N-7, this chapter applies except that the powers of the Surface Rights Board shall be exercised by the board, committee, panel or other body authorized by the National Energy Board Act, R.S.C. 1985, c.
Under a Right of Entry Order the Surface Rights Board has historically awarded a 100% the land value of the right of way for compensation, due to the permanent nature of the work space.
In 2013 a case proceeded to Court of Queen’s Bench on appeal of a Surface Rights Board Decision, whereby the Operator argued work space should be paid at a lesser or reduced value (50% value of the ROW).
When a right of entry order is granted by the Surface Rights Board that includes work space, the work space is granted as permanent right of way, due to the fact the work space area will not be reclaimed until the associated development is also reclaimed.
The courts upheld the Surface Rights Board decision stating that the permanent nature of work space The Court confirmed that the work space remains in the permanent possession of the Operator until a Reclamation Certificate issues as some rights are retained by the Operator.
Not only are freeholders not consulted before posting, but if approval for a project is granted by the Alberta Energy Regulator, freeholders cannot block surface access through Surface Rights Board proceedings.88 Moreover, the CMA provides pre-posting intervention rights that are not oth- erwise (currently) accorded to any other aborigi- nal peoples in Alberta.
If the landowner and the company are unsuccessful in negotiating compensation, the company may obtain a Right of Entry Order through the Surface Rights Board (SRB) under the Surface Rights Act once an AER licence has been approved.
This option is not available to agreements negotiated prior to November 2013 or orders granted by the Surface Rights Board (SRB).
The damages, proceeds, consideration and award, whether awarded by the Land Compensation Board, the Surface Rights Board, a court or otherwise, resulting from any expropriation are, to the extent of the full amount of the monies and obligations secured by this mortgage and remaining unpaid on the date of such expropriation, hereby assigned by the Mortgagor to the Mortgagee and will be paid immediately to the Mortgagee.
This option is not available to orders granted by the Surface Rights Board (SRB) or commitments made to adjacent landowners or in a construction report.