In consideration of the [Insert name of the Bidder] (hereinafter referred to as ‘selected Wind Power Developer') submitting the response to RfS inter alia for [Insert name of the RfS] of the capacity of ………..
Power Project (To be issued by the SECI on its letterhead) Ref: Dated: This is to certify that M/s (insert name of the WPD) has successfully commissioned connected Wind Power Project [Project ID: (insert installed Project capacity) MW ISTS- ] consisting of (insert no.
This compensation shall not be applicable in events of Force Majeure identified under this Agreement, affecting supply of Wind Power by WPD.
The Guarantor Bank shall make payment hereunder on first demand without restriction or conditions and notwithstanding any objection by [Insert name of the selected Wind Power Developer / Project Company as applicable] and/or any other person.
The Government of India has announced the Policy for promotion of the Wind Power in the country and has provided a target to achieve an aggregate installed capacity of 60 GW by the year 2022.
The Wind Power Developer shall, on his own, obtain permissions/ sanctions from Government authorities, if any required for establishing the project.
Wind Power Developer (WPD) shall give to CTU/PGCIL, State Nodal Agency (SNA), Concerned RLDC and SECI at least thirty (30) days’ final written notice, of the date on which it intends to synchronize the Project to the Grid System.
Commercial Operation Date (COD) of MW ISTS-Connected Wind Power Project is to be considered from 00:00 hrs of .
As per the terms of the RfS, the [insert name & address of bank] hereby agrees unequivocally, irrevocably and unconditionally to pay to SECI at [Insert Name of the Place from the address of the SECI] forthwith on demand in writing from SECI or any Officer authorized by it in this behalf, any amount up to and not exceeding Indian Rupees [Total Value] only, on behalf of M/s _ [Insert name of the selected Wind Power Developer / Project Company].
Wind Power Developer shall ensure that the Wind Turbine Generators (WTGs) have been installed and completed in all aspects and the Project is synchronized to the grid in order for it to be declared as being commissioned.