Preliminary drawings definition

Preliminary drawings means drawings which the Contractor submits to the Engineer in charge for approval and any drawings returned by the Engineer in charge marked "Preliminary" or not marked "Approved".
Preliminary drawings shall have the meaning assigned to such term in Section 5.7(b).
Preliminary drawings means the drawings prepared by the Contractor that are built on the Reference Drawings and accompany the Contractor’s Preliminary Design submissions.

Examples of Preliminary drawings in a sentence

  • Preliminary drawings of the proposed project, including a site plan, building elevations, and unit floor plans (including square footage of each unit).

  • Preliminary drawings of the finished project, including the site plan, floor plan and elevations drawn to scale, shall be submitted with the narrative.

  • Preliminary drawings, at a minimum including site plan, elevations and unit plans.

  • Said survey shall confirm benchmarks and spot elevations on selected structures; A written description of all permitting and code requirements for the Project; Preliminary drawings which illustrate all site development requirements including paving, grading, drainage, and utilities.

  • Preliminary drawings and specifications describing the proposed changes.

  • Preliminary drawings of the proposed project, including a site plan, building elevations, and unit floor plans (designate square footage).

  • Preliminary drawings, matrices, diagrams, and narratives describing the smoke control systems in the building (when applicable).

  • Preliminary drawings as listed below communicating design concepts accurately but not so detailed as to detract from understanding the form and function of structures.

  • Preliminary drawings, described above, shall be submitted in all of the following formats:□ Electronic format (pdf) o Single PDF file for all drawings specified above.o Separate, single PDF for specifications.□ Hard copyo Full set of architectural plans, 11”x17" scaled to fit.

  • Preliminary drawings of the Site Work are attached as Exhibit G (the “Preliminary Plans”).


More Definitions of Preliminary drawings

Preliminary drawings. Submit three (3) paper copies and an electronic PDF version of the Preliminary plans and specifications to City for review and comment.
Preliminary drawings shall have the meaning assigned to such term in Section 5.9(b). [Note: This definition is to be included in all Continuing Term Separate Leases.]
Preliminary drawings means accurate delineation drawings of proposed improvements necessary for filing formal application.
Preliminary drawings means the outline specifications and preliminary drawings prepared on behalf of Landlord and approved by Tenant for the Improvements to be constructed by Landlord which are described in attached EXHIBIT B-1.
Preliminary drawings or “Design Drawings” clearly indicated.
Preliminary drawings means drawings to be provided by the Contractor to the Employer’s Representative for review and comment.

Related to Preliminary drawings

  • Preliminary Work means all work done in the concept and preparatory stages (including non-exhaustively design, artwork, colour matching).

  • Construction Drawings means those drawings containing the technical details associated with the design, construction and installation of the Infrastructure;

  • Working Drawings means the final working drawings approved by Landlord, as amended from time to time by any approved changes thereto, and “Work” means all improvements to be constructed in accordance with and as indicated on the Working Drawings, together with any work required by governmental authorities to be made to other areas of the Building as a result of the improvements indicated by the Working Drawings. Landlord’s approval of the Working Drawings shall not be a representation or warranty of Landlord that such drawings are adequate for any use or comply with any Law, but shall merely be the consent of Landlord thereto. Tenant shall, at Landlord’s request, sign the Working Drawings to evidence its review and approval thereof. After the Working Drawings have been approved, Tenant shall cause the Work to be performed in accordance with the Working Drawings.

  • Contract Drawings means only those drawings specifically entitled as such and listed in the Specifications or in any Addendum, or any drawings furnished by the Commissioner, pertaining or supplemental thereto.

  • Preliminary Title Report A report issued by a title insurance company in anticipation of issuing a Title Insurance policy which evidences existing liens and gives a preliminary opinion as to the absence of any encumbrance on title to a Mortgaged Property, except liens to be removed on or before purchase or refinance, as the case may be, by the Borrower and Permitted Encumbrances.

  • Space Plan herein means, to the extent required by the nature of the Work, detailed plans (including any so-called “pricing plans”), including a fully dimensioned floor plan and drawn to scale, showing: (i) demising walls, interior walls and other partitions, including type of wall or partition and height, and any demolition or relocation of walls, and details of space occupancy and density, (ii) doors and other openings in such walls or partitions, including type of door and hardware, (iii) electrical and computer outlets, circuits and anticipated usage therefor, (iv) any special purpose rooms, any sinks or other plumbing facilities, heavy items, and any other special electrical, HVAC or other facilities or requirements, including all special loading and related calculations, (v) any space planning considerations to comply with fire or other codes or other governmental or legal requirements, (vi) finish selections, and (vii) any other details or features requested by Architect, Engineer or Landlord, or otherwise required, in order for the Space Plan to serve as a basis for Landlord to approve the Work, and for Tenant to contract and obtain permits for the Work, or for the Space Plan to serve as a basis for preparing Construction Drawings.

  • Preliminary Report means the communication used for the prompt dissemination of data obtained during the early stages of the investigation;

  • Shop Drawings means drawings, submitted to the PHA by the Contractor, subcontractor, or any lower tier subcontractor, showing in detail (1) the proposed fabrication and assembly of structural elements and (2) the installation (i.e., form, fit, and attachment details) of materials of equipment. It includes drawings, diagrams, layouts, schematics, descriptive literature, illustrations, schedules, performance and test data, and similar materials furnished by the Contractor to explain in detail specific portions of the work required by the contract. The PHA may duplicate, use, and disclose in any manner and for any purpose shop drawings delivered under this contract.

  • As-built drawings, as used in this clause, means drawings submitted by the Contractor or subcontractor at any tier to show the construction of a particular structure or work as actually completed under the contract. “As-built drawings” shall be synonymous with “Record

  • Preliminary plat means a map showing the salient features of a proposed subdivision submitted to an approving authority for purposes of preliminary consideration.

  • Preliminary Plans means a site plan, architectural floor plans, elevations, outline specifications and a cost estimate for each utility, site development, conversion, and remodeling project. The drawings shall be sufficiently descriptive to accurately convey the location, scope, cost and the nature of the improvement being proposed.

  • Punch List means the list of items, prepared in connection with the inspection of the Project by the Owner’s Representative or Architect in connection with Substantial Completion of the Work or a portion of the Work, which the Owner’s Representative or Architect has designated as remaining to be performed, completed or corrected before the Work will be accepted by the Owner.

  • Preliminary assessment means the first phase in the process of identifying areas of concern and determining whether contaminants are or were present at a site or have migrated or are migrating from a site, and shall include the initial search for and evaluation of, existing site specific operational and environmental information, both current and historic, to determine if further investigation concerning the documented, alleged, suspected or latent discharge of any contaminant is required. The evaluation of historic information shall be conducted from 1932 to the present, except that the department may require the search for and evaluation of additional information relating to ownership and use of the site prior to 1932 if such information is available through diligent inquiry of the public records.

  • Construction Schedule means a construction schedule indicating the planned start and completion dates of the major activities of the Work as set out in Appendix [ ], a future Appendix;

  • Record Drawings means a reproducible set of Construction Documents into which the Architect has incorporated: (a) clarifications, sketches and other Modifications made by the Architect during the Construction Phase; and (b) significant changes in the Work made during construction as shown on the Trade Contractor’s As-Built Drawings.

  • Shop Drawing means any and all drawings, diagrams, layouts, explanations, illustrations, manufacturer's drawings or other written or graphic materials which illustrate any portion of the construction work.

  • Final Drawing has the meaning specified in Section 3.05(i).

  • Correctional facility means a facility operated under the management and control of the Virginia Department of Corrections.

  • The DRAWINGS / MAPS means the drawing/map or drawings/maps mentioned in NIT and any modifications of them approved by the Employer or any further Working drawings/maps or sketches by the Employer or any further working drawings/maps or sketches which may be furnished or approved in writing by the Employer.

  • Construction project means the same as that term is defined in Section 38-1a-102.

  • Sign face means the entire area of the surface of a sign including the border or frame together with any material forming an integral part of the background of the display or used to differentiate the sign from the backdrop or building against which it is erected. Where a sign is composed of individually installed letters, numerals or shapes, the sign face shall mean the area of the smallest polygon containing a maximum of eight (8) right angle sides that enclose the groupings of letters, numerals or shapes;

  • Project Schedule means a document that, with respect to each Phase of the Project, identifies, coordinates and integrates the anticipated design and construction schedules, the Contracting Authority’s and Owner's responsibilities, government authority reviews and other activities as are necessary for the timely completion of the Work.

  • Preliminary Closing Statement shall have the meaning set forth in Section 2.3(a).

  • Maximum Drawing Amount means the maximum aggregate amount that the beneficiaries may at any time draw under outstanding Letters of Credit, as such aggregate amount may be reduced from time to time pursuant to the terms of the Letters of Credit.

  • Preliminary Approval means the Court’s Order Granting Preliminary Approval of the Settlement.