MEP Fully Engineered Drawings definition

MEP Fully Engineered Drawings means a complete set of engineered MEP drawings, reflecting the final design of the MEP mechanical, plumbing and electrical to be incorporated into the T.I. Construction Drawings and incorporating the MEP/Lab Program as approved (or deemed approved) by Landlord. The MEP Fully Engineered Drawings shall be prepared by third (3rd) party engineers retained by Landlord for such purpose, in consultation with the Tenant’s MEP Consultant(s), if Tenant so requests. Landlord shall use commercially reasonable efforts to cause the MEP Fully Engineered Drawings to be completed within forty-five (45) days following Landlord’s approval (or deemed approval of Tenant’s Manufacturing/Lab Layout. Tenant shall approve or reasonably disapprove the MEP Fully Engineered Drawings or any revisions thereto within five (5) business days after Landlord or Landlord’s third (3rd) party consultant delivers the MEP Fully Engineered Drawings or such revisions to Tenant. If Tenant expressly and reasonably disapproves the MEP Fully Engineered Drawings, then Tenant shall, as part of its disapproval notice, (a) approve those portions which are acceptable, and (b) disapprove those portions which are not acceptable, specifying the reasons for such disapproval and describing the changes Tenant requests for each item disapproved. Tenant’s failure to reasonably disapprove the MEP Fully Engineered Drawings or any revisions thereto by written notice to Landlord (which notice shall specify in detail the reasonable reasons for Tenant’s disapproval) within said five (5) business day period shall be deemed to constitute Tenant’s approval of the MEP Fully Engineered Drawings or such revisions.

Examples of MEP Fully Engineered Drawings in a sentence

  • Tenant hereby assigns to Landlord all of Tenant’s present and future right, title and interest in and to the T.I. Plans and Specifications, including, without limitation, the Space Plan, the MEP/Lab Program, the MEP Fully Engineered Drawings and the T.I.

  • Plans and Specifications shall be prepared by Architect (provided that the Manufacturing/Lab Layout and the MEP/Lab Program shall be prepared by Tenant’s third (3rd) party consultant as set forth above and the MEP Fully Engineered Drawings shall be prepared by Landlord’s third (3rd) party consultant(s) as set forth above) or as otherwise agreed in a separate writing signed by Landlord and Tenant.

  • The MEP Fully Engineered Drawings shall be prepared by third (3rd) party engineers retained by Landlord for such purpose, in consultation with the Tenant’s MEP Consultant(s), if Tenant so requests.

  • Tenant shall approve or reasonably disapprove the MEP Fully Engineered Drawings or any revisions thereto within five (5) business days after Landlord or Landlord’s third (3rd) party consultant delivers the MEP Fully Engineered Drawings or such revisions to Tenant.

  • Landlord shall use commercially reasonable efforts to cause the MEP Fully Engineered Drawings to be completed within forty-five (45) days following Landlord’s approval (or deemed approval of Tenant’s Manufacturing/Lab Layout.

  • Tenant’s failure to reasonably disapprove the MEP Fully Engineered Drawings or any revisions thereto by written notice to Landlord (which notice shall specify in detail the reasonable reasons for Tenant’s disapproval) within said five (5) business day period shall be deemed to constitute Tenant’s approval of the MEP Fully Engineered Drawings or such revisions.

  • If Tenant expressly and reasonably disapproves the MEP Fully Engineered Drawings, then Tenant shall, as part of its disapproval notice, (a) approve those portions which are acceptable, and (b) disapprove those portions which are not acceptable, specifying the reasons for such disapproval and describing the changes Tenant requests for each item disapproved.

  • Accordingly, for each day which passes after the date(s)/time frames required for performance for such delivery of the MEP/Lab Program and Manufacturing/Lab Layout and/or approval of the Space Plan, the MEP Fully Engineered Drawings and the T.I. Construction Drawings, but prior to Tenant performing such obligations, shall constitute a Tenant Delay (as such term is defined hereinbelow).