedule update pursuant to (d) above would show that a Contract Milestone would no longer be timely achieved, the Contractor must provide increased productivity proposals to bring the Schedule duration back to the original Schedule.