Examples of Template Call Off Terms in a sentence
Subject to paragraphs 1 to 5 above, a Contracting Body may award a Call Off Contract with the Supplier by sending (including electronically) a signed order form substantially in the form (as as may be amended or refined by the Contracting Body in accordance with paragraph 2.1.2 above) of the Template Order Form set out in Framework Schedule 4 (Template Order Form and Template Call Off Terms).
If the Customer requires the assistance of the Supplier to fill in certain sections of the Template Call Off Order Form and Template Call Off Terms prior to those becoming the Call Off Contract, this will be agreed between the parties.
The Authority will not be party to, nor have any involvement in the management or administration of (any Call Off Agreement involving Other Contracting Bodies, save where expressly mentioned in Framework Schedule 1 (Goods and/or Services and Key Performance Indicators) and the Template Call Off Terms (as these may be refined by a Contracting Body under the Further Competition Procedure).
If you place repeat Orders of the same nature which contain repeat requirements, consider creating a customised set of amended and/or refined Template Call Off Terms or a Call Off Schedule containing those amendments or refinements (including incorporating any Alternative or Additional Clauses from Call Off Schedule 14 (Alternative and/or Additional Clauses)) which you can use with every Order.
Guidance Note: Include any other provisions in addition to, modification or substitution of the Template Call Off Terms prior to those becoming the Call Off Terms of the Call Off Contract.
For the avoidance of doubt, Clause 1.2.11 of the Framework Agreement applies so that any permitted changes by the Customer to the Template Call Off Terms and the Template Call Off Form under the Framework Agreement prior to the Parties entering this Call Off Contract shall not constitute any conflict with the provisions of the Framework Agreement.
See also Clauses 8.1 and/or Error: Reference source not found of the Template Call Off Terms in relation to time of Delivery and consider if you should make 'time of the essence” in respect of any Milestone Dates.] [Guidance Note: Consider if you should include any Milestone Payments for Achievement of certain Milestones.
See also Clauses 7.2 and/or 8.2 of the Template Call Off Terms in relation to time of Delivery and consider if you should make 'time of the essence in respect of any Milestone Dates.] [Guidance Note: Consider if you should include any Milestone Payments for Achievement of certain Milestones.
Clause 14 of the Template Call Off Terms provides the Customer with a right to retain and deduct Call Off Contract Charges as compensation or terminate this Call Off Contract for Material Breach in the event of a Critical Service Level Failure.
See Clause 45.5 of the Template Call Off Terms and Call Off Schedule 10 (Exit Management).