Common use of Activity Information Clause in Contracts

Activity Information. Developer shall divide the Work into activities with appropriate logic 26 ties to show Developer’s overall approach to the planning, scheduling, and execution of 27 the Work. Developer shall base duration and logical relationships of the Project activities 28 (or summaries at phase level) on the actual duration and relationships anticipated. Each 29 activity must have a duration not exceeding 20 Business Days.

Appears in 3 contracts

Samples: Design Build Maintain Agreement, Design Build Maintain Agreement, Design Build Maintain Agreement

AutoNDA by SimpleDocs

Activity Information. Developer shall divide the Work into activities with appropriate logic 26 10 ties to show Developer’s overall approach to the planning, scheduling, and execution of 27 11 the Work. Developer shall base duration and logical relationships of the Project activities 28 12 (or summaries at phase level) on the actual duration and relationships anticipated. Each 29 13 activity must have a duration not exceeding 20 Business Days.

Appears in 3 contracts

Samples: Design Build Maintain Agreement, Design Build Maintain Agreement, Design Build Maintain Agreement

Activity Information. Developer shall divide the Work into activities with appropriate logic 26 13 ties to show DeveloperXxxxxxxxx’s overall approach to the planning, scheduling, and execution of 27 14 the Work. Developer shall base duration and logical relationships of the Project activities 28 15 (or summaries at phase level) on the actual duration and relationships anticipated. Each 29 16 activity must have a duration not exceeding 20 Business Days.

Appears in 2 contracts

Samples: Design Build Maintain Agreement, Design Build Maintain Agreement

Activity Information. Developer shall divide the Work into activities with appropriate logic 26 12 ties to show DeveloperXxxxxxxxx’s overall approach to the planning, schedulingxxxxxxxxxx, and execution of 27 13 the Work. Developer shall base duration and logical relationships of the Project activities 28 14 (or summaries at phase level) on the actual duration and relationships anticipated. Each 29 15 activity must have a duration not exceeding 20 Business Days.

Appears in 1 contract

Samples: Design Build Maintain Agreement

Activity Information. Developer shall divide the Work into activities with appropriate logic 26 17 ties to show Developer’s overall approach to the planning, scheduling, and execution of 27 18 the Work. Developer shall base duration Duration and logical relationships of the Project activities 28 (or summaries at 19 phase level) on the actual duration and relationships anticipated. Each 29 activity must 20 have a duration not exceeding 20 Business Days.

Appears in 1 contract

Samples: Design Build Maintain Agreement

AutoNDA by SimpleDocs

Activity Information. Developer shall divide the Work into activities with appropriate logic 26 12 ties to show Developer’s overall approach to the planning, scheduling, and execution of 27 13 the Work. Developer DurationDeveloper shall base duration and logical relationships of the Project 14 activities 28 (or summaries at phase level) on the actual duration and relationships 15 anticipated. Each 29 activity must have a duration not exceeding 20 Business Days.

Appears in 1 contract

Samples: Design Build Maintain Agreement

Activity Information. Developer shall divide the Work into activities with appropriate logic 26 14 ties to show Developer’s overall approach to the planning, scheduling, and execution of 27 15 the Work. Developer shall base duration and logical relationships of the Project activities 28 16 (or summaries at phase level) on the actual duration and relationships anticipated. Each 29 17 activity must have a duration not exceeding 20 Business Days.

Appears in 1 contract

Samples: Design Build Maintain Agreement

Activity Information. Developer shall divide the Work into activities with appropriate logic 26 8 ties to show Developer’s overall approach to the planning, scheduling, and execution of 27 9 the Work. Developer shall base duration Duration and logical relationships of the Project activities 28 (or summaries at 10 phase level) on the actual duration and relationships anticipated. Each 29 activity must 11 have a duration not exceeding 20 Business Days.

Appears in 1 contract

Samples: Design Build Maintain Agreement