Examples of Western Sustainable Power in a sentence
TransAlta Renewables entered into the Purchase and Sale Agreement pursuant to which we acquired the Initial Assets by purchasing all of the issued and outstanding shares of Western Sustainable Power and CHD from TransAlta for approximately $1.7 billion which was determined through negotiations with the underwriting syndicate involved in the Offering after taking into consideration, among other things, the valuation multiples of publicly traded companies that were deemed comparable to the Initial Assets.
S I G N I F I C A N T A C Q U I S I T I O N The Company and TransAlta will enter into the Purchase and Sale Agreement, pursuant to which the Company will indirectly acquire certain wind and hydroelectric power generation assets held by Western Sustainable Power Inc.
The Company will complete this acquisition by acquiring all of the issued and outstanding common shares of Western Sustainable Power and CHD (the “Acquisition”), which are entities that directly and indirectly own the Acquired Assets.
The Notes may be issued in bearer form only ("Bearer Notes"), in bearer form exchangeable for Registered Notes (as defined herein) ("Exchangeable Bearer Notes") or in registered form only ("Registered Notes").
TransAlta Renewables entered into the Purchase and Sale Agreement pursuant to which we acquired the Initial Assets by purchasing all of the issued and outstanding shares of Western Sustainable Power and CHD from TransAlta for approximately $1.7 billion.
Pursuant to Approval U2013-411,1 and Licence 24622-D02-2019,2 Western Sustainable Power Corporation owns and operates the Summerview Wind Power Plant and the Summerview 354S Substation in the Pincher Creek area.
As well, the Commission transferred the connection order for the Summerview 354S Substation from TransAlta Corporation to Western Sustainable Power Corporation.
Latitude 49.582°N Longitude 113.435°W Refer to Appendix A for a map of the facility OwnershipThe Project is owned by Western Sustainable Power Inc., a wholly owned subsidiary of TransAlta Renewables Inc.
In this decision, the Alberta Utilities Commission considers whether to approve an application from Western Sustainable Power Corporation to alter its Summerview Wind Power Plant by adding an energy storage project designated as the WindCharger Battery Storage Project.
Pursuant to sections 11 and 19 of the Hydro and Electric Energy Act, the Commission approves the application and grants Western Sustainable Power Corporation the approval set out in Appendix 1 – Summerview Wind and Battery Storage Power Plant – Power Plant Approval 24454-D02-2019 – November 7, 2019 (Appendix 1 will be distributed separately).