Examples of Target Service Availability Date in a sentence
Notwithstanding the Service Availability Requirements may have been met in relation to a New Project Facility, a Service Availability Date may only fall on a date on or after the Target Service Availability Date for such New Project Facility unless the Authority otherwise agrees (in its absolute discretion).
The Contractor shall provide to the Authority, not later than one month prior to each Target Service Availability Date, an operating and maintenance manual setting out the procedures for providing the Services at the relevant New Project Facility which if complied with will deliver the Services in accordance with the terms of this Agreement (Operating Manual).
If approval is not obtained by the Contractor for the new proposal then it is almost certain that they will be unable to complete the new school facility for the contract Target Service Availability Date (TSAD).
The Contractor shall not be entitled to propose a variation to the Contractor’s Proposals or the Construction Programme (other than where necessitated by a Discriminatory Change of Law or as a direct consequence of an variation to the Contractor’s Proposals or the Construction Programme which is implemented at the request of the Authority) which would delay [a/the] Target Service Availability Date or would lead to an increase in the Unitary Charge.
The Authority shall not be entitled to issue the Pre-Agreed Variation Notice later than six (6) Months prior to the Target Service Availability Date for Elgin Academy.
To the extent that the Relocation Date is delayed as a direct result of a Relief Event, a Compensation Event or a Force Majeure Event the provisions of clause 17 shall apply mutatis mutandis and the Relocation Date shall be revised in the same manner as a revision would be made to the Target Service Availability Date (notwithstanding that all the Acceptance Certificates may at that point have been issued).
The Service Availability Date for any New Facility shall be the date on which an Acceptance Certificate is issued in respect of that New Facility PROVIDED THAT such date shall be no earlier than the relevant Target Service Availability Date.
If the parties cannot agree the extent of the relief required, or the Authority disagrees that a Relief Event has occurred or that the Contractor is entitled to any relief under this Clause (including postponement of any relevant Target Service Availability Date, Target External Works Availability Date, Target Grass Pitch Availability Date or Deadline Date) the matter shall be resolved in accordance with the Dispute Resolution Procedure.
If the Parties cannot agree the extent of the relief required, or the Authority disagrees that a Relief Event has occurred or that the Contractor is entitled to any extension of the Target Practical Completion Date, Target Service Availability Date and/or the Longstop Date and/or any relief under this clause the matter shall be resolved in accordance with the Dispute Resolution Procedure.
Performance Monitoring 2.1 The parties shall in respect of each of the Services, no later than six months before the first Target Service Availability Date, agree a detailed monitoring and reporting procedure which shall: 2.1.1 comply in all material respects with this Part 5 of Section A of Schedule Part 7; and 2.1.2 be based on methods and recording frequencies to be agreed.