Related Permits definition
Examples of Related Permits in a sentence
The Contractor will, as part of the Work, provide all assistance reasonably requested by BC Hydro to obtain, maintain and renew Project Related Permits as required for the performance of the Work.
BC Hydro has obtained, or will obtain, the Permits listed in Appendix 2-3 [Project Related Permits] (the “Project Related Permits”).
Therefore, the Entertainment Commission agrees to be responsible for all costs associated with any actions on the part of the Entertainment Commission pursuant to the MOU, including, but not limited to, the issuance or denial, the suspension and/or revocation, the transfer, or an application for amendments to Entertainment Related Permits.
However, if the Contractor wishes to request that BC Hydro seek changes to Project Related Permits, such will be at the Contractor’s sole risk and cost, including all risk of delay or impact to the time for performance of the Work, unless it would be impossible for the Contractor to perform the Work in accordance with the Contract without the requested changes to the Project Related Permits, in which case such changes will be a Change to which the provisions of Schedule 12 [Changes] will apply.
The San Francisco Port Commission has delegated the responsibility to hear appeals of any Entertainment Commission decisions regarding the issuance, denial, suspension, and/or revocation, transfer, and applications for amendments of Entertainment Related Permits on Port property in a manner that is consistent with the procedures set forth in San Francisco Administrative Code Chapter 90, and the San Francisco Police Code Articles 1, 15, 15.1, and 15.
For certainty, the Contractor will be solely responsible for the costs of obtaining, maintaining and renewing all Permits, other than the Project Related Permits.
BC Hydro will maintain and renew, at BC Hydro’s cost, the Project Related Permits as required for the performance of the Work.
For certainty, the Contractor will be solely responsible for all risks and costs of obtaining, maintaining and renewing all Permits, other than the Project Related Permits.
Except as expressly set out otherwise in Appendix 2-3 [Project Related Permits], BC Hydro will maintain and renew, at BC Hydro’s cost, the Project Related Permits as required for the performance of the Work.
In general, the time and difficulty of obtaining changes to Project Related Permits is prohibitive to seeking such changes.