The contractor may within 30 days of the receipt of the decision of The Assistant General Manager, SBI Infra Management Solutions Pvt.
The Assistant General Manager (Premises& Estate) shall give his decision in writing on the claims notified by the contractor.
The said notice shall give full particulars of the claim, grounds on which it is based and detailed calculations of the amount claimed and the contractor shall not be entitled to raise any claim nor shall the bank be in any way liable in respect of any claim by the contractor unless notice of such claim have been given by the Contractor The Assistant General Manager, SBI Infra Management Solutions Pvt.
Ltd, 4th Floor, State Bank of India, LHO Building, Poojappura, Thiruvananthapuram – 695012 submit his claims to the conciliating authority namely the Circle Development Officer, State Bank of India, Local Head Office, Thiruvananthapuram for conciliation along with all details and copies of correspondence exchanged between him and The Assistant General Manager, SBI Infra Management Solutions Pvt.
If the contractor considers that he is entitled to any extra payment or compensation in respect of the works over and above the amounts admitted as payable by the Architect or in case the contractor wants to dispute the validity of any deductions or recoveries made or proposed to be made from the contract or raise any dispute, the contractor shall forthwith give notice in writing of his claim, or dispute to The Assistant General Manager, SBI Infra Management Solutions Pvt.
If the contractor considers that he is entitled to any extra payment or compensation in respect of the works over and above the amounts admitted as payable by the SBIIMS or in case the contractor wants to dispute the validity of any deductions or recoveries made or proposed to be made from the contract or raise any dispute, the contractor shall forthwith give notice in writing of his claim, or dispute to The Assistant General Manager, SBI Infra Management Solutions Pvt.
The Assistant General Manager shall give his decision in writing on the claims notified by the contractor.The contractor may within 30 days of the receipt of the decision of the Assistant General Manager submit his claims to the conciliating authority namely the DGM & Circle Development Officer for conciliation along with all details and copies of correspondence exchanged between him and the Assistant General Manager .
The contractor shall be deemed to have waived and extinguished all his rights in respect of any claim not notified to The Assistant General Manager, SBI Infra ManagementSolutions Pvt.
Ltd, 4th Floor, State Bank of India LHO Building, Poojappura, Thiruvananthapuram – 695012submit his claims to the conciliating authority namely the Circle Development Officer, State Bank of India, Local Head Office, Thiruvananthapuram for conciliation along with all details and copies of correspondence exchanged between him and The Assistant General Manager, SBI Infra Management Solutions Pvt.
The Assistant General Manager shall give his decision in writing on the claims notified by the contractor.