Examples of Final Acceptance Deadline in a sentence
Permitting or requiring the Contractor to continue and finish the Work or any part thereof after the Final Acceptance Deadline shall not act as a waiver of the Authority's right to receive Liquidated Damages hereunder or any rights or remedies otherwise available to the Authority.
On or before the Final Acceptance Deadline, the Contractor shall perform all Work, if any, which was waived for purposes of Substantial Completion and shall satisfy all of its other obligations under the Contract Documents, including ensuring that the Project has been completed and all Project components have been properly inspected and tested.
The Contractor shall diligently prosecute the Work so as to achieve Substantial Completion by the Substantial Completion Deadline and to achieve Final Acceptance by the Final Acceptance Deadline, as such dates may be extended in accordance with the Contract Documents.
Except as otherwise specifically provided in this Section and Section 13, CDOT shall have no obligation to extend the Completion Deadline and the Contractor shall not be relieved of its obligation to comply with the Contract Schedule and Final Acceptance Deadline by the applicable Completion Deadline for any reason.
Therefore, the Contractor and Authority have agreed to a stipulated amount to be paid by the Contractor in the event the Contractor fails to achieve Final Acceptance by the Final Acceptance Deadline.