Examples of Scheduled Unloading Date in a sentence
Customer may propose to SABINE to change any such Scheduled Unloading Date, and SABINE agrees to give due consideration to, and use reasonable efforts to accommodate, such change.
SABINE shall berth an LNG Vessel arriving after its Scheduled Unloading Date at the first opportunity that SABINE reasonably determines such LNG Vessel will not cause the Sabine Pass Facility to lack either berthing space or sufficient storage capacity to allow unloading of an LNG vessel from the priority group in Section 8.6(b)(i).
In such an event references in this New Shipper Access Code to the Scheduled Unloading Date shall be to the first of such Berthing Slots, and the second of such Berthing Slots shall not have a separate Scheduled Unloading Date.
SABINE shall berth an LNG Vessel arriving before or during its Scheduled Unloading Date at the first opportunity that SABINE determines such LNG Vessel will not interfere with berthing and unloading of any other scheduled LNG vessel with a higher berthing priority.
Moreover, if the vessel that Customer proposes to use as an LNG Vessel has not, within the immediately preceding Contract Year, delivered LNG to the Sabine Pass Facility, Customer shall notify SABINE thereof at least sixty (60) days prior to the applicable Scheduled Unloading Date.
The second berthing priority on any day the be for LNG vessels with a Scheduled Unloading Date on currency future day.
At any time following the issuance of the Annual Delivery Program and any applicable Three Month Unloading Schedule, Seller’s Scheduling Representative may submit to Buyer a written request to change a Scheduled Unloading Date to any Available Unloading Date (such request to change, a “Seller Unloading Date Change Request”).
The subject Application reflects that highly collaborative process that has enabled a major Site Plan to be brought to the Planning Board only six months after its filing.
For the avoidance of doubt, Buyer’s Facility will allow berthing and unloading of LNG vessels from the priority group in Sections 5.5(b)(ii) above only if, in the reasonable judgment of Buyer’s Facility, such berthing and unloading will not cause Buyer’s Facility to lack either berthing space or sufficient storage capacity to allow unloading of an LNG vessel on its Scheduled Unloading Date.
Buyer’s Facility shall berth an LNG Vessel arriving after its Scheduled Unloading Date at the first opportunity that Buyer’s Facility reasonably determines such LNG Vessel will not cause Buyer’s Facility to lack either berthing space or sufficient storage capacity to allow unloading of an LNG vessel from the priority group in Section 5.5(b)(i).