Accepted Program. At the time period stated in the Contract Data, the Contractor submits his program for the Project Manager’s
Accepted Program. At the time period stated in the Contract Data, the Contractor submits his program for the Project Manager’s acceptance. A summary program (Hammock) is provided where the summarised activities including the possession dates, and major interfaces of services and or other contracts logically required for the completion of the contract are clearly shown.