During the performance of the contract, the Government shall have the right to perform a Physical Configuration Audit (PCA).
PRR IAW SOW Paragraph 16.1 FOB: Destination PSC CD: 5999 NET AMT ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT 7000 1 Each OPTION Physical Configuration Audit BY FFP Physical Configuration Audit (PCA) MK 235 MOD 17 & 18 Production Phase: PRR IAW SOW Paragraph 6.0 FOB: Destination PSC CD: 5999 NET AMT ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT 8000 Data Deliverables Prepare, maintain, and deliver data IAW CDRLS A001 through A007 and applicable Data Item Description (DID).
The first complete delivery shall be with the Physical Configuration Audit Summary Report (PCA).
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT 1000 MK 235 LCU Base Year (BY) FFP Procure, fabricate, assemble and conduct First Article Inspection (FAI) and Physical Configuration Audit (PCA) in accordance with (IAW) Statement of Work (SOW) sections 4.2 and 6.0 respectively.
Article Physical Configuration Audit (FA-PCA) The contractor shall conduct an FA-PCA.
The Physical Configuration Audit (PCA) shall be performed to verify the MBP and its configuration items (CIs) are accurate, complete, compatible, and that the CI has achieved the performance and functional characteristics defined in the functional configuration baseline.
Qualification of the Contractor and its facilities, as well as all subcontractors and their facilities, for this Build to Print (BTP) procurement will be established upon successful completion of Production Readiness Review (PRR) and the Government conducted Physical Configuration Audit (PCA) (see 3.4.2.2) and Functional Configuration Audit (FCA) (see 3.4.
The CMP shall address procedures for a Physical Configuration Audit (PCA) of the first production unit, Configuration Status Accounting (CSA) procedures and requirements outlined in Section 1.4.2. The CMP, PCA procedures, PCA data, CSA procedures, and CSA data shall be provided to the Government.
T able 1: Meetings and Reviews Post Award Conference Once 0 Quarterly In Process Review 90 calendar days after Post Award Conference then Quarterly 0 FAT Test Readiness Review Once** 0 System Verification Review Once** 0 Physical Configuration Audit Once** 0 Weekly Telecon Weekly 0 ** Once for each CWB configuration proposed by the Contractor.
The baseline is established at the acceptance of the Physical Configuration Audit report documenting the functional and physical characteristics of the DE system.