Examples of Satellite Test Plan in a sentence
The price for Ground Storage includes all costs associated with Ground Storage for the applicable period noted Table 34-4 below, as well as maintenance of critical units (for instance, the batteries) while in storage, but does not include periodic testing or the costs related to the post-Ground Storage testing as set forth in Exhibit D (Satellite Test Plan).
In the event there is no eclipse season during the Satellite IOT period, then Boeing shall conduct the IOT Eclipse Test set forth in Section 6.2.1 of Exhibit D (Satellite Test Plan) with respect to the Satellite during the first eclipse season after IOT is otherwise completed and provide Customer the results thereof.
If there is an eclipse season during the Satellite IOT period, Boeing shall conduct the eclipse test set forth in Exhibit D (Satellite Test Plan) during IOT (the “IOT Eclipse Test”).
In the event there is no eclipse season during the SATMEX 8 Satellite IOT period, then Contractor shall conduct the IOT eclipse test, as set forth in the applicable parts of section 7.7 of Exhibit D, SATMEX 8 Satellite Test Plan, with respect to the SATMEX 8 Satellite during the first eclipse season after IOT is otherwise completed.
When IOT has been completed for the SATMEX 8 Satellite in accordance with Exhibit D, SATMEX 8 Satellite Test Plan, Contractor shall submit and certify the required IOT results to Purchaser.
Upon Purchaser’s direction to Contractor to remove the Satellite from Storage, Contractor shall, (i) conduct the post-storage verification tests as set forth in Exhibit D, SATMEX 8 Satellite Test Plan, (ii) refurbish and retest the refurbishment as needed due to Storage and (iii) take appropriate corrective measures pursuant to Article 31.
Purchaser may direct Contractor, through a Change Request, to perform additional post-storage verification testing in addition to those tests described in Section 7 (Storage and Post-Storage Test) of Exhibit D, Satellite Test Plan.
Storage for a Satellite shall be performed at a Contractor controlled facility and shall be performed pursuant to Section 7 (Storage and Post-Storage Test) of Exhibit D, Satellite Test Plan, the Satellite storage plan (“Satellite Storage Plan”).
Upon Purchaser direction to Contractor to remove the Satellite from Storage, Contractor shall conduct the post-storage verification tests as set forth in Section 7 (Storage and Post-Storage Test) of Exhibit D, Satellite Test Plan, and ship the Satellite to the designated Launch Site (or to such other location as Purchaser may direct).
Table 34-4 Description Price (U.S.$ Millions) (***) (***) (***) (***) (***) (***) (***) (***) (***) (***) (***) (***) (***) (***) (***) Customer may request Boeing, through a Major Change Order in accordance with Article 24.1 (Material Changes Requested by Customer), to perform additional post-Ground Storage verification testing in addition to those tests described in Exhibit D (Satellite Test Plan).