Allocation of Costs of Approved Interregional Transmission Projects. The costs of Interregional Transmission Projects, as defined in the Protocol, evaluated under the Protocol and selected by PJM and NYISO (the “Regions”) in their regional transmission plans for purposes of cost allocation under their respective tariffs shall, when applicable, be allocated to the PJM Region and the NYISO Region in accordance with the cost allocation principles of FERC Order No. 1000, as follows: (a) To be eligible for interregional cost allocation pursuant to this Section 35.10.2, an Interregional Transmission Project must be selected in both the PJM and NYISO regional transmission plans for purposes of cost allocation pursuant to agreements and tariffs on file at FERC for each Region, and must be planned for construction in both the PJM region and the NYISO Region. (b) The share of the costs of an Interregional Transmission Project allocated to a Region will be determined by the ratio of the present value of the estimated costs of such Region’s displaced regional transmission project or projects to the total of the present values of the estimated costs of the displaced regional transmission projects in the Regions that have selected the Interregional Transmission Project in their regional transmission plans. (c) The present values of the estimated costs of each Region’s displaced regional transmission project shall be based on a common base date that will be the beginning of the calendar month of the cost allocation analysis for the subject Interregional Transmission Project (the “Base Date”). (d) In order to perform the analysis in Section 35.10.2(b) above, the estimated cost of the displaced regional transmission projects shall specify the year’s dollars in which those estimates are provided. (e) The present value analysis for all displaced regional transmission projects shall use a common discount rate. PJM and NYISO, in consultation with their respective transmission owners, and NYISO in consultation with other stakeholders, shall agree on the discount rate to be used for the present value analysis. (f) PJM and NYISO, in consultation with the transmission owners in their respective regions, and NYISO in consultation with other stakeholders, shall review and determine that the cost estimates of the displaced regional transmission projects have been determined in a comparable manner prior to applying this cost allocation. (g) No cost shall be allocated to a Region that has not selected the Interregional Transmission Project in its regional transmission plan. (h) When a portion of an Interregional Transmission Project evaluated under the Protocol is included by a region (Region 1) in its regional transmission plan but there is no regional need or displaced regional transmission project in Region 1 and the neighboring region (Region 2) has a regional need or displaced regional project for the Interregional Transmission Project and selects the Interregional Transmission Project in its regional transmission plan, all of the costs of the Interregional Transmission Project shall be allocated to Region 2 in accordance with the methodology in this Section 35.10.2 and none of the costs shall be allocated to Region 1. (i) The portion of the costs allocated to a region pursuant to this Section 35.10.2 shall be further allocated to the transmission customers within such Region pursuant to the applicable provisions of the region’s tariffs and, if applicable, agreements on file with FERC. (j) The following example illustrates the cost allocation for such an Interregional Transmission Project: A cost allocation analysis of the costs of Interregional Transmission Project Z is to be performed during a given month establishing the beginning of that month as the Base Date. Region A has identified a reliability need in its region and has selected a transmission project (Project X) as the preferred solution in its regional plan. The estimated cost of Project X is: Cost (X), provided in a given year’s dollars. The number of years from the Base Date to the year associated with the cost estimate of Project (X) is: N(X). Region B has identified a reliability need in its region and has selected a transmission project (Project Y) as the preferred solution in its Regional Plan. The estimated cost of Project Y is: Cost (Y), provided in a given year’s dollars. The number of years from the Base Date to the year associated with the cost estimate of Project (Y) is: N(Y). Regions A and B, through the interregional planning process have determined that an Interregional Transmission Project (Project Z) will address the reliability needs in both regions more efficiently and cost-effectively than the separate regional projects. The estimated cost of Project Z is: Cost (Z). Regions A and B have each determined that Interregional Transmission Project Z is the preferred solution to their reliability needs and have adopted that Interregional Transmission Project in their respective regional plans in lieu of Projects X and Y, respectively. If Regions A and B have agreed to bear the costs of upgrades in other affected transmission planning regions, these costs will be considered part of Cost (Z). The discount rate used for all displaced regional transmission projects is: D Based on the foregoing assumptions, the following formulas will be used: Present Value of Cost (X) = PV Cost (X) = Cost (X) / (1+D)N(X) Present Value of Cost (Y) = PV Cost (Y) = Cost (Y) / (1+D)N(Y) Cost Allocation to Region A = Cost (Z) x PV Cost (X)/[PV Cost (X) + PV Cost (Y)] Cost Allocation to Region B = Cost (Z) x PV Cost (Y)/[PV Cost (X) + PV Cost (Y)] Applying those formulas, if: Cost (X) = $60 Million and N(X) = 8.25 years Cost (Y) = $40 Million and N(Y) = 4.50 years Cost (Z) = $80 Million D = 7.5% per year Then: PV Cost (X) = 60/(1+0.075)8.25 = 33.039 Million PV Cost (Y) = 40/(1+0.075)4.50 = 28.888 Million Cost Allocation to Region A = $80 x 33.039/(33.039 + 28.888) = $42.681 Million Cost Allocation to Region B = $80 x 28.888/(33.039 + 28.888) = $37.319 Million
Appears in 29 contracts
Samples: Joint Operating Agreement, Joint Operating Agreement, Joint Operating Agreement
Allocation of Costs of Approved Interregional Transmission Projects. The costs of Interregional Transmission Projects, as defined in the Protocol, evaluated under the Protocol and selected by PJM and NYISO (the “Regions”) in their regional transmission plans for purposes of cost allocation under their respective tariffs shall, when applicable, be allocated to the PJM Region and the NYISO Region in accordance with the cost allocation principles of FERC Order No. 1000, as follows:
(a) To be eligible for interregional cost allocation pursuant to this Section 35.10.2, an Interregional Transmission Project must be selected in both the PJM and NYISO regional transmission plans for purposes of cost allocation pursuant to agreements and tariffs on file at FERC for each Region, and must be planned for construction in both the PJM region and the NYISO Region.
(b) The share of the costs of an Interregional Transmission Project allocated to a Region will be determined by the ratio of the present value of the estimated costs of such Region’s displaced regional transmission project or projects to the total of the present values of the estimated costs of the displaced regional transmission projects in the Regions that have selected the Interregional Transmission Project in their regional transmission plans.
(c) The present values of the estimated costs of each Region’s displaced regional transmission project shall be based on a common base date that will be the beginning of the calendar month of the cost allocation analysis for the subject Interregional Transmission Project (the “Base Date”).
(d) In order to perform the analysis in Section 35.10.2(b) above, the estimated cost of the displaced regional transmission projects shall specify the year’s dollars in which those estimates are provided.
(e) The present value analysis for all displaced regional transmission projects shall use a common discount rate. PJM and NYISO, in consultation with their respective transmission owners, and NYISO in consultation with other stakeholders, shall agree on the discount rate to be used for the present value analysis.
(f) PJM and NYISO, in consultation with the transmission owners in their respective regions, and NYISO in consultation with other stakeholders, shall review and determine that the cost estimates of the displaced regional transmission projects have been determined in a comparable manner prior to applying this cost allocation.
(g) No cost shall be allocated to a Region that has not selected the Interregional Transmission Project in its regional transmission plan.
(h) When a portion of an Interregional Transmission Project evaluated under the Protocol is included by a region (Region 1) in its regional transmission plan but there is no regional need or displaced regional transmission project in Region 1 and the neighboring region (Region 2) has a regional need or displaced regional project for the Interregional Transmission Project and selects the Interregional Transmission Project in its regional transmission plan, all of the costs of the Interregional Transmission Project shall be allocated to Region 2 in accordance with the methodology in this Section 35.10.2 and none of the costs shall be allocated to Region 1.
(i) The portion of the costs allocated to a region pursuant to this Section 35.10.2 shall be further allocated to the transmission customers within such Region pursuant to the applicable provisions of the region’s tariffs and, if applicable, agreements on file with FERC.
(j) The following example illustrates the cost allocation for such an Interregional Transmission Project: A cost allocation analysis of the costs of Interregional Transmission Project Z is to be performed during a given month establishing the beginning of that month as the Base Date. .
Region A has identified a reliability need in its region and has selected a transmission project (Project X) as the preferred solution in its regional plan. The estimated cost of Project X is: Cost (X), provided in a given year’s dollars. The number of years from the Base Date to the year associated with the cost estimate of Project (X) is: N(X). Region B has identified a reliability need in its region and has selected a transmission project (Project Y) as the preferred solution in its Regional Plan. The estimated cost of Project Y is: Cost (Y), provided in a given year’s dollars. The number of years from the Base Date to the year associated with the cost estimate of Project (Y) is: N(Y). Regions A and B, through the interregional planning process have determined that an Interregional Transmission Project (Project Z) will address the reliability needs in both regions more efficiently and cost-effectively than the separate regional projects. The estimated cost of Project Z is: Cost (Z). Regions A and B have each determined that Interregional Transmission Project Z is the preferred solution to their reliability needs and have adopted that Interregional Transmission Project in their respective regional plans in lieu of Projects X and Y, respectively. If Regions A and B have agreed to bear the costs of upgrades in other affected transmission planning regions, these costs will be considered part of Cost (Z). The discount rate used for all displaced regional transmission projects is: D Based on the foregoing assumptions, the following formulas will be used: Present Value of Cost (X) = PV Cost (X) = Cost (X) / (1+D)N(X) Present Value of Cost (Y) = PV Cost (Y) = Cost (Y) / (1+D)N(Y) Cost Allocation to Region A = Cost (Z) x PV Cost (X)/[PV Cost (X) + PV Cost (Y)] Cost Allocation to Region B = Cost (Z) x PV Cost (Y)/[PV Cost (X) + PV Cost (Y)] Applying those formulas, if: Cost (X) = $60 Million and N(X) = 8.25 years Cost (Y) = $40 Million and N(Y) = 4.50 years Cost (Z) = $80 Million D = 7.5% per year Then: PV Cost (X) = 60/(1+0.075)8.25 = 33.039 Million PV Cost (Y) = 40/(1+0.075)4.50 = 28.888 Million Cost Allocation to Region A = $80 x 33.039/(33.039 + 28.888) = $42.681 Million Cost Allocation to Region B = $80 x 28.888/(33.039 + 28.888) = $37.319 Million
Appears in 24 contracts
Samples: Joint Operating Agreement, Joint Operating Agreement, Joint Operating Agreement
Allocation of Costs of Approved Interregional Transmission Projects. The costs of Interregional Transmission Projects, as defined in the Protocol, evaluated under the Protocol and selected by PJM and NYISO (the “Regions”) in their regional transmission plans for purposes of cost allocation under their respective tariffs shall, when applicable, be allocated to the PJM Region and the NYISO Region in accordance with the cost allocation principles of FERC Order No. 1000, as follows:
(a) To be eligible for interregional cost allocation pursuant to this Section 35.10.2, an Interregional Transmission Project must be selected in both the PJM and NYISO regional transmission plans for purposes of cost allocation pursuant to agreements and tariffs on file at FERC for each Region, and must be planned for construction in both the PJM region and the NYISO Region.
(b) The share of the costs of an Interregional Transmission Project allocated to a Region will be determined by the ratio of the present value of the estimated costs of such Region’s displaced regional transmission project or projects to the total of the present values of the estimated costs of the displaced regional transmission projects in the Regions that have selected the Interregional Transmission Project in their regional transmission plans.
(c) The present values of the estimated costs of each Region’s displaced regional transmission project shall be based on a common base date that will be the beginning of the calendar month of the cost allocation analysis for the subject Interregional Transmission Project (the “Base Date”).
(d) In order to perform the analysis in Section 35.10.2(b) above, the estimated cost of the displaced regional transmission projects shall specify the year’s dollars in which those estimates are provided.
(e) The present value analysis for all displaced regional transmission projects shall use a common discount rate. PJM and NYISO, in consultation with their respective transmission owners, and NYISO in consultation with other stakeholders, shall agree on the discount rate to be used for the present value analysis.
(f) PJM and NYISO, in consultation with the transmission owners in their respective regions, and NYISO in consultation with other stakeholders, shall review and determine that the cost estimates of the displaced regional transmission projects have been determined in a comparable manner prior to applying this cost allocation.
(g) No cost shall be allocated to a Region that has not selected the Interregional Transmission Project in its regional transmission plan.
(h) When a portion of an Interregional Transmission Project evaluated under the Protocol is included by a region (Region 1) in its regional transmission plan but there is no regional need or displaced regional transmission project in Region 1 and the neighboring region (Region 2) has a regional need or displaced regional project for the Interregional Transmission Project and selects the Interregional Transmission Project in its regional transmission plan, all of the costs of the Interregional Transmission Project shall be allocated to Region 2 in accordance with the methodology in this Section 35.10.2 and none of the costs shall be allocated to Region 1.
(i) The portion of the costs allocated to a region pursuant to this Section 35.10.2 shall be further allocated to the transmission customers within such Region pursuant to the applicable provisions of the region’s tariffs and, if applicable, agreements on file with FERC.
(j) The following example illustrates the cost allocation for such an Interregional Transmission Project: A cost allocation analysis of the costs of Interregional Transmission Project Z is to be performed during a given month establishing the beginning of that month as the Base Date. Region A has identified a reliability need in its region and has selected a transmission project (Project X) as the preferred solution in its regional plan. The estimated cost of Project X is: Cost (X), provided in a given year’s dollars. The number of years from the Base Date to the year associated with the cost estimate of Project (X) is: N(X). Region B has identified a reliability need in its region and has selected a transmission project (Project Y) as the preferred solution in its Regional Plan. The estimated cost of Project Y is: Cost (Y), provided in a given year’s dollars. The number of years from the Base Date to the year associated with the cost estimate of Project (Y) is: N(Y). Regions A and B, through the interregional planning process have determined that an Interregional Transmission Project (Project Z) will address the reliability needs in both regions more efficiently and cost-effectively than the separate regional projects. The estimated cost of Project Z is: Cost (Z). Regions A and B have each determined that Interregional Transmission Project Z is the preferred solution to their reliability needs and have adopted that Interregional Transmission Project in their respective regional plans in lieu of Projects X and Y, respectively. If Regions A and B have agreed to bear the costs of upgrades in other affected transmission planning regions, these costs will be considered part of Cost (Z). The discount rate used for all displaced regional transmission projects is: D Based on the foregoing assumptions, the following formulas will be used: Present Value of Cost (X) = PV Cost (X) = Cost (X) / (1+D)N(X) Present Value of Cost (Y) = PV Cost (Y) = Cost (Y) / (1+D)N(Y) Cost Allocation to Region A = Cost (Z) x PV Cost (X)/[PV Cost (X) + PV Cost (Y)] Cost Allocation to Region B = Cost (Z) x PV Cost (Y)/[PV Cost (X) + PV Cost (Y)] Applying those formulas, if: Cost (X) = $60 Million and N(X) = 8.25 years Cost (Y) = $40 Million and N(Y) = 4.50 years Cost (Z) = $80 Million D = 7.5% per year Then: PV Cost (X) = 60/(1+0.075)8.25 = 33.039 Million PV Cost (Y) = 40/(1+0.075)4.50 = 28.888 Million Cost Allocation to Region A = $80 x 33.039/(33.039 + 28.888) = $42.681 Million Cost Allocation to Region B = $80 x 28.888/(33.039 + 28.888) = $37.319 Million
Appears in 7 contracts
Samples: Open Access Transmission Tariff (Oatt), Open Access Transmission Tariff (Oatt), Open Access Transmission Tariff (Oatt)
Allocation of Costs of Approved Interregional Transmission Projects. The costs of Interregional Transmission Projects, as defined in the Protocol, evaluated under the Protocol and selected by PJM and NYISO (the “Regions”) in their regional transmission plans for purposes of cost allocation under their respective tariffs shall, when applicable, be allocated to the PJM Region and the NYISO Region in accordance with the cost allocation principles of FERC Order No. 1000, as follows:
(a) To be eligible for interregional cost allocation pursuant to this Section 35.10.2, an Interregional Transmission Project must be selected in both the PJM and NYISO regional transmission plans for purposes of cost allocation pursuant to agreements and tariffs on file at FERC for each Region, and must be planned for construction in both the PJM region and the NYISO Region.
(b) The share of the costs of an Interregional Transmission Project allocated to a Region will be determined by the ratio of the present value of the estimated costs of such Region’s displaced regional transmission project or projects to the total of the present values of the estimated costs of the displaced regional transmission projects in the Regions that have selected the Interregional Transmission Project in their regional transmission plans.
(c) The present values of the estimated costs of each Region’s displaced regional transmission project shall be based on a common base date that will be the beginning of the calendar month of the cost allocation analysis for the subject Interregional Transmission Project (the “Base Date”).
(d) In order to perform the analysis in Section 35.10.2(b) above, the estimated cost of the displaced regional transmission projects shall specify the year’s dollars in which those estimates are provided.
(e) The present value analysis for all displaced regional transmission projects shall use a common discount rate. PJM and NYISO, in consultation with their respective transmission owners, and NYISO in consultation with other stakeholders, shall agree on the discount rate to be used for the present value analysis.
(f) PJM and NYISO, in consultation with the transmission owners in their respective regions, and NYISO in consultation with other stakeholders, shall review and determine that the cost estimates of the displaced regional transmission projects have been determined in a comparable manner prior to applying this cost allocation.
(g) No cost shall be allocated to a Region that has not selected the Interregional Transmission Project in its regional transmission plan.
(h) When a portion of an Interregional Transmission Project evaluated under the Protocol is included by a region (Region 1) in its regional transmission plan but there is no regional need or displaced regional transmission project in Region 1 and the neighboring region (Region 2) has a regional need or displaced regional project for the Interregional Transmission Project and selects the Interregional Transmission Project in its regional transmission plan, all of the costs of the Interregional Transmission Project shall be allocated to Region 2 in accordance with the methodology in this Section 35.10.2 and none of the costs shall be allocated to Region 1.
(i) The portion of the costs allocated to a region pursuant to this Section 35.10.2 shall be further allocated to the transmission customers within such Region pursuant to the applicable provisions of the region’s tariffs and, if applicable, agreements on file with FERC.
(j) The following example illustrates the cost allocation for such an Interregional Transmission Project: A cost allocation analysis of the costs of Interregional Transmission Project Z is to be performed during a given month establishing the beginning of that month as the Base Date. Region A has identified a reliability need in its region and has selected a transmission project (Project X) as the preferred solution in its regional plan. The estimated cost of Project X is: Cost (X), provided in a given year’s dollars. The number of years from the Base Date to the year associated with the cost estimate of Project (X) is: N(X). Region B has identified a reliability need in its region and has selected a transmission project (Project Y) as the preferred solution in its Regional Plan. The estimated cost of Project Y is: Cost (Y), provided in a given year’s dollars. The number of years from the Base Date to the year associated with the cost estimate of Project (Y) is: N(Y). Regions A and B, through the interregional planning process have determined that an Interregional Transmission Project (Project Z) will address the reliability needs in both regions more efficiently and cost-effectively than the separate regional projects. The estimated cost of Project Z is: Cost (Z). Regions A and B have each determined that Interregional Transmission Project Z is the preferred solution to their reliability needs and have adopted that Interregional Transmission Project in their respective regional plans in lieu of Projects X and Y, respectively. If Regions A and B have agreed to bear the costs of upgrades in other affected transmission planning regions, these costs will be considered part of Cost (Z). The discount rate used for all displaced regional transmission projects is: D Based on the foregoing assumptions, the following formulas will be used: Present Value of Cost (X) = PV Cost (X) = Cost (X) / (1+D)N(X) Present Value of Cost (Y) = PV Cost (Y) = Cost (Y) / (1+D)N(Y) Cost Allocation to Region A = Cost (Z) x PV Cost (X)/[PV Cost (X) + PV Cost (Y)] Cost Allocation to Region B = Cost (Z) x PV Cost (Y)/[PV Cost (X) + PV Cost (Y)] Applying those formulas, if: Cost (X) = $60 Million and N(X) = 8.25 years Cost (Y) = $40 Million and N(Y) = 4.50 years Cost (Z) = $80 Million D = 7.5% per year Then: PV Cost (X) = 60/(1+0.075)8.25 = 33.039 Million PV Cost (Y) = 40/(1+0.075)4.50 = 28.888 Million Cost Allocation to Region A = $80 x 33.039/(33.039 + 28.888) = $42.681 Million Cost Allocation to Region B = $80 x 28.888/(33.039 + 28.888) = $37.319 Million
Appears in 6 contracts
Samples: Joint Operating Agreement, Joint Operating Agreement, Joint Operating Agreement
Allocation of Costs of Approved Interregional Transmission Projects. The costs of Interregional Transmission Projects, as defined in the Protocol, evaluated under the Protocol and selected by PJM and NYISO (the “Regions”) in their regional transmission plans for purposes of cost allocation under their respective tariffs shall, when applicable, be allocated to the PJM Region and the NYISO Region in accordance with the cost allocation principles of FERC Order No. 1000, as follows:
(a) To be eligible for interregional cost allocation pursuant to this Section 35.10.2, an Interregional Transmission Project must be selected in both the PJM and NYISO regional transmission plans for purposes of cost allocation pursuant to agreements and tariffs on file at FERC for each Region, and must be planned for construction in both the PJM region and the NYISO Region.
(b) The share of the costs of an Interregional Transmission Project allocated to a Region will be determined by the ratio of the present value of the estimated costs of such Region’s displaced regional transmission project or projects to the total of the present values of the estimated costs of the displaced regional transmission projects in the Regions that have selected the Interregional Transmission Project in their regional transmission plans.
(c) The present values of the estimated costs of each Region’s displaced regional transmission project shall be based on a common base date that will be the beginning of the calendar month of the cost allocation analysis for the subject Interregional Transmission Project (the “Base Date”).
(d) In order to perform the analysis in Section 35.10.2(b) above, the estimated cost of the displaced regional transmission projects shall specify the year’s dollars in which those estimates are provided.
(e) The present value analysis for all displaced regional transmission projects shall use a common discount rate. PJM and NYISO, in consultation with their respective transmission owners, and NYISO in consultation with other stakeholders, shall agree on the discount rate to be used for the present value analysis.
(f) PJM and NYISO, in consultation with the transmission owners in their respective regions, and NYISO in consultation with other stakeholders, shall review and determine that the cost estimates of the displaced regional transmission projects have been determined in a comparable manner prior to applying this cost allocation.
(g) No cost shall be allocated to a Region that has not selected the Interregional Transmission Project in its regional transmission plan.
(h) When a portion of an Interregional Transmission Project evaluated under the Protocol is included by a region (Region 1) in its regional transmission plan but there is no regional need or displaced regional transmission project in Region 1 and the neighboring region (Region 2) has a regional need or displaced regional project for the Interregional Transmission Project and selects the Interregional Transmission Project in its regional transmission plan, all of the costs of the Interregional Transmission Project shall be allocated to Region 2 in accordance with the methodology in this Section 35.10.2 and none of the costs shall be allocated to Region 1.
(i) The portion of the costs allocated to a region pursuant to this Section 35.10.2 shall be further allocated to the transmission customers within such Region pursuant to the applicable provisions of the region’s tariffs and, if applicable, agreements on file with FERC.
(j) The following example illustrates the cost allocation for such an Interregional Transmission Project: • A cost allocation analysis of the costs of Interregional Transmission Project Z is to be performed during a given month establishing the beginning of that month as the Base Date. • Region A has identified a reliability need in its region and has selected a transmission project (Project X) as the preferred solution in its regional plan. The estimated cost of Project X is: Cost (X), provided in a given year’s dollars. The number of years from the Base Date to the year associated with the cost estimate of Project (X) is: N(X). • Region B has identified a reliability need in its region and has selected a transmission project (Project Y) as the preferred solution in its Regional Plan. The estimated cost of Project Y is: Cost (Y), provided in a given year’s dollars. The number of years from the Base Date to the year associated with the cost estimate of Project (Y) is: N(Y). • Regions A and B, through the interregional planning process have determined that an Interregional Transmission Project (Project Z) will address the reliability needs in both regions more efficiently and cost-effectively than the separate regional projects. The estimated cost of Project Z is: Cost (Z). Regions A and B have each determined that Interregional Transmission Project Z is the preferred solution to their reliability needs and have adopted that Interregional Transmission Project in their respective regional plans in lieu of Projects X and Y, respectively. If Regions A and B have agreed to bear the costs of upgrades in other affected transmission planning regions, these costs will be considered part of Cost (Z). • The discount rate used for all displaced regional transmission projects is: D • Based on the foregoing assumptions, the following formulas will be used: ▪ Present Value of Cost (X) = PV Cost (X) = Cost (X) / (1+D)N(X) ▪ Present Value of Cost (Y) = PV Cost (Y) = Cost (Y) / (1+D)N(Y) ▪ Cost Allocation to Region A = Cost (Z) x PV Cost (X)/[PV Cost (X) + PV Cost (Y)] ▪ Cost Allocation to Region B = Cost (Z) x PV Cost (Y)/[PV Cost (X) + PV Cost (Y)] • Applying those formulas, if: Cost (X) = $60 Million and N(X) = 8.25 years Cost (Y) = $40 Million and N(Y) = 4.50 years Cost (Z) = $80 Million D = 7.5% per year Then: PV Cost (X) = 60/(1+0.075)8.25 = 33.039 Million PV Cost (Y) = 40/(1+0.075)4.50 = 28.888 Million Cost Allocation to Region A = $80 x 33.039/(33.039 + 28.888) = $42.681 Million Cost Allocation to Region B = $80 x 28.888/(33.039 + 28.888) = $37.319 Million
Appears in 1 contract
Samples: Joint Operating Agreement
Allocation of Costs of Approved Interregional Transmission Projects. The costs of Interregional Transmission Projects, as defined in the Protocol, evaluated under the Protocol and selected by PJM and NYISO (the “Regions”) in their regional transmission plans for purposes of cost allocation under their respective tariffs shall, when applicable, be allocated to the PJM Region and the NYISO Region in accordance with the cost allocation principles of FERC Order No. 1000, as follows:
(a) To be eligible for interregional cost allocation pursuant to this Section 35.10.2, an Interregional Transmission Project must be selected in both the PJM and NYISO regional transmission plans for purposes of cost allocation pursuant to agreements and tariffs on file at FERC for each Region, and must be planned for construction in both the PJM region and the NYISO Region.
(b) The share of the costs of an Interregional Transmission Project allocated to a Region will be determined by the ratio of the present value of the estimated costs of such Region’s displaced regional transmission project or projects to the total of the present values of the estimated costs of the displaced regional transmission projects in the Regions that have selected the Interregional Transmission Project in their regional transmission plans.
(c) The present values of the estimated costs of each Region’s displaced regional transmission project shall be based on a common base date that will be the beginning of the calendar month of the cost allocation analysis for the subject Interregional Transmission Project (the “Base Date”).
(d) In order to perform the analysis in Section 35.10.2(b) above, the estimated cost of the displaced regional transmission projects shall specify the year’s dollars in which those estimates are provided.
(e) The present value analysis for all displaced regional transmission projects shall use a common discount rate. PJM and NYISO, in consultation with their respective transmission owners, and NYISO in consultation with other stakeholders, shall agree on the discount rate to be used for the present value analysis.
(f) PJM and NYISO, in consultation with the transmission owners in their respective regions, and NYISO in consultation with other stakeholders, shall review and determine that the cost estimates of the displaced regional transmission projects have been determined in a comparable manner prior to applying this cost allocation.
(g) No cost shall be allocated to a Region that has not selected the Interregional Transmission Project in its regional transmission plan.
(h) When a portion of an Interregional Transmission Project evaluated under the Protocol is included by a region (Region 1) in its regional transmission plan but there is no regional need or displaced regional transmission project in Region 1 and the neighboring region (Region 2) has a regional need or displaced regional project for the Interregional Transmission Project and selects the Interregional Transmission Project in its regional transmission plan, all of the costs of the Interregional Transmission Project shall be allocated to Region 2 in accordance with the methodology in this Section 35.10.2 and none of the costs shall be allocated to Region 1.
(i) The portion of the costs allocated to a region pursuant to this Section 35.10.2 shall be further allocated to the transmission customers within such Region pursuant to the applicable provisions of the region’s tariffs and, if applicable, agreements on file with FERC.
(j) The following example illustrates the cost allocation for such an Interregional Transmission Project: A cost allocation analysis of the costs of Interregional Transmission Project Z is to be performed during a given month establishing the beginning of that month as the Base Date. Region A has identified a reliability need in its region and has selected a transmission project (Project X) as the preferred solution in its regional plan. The estimated cost of Project X is: Cost (X), provided in a given year’s dollars. The number of years from the Base Date to the year associated with the cost estimate of Project (X) is: N(X). Region B has identified a reliability need in its region and has selected a transmission project (Project Y) as the preferred solution in its Regional Plan. The estimated cost of Project Y is: Cost (Y), provided in a given year’s dollars. The number of years from the Base Date to the year associated with the cost estimate of Project (Y) is: N(Y). Regions A and B, through the interregional planning process have determined that an Interregional Transmission Project (Project Z) will address the reliability needs in both regions more efficiently and cost-effectively than the separate regional projects. The estimated cost of Project Z is: Cost (Z). Regions A and B have each determined that Interregional Transmission Project Z is the preferred solution to their reliability needs and have adopted that Interregional Transmission Project in their respective regional plans in lieu of Projects X and Y, respectively. If Regions A and B have agreed to bear the costs of upgrades in other affected transmission planning regions, these costs will be considered part of Cost (Z). The discount rate used for all displaced regional transmission projects is: D Based on the foregoing assumptions, the following formulas will be used: Present Value of Cost (X) = PV Cost (X) = Cost (X) / (1+D)N(X) Present Value of Cost (Y) = PV Cost (Y) = Cost (Y) / (1+D)N(Y) Cost Allocation to Region A = Cost (Z) x PV Cost (X)/[PV Cost (X) + PV Cost (Y)] Cost Allocation to Region B = Cost (Z) x PV Cost (Y)/[PV Cost (X) + PV Cost (Y)] Applying those formulas, if: Cost (X) = $60 Million and N(X) = 8.25 years Cost (Y) = $40 Million and N(Y) = 4.50 years Cost (Z) = $80 Million D = 7.5% per year Then: PV Cost (X) = 60/(1+0.075)8.25 = 33.039 Million PV Cost (Y) = 40/(1+0.075)4.50 = 28.888 Million Cost Allocation to Region A = $80 x 33.039/(33.039 + 28.888) = $42.681 Million Cost Allocation to Region B = $80 x 28.888/(33.039 + 28.888) = $37.319 Million