Affected Party. 11.2.1 An Affected Party means any of the Long Term Transmission Customers or the TSP whose performance has been affected by an event of Force Majeure. 11.2.2 An event of Force Majeure affecting the CTU/STU or any agent of the Long Term Transmission Customers, which has affected the Interconnection Facilities, shall be deemed to be an event of Force Majeure affecting the Long Term Transmission Customers. 11.2.3 Any event of Force Majeure shall be deemed to be an event of Force Majeure affecting the TSP only if the Force Majeure event affects and results in, late delivery of machinery and equipment for the Project or construction, completion, commissioning of the Project by Scheduled COD and/or operation thereafter ;
Appears in 6 contracts
Samples: Transmission Service Agreement, Transmission Service Agreement, Transmission Service Agreement
Affected Party. 11.2.1 An Affected Party means any of the Long Term Transmission Customers or the TSP whose performance has been affected by an event of Force Majeure.
11.2.2 An event of Force Majeure affecting the CTU/CTU/ STU or any agent of the Long Term Transmission Customers, which has affected the Interconnection Facilities, shall be deemed to be an event of Force Majeure affecting the Long Term Transmission Customers.
11.2.3 Any event of Force Majeure shall be deemed to be an event of Force Majeure affecting the TSP only if the Force Majeure event affects and results in, late delivery of machinery and equipment for the Project or construction, completion, commissioning of the Project by Scheduled COD and/or and/ or operation thereafter ;
Appears in 3 contracts
Samples: Transmission Service Agreement, Transmission Service Agreement, Transmission Service Agreement
Affected Party. 11.2.1 An Affected Party means any of the Long Term Transmission Customers or the TSP whose performance has been affected by an event of Force Majeure.
11.2.2 An event of Force Majeure affecting the CTU/STU or any agent of the Long Term Transmission Customers, which has affected the Interconnection Facilities, shall be deemed to be an event of Force Majeure affecting the Long Term Transmission Customers.
11.2.3 Any event of Force Majeure shall be deemed to be an event of Force Majeure affecting the TSP only if the Force Majeure event affects and results in, late delivery of machinery and equipment for the Project or construction, completion, commissioning of the Project by Scheduled COD and/or operation thereafter thereafter;
Appears in 1 contract
Samples: Transmission Service Agreement
Affected Party. 11.2.1 An Affected Party means any of the Long Term Transmission Customers or the TSP whose performance has been affected by an event of Force Majeure.
11.2.2 An event of Force Majeure affecting the CTU/STU or any agent of the Long Term Transmission Customers, which has affected the Interconnection Facilities, shall be deemed to be an event of Force Majeure affecting the Long Term Transmission Customers.
11.2.3 Any event of Force Majeure shall be deemed to be an event of Force Majeure affecting the TSP only if the Force Majeure event affects and results in, late delivery of machinery and equipment for equipmentfor the Project or construction, completion, commissioning of the Project by Scheduled COD and/or operation thereafter thereafter;
Appears in 1 contract
Samples: Transmission Service Agreement