Actions if Not Resolved. If a claim has not been resolved, the party making the claim shall, within ten (10) days after the Project Manager's preliminary response, take one or more of the following actions: submit additional supporting data requested by the Project Manager; modify the initial claim; or notify the Project Manager that the initial claim stands.
Appears in 3 contracts
Samples: Contract for Sidewalk and Driveway Concrete Repairs, Contract for Generator Installation, Contract for Construction Services
Actions if Not Resolved. If a preliminary claim has not been resolved, the party making the claim shall, within ten (10) days after the Project Manager's preliminary response, take one or more of the following actions: submit additional supporting data requested by the Project Manager; modify the initial preliminary claim; or notify submit a formal claim to the Project Manager that the initial claim standsCity pursuant to paragraph 42(b).
Appears in 1 contract