Anticipated Completion Date Sample Clauses

Anticipated Completion Date. Months after the Transfer Date in 1.4.1 above
Anticipated Completion Date. Landlord presently anticipates that the Premises will be substantially completed and ready for occupancy by Tenant on or about September 1, 1994. In the event that Landlord's substantial completion of construction of the Premises or the delivery of possession of the Premises to Tenant is delayed, regardless of the reasons or causes of such delay, this Lease shall not be rendered void or voidable as a result of such delay, and the term of this Lease shall commence on the Lease Commencement Date as determined pursuant to Section 2.2 hereof. Furthermore, Landlord shall not have any liability whatsoever to Tenant on account of such delay.
Anticipated Completion Date. Within approximately 9 (Nine) months after the suspensive condition contained in clause 28 has been met PURCHASER (who warrants, if this Agreement is executed by him/her as representative or agent that he/she is duly authorised hereto, and assisted by SPOUSE as far as needs be)
Anticipated Completion Date. The anticipated completion date for the development is 31ST DECEMBER 2009. However, in the event of an appeal being lodged against the development, or in the event of unforeseen circumstances preventing the completion, the parties agree to extend this date by whatever period required to finalise the completion. SIGNED AT on this the day of 2009. SIGNED AT on this the day of 2009. for and on behalf of SELLER
Anticipated Completion Date. 8.03(b) Anticipated Option Space Inclusion Date............................25.
Anticipated Completion Date. 01 June 2021 or such alternative date as notified by the Seller to the Purchaser.
Anticipated Completion Date. 101 Anticipated Completion Date Notice.......................101 Article 4 Landlord's Work.................................23
Anticipated Completion Date. 3.8 As-Built Floor Area......................................... 2.3 Assignment.................................................. 14.1 at Developer's expense...................................... 1.2 at Mall II Buyer's expense.................................. 1.2

Related to Anticipated Completion Date

  • Project Completion Date It is agreed between the Parties that the Project Completion Date is <END DATE, YEAR>. If the Project is not completed by such date then, subject to an amendment agreed to between the Parties, Alberta Innovates may elect to terminate this Investment Agreement. In such event, Alberta Innovates will notify the Applicant of its decision to terminate as soon as reasonably practical and shall advise the Applicant of the effective date of termination. Alberta Innovates will have no liability or obligation to reimburse the Applicant for any Project Costs incurred after the effective date of termination and may require the Applicant to return any portions of the Investment which were spent on Ineligible Expenses. Additionally, any portion of the Investment not used and accounted for in accordance with this Agreement as of the Project Completion Date or earlier termination is repayable by the Applicant to AI at AI’s request.

  • Completion Date The Work under this Contract shall be completed by midnight of the date required in the Contract as the Material Completion and Occupancy Date unless extended by approved requests for extension of time.

  • Substantial Completion Date Substantial Completion of the Work as defined in Article 6.1.2 of the General Conditions to the Continuing Contract for Construction Management shall be achieved by July 31, 2022.

  • Final Completion Date Final Completion for the Work as defined in Article 6.1.3 of the General Conditions to the Continuing Contract for Construction Management shall be achieved by October 31, 2024.

  • Construction Period During the construction period, Redeveloper agrees to keep the construction area, including completed operations insured against loss or damage by fire, and such other risks, casualties, and hazards as are customarily covered by builders’ risk or extended coverage policies in an amount not less than the replacement value but allowing for reasonable coinsurance clauses and deductibles. In the event of any insured damage or destruction, Redeveloper agrees to use its good faith efforts to commence restoration of the Private Improvements to its prior condition within nine (9) months from the date of the damage or destruction, and shall diligently pursue the same to completion.

  • Start Date The parental leave must begin no later than 52 weeks after the day the child is born or comes into the custody, care and control of the parent for the first time for provincially or federally regulated employees. The parental leave of an employee who takes a pregnancy leave must begin when the pregnancy leave ends unless the child has not yet come into the care and control of the parent for the first time.

  • Substantial Completion Section 7.4.1 When Supplier believes that it has achieved the requirements of Substantial Completion, Supplier shall provide written notice (the “Notice of Substantial Completion”) to System Owner stating that Supplier has achieved Substantial Completion, together with copies of all documents (as identified in the definition of Substantial Completion) that are required to be delivered to System Owner to meet Substantial Completion that have not been previously delivered. Section 7.4.2 Upon receipt of the Notice of Substantial Completion, System Owner shall promptly proceed to obtain Independent Engineer’s review and approval of the Notice of Substantial Completion and the Commissioning Report within a reasonable time, but in no event more than ten (10) Business Days following receipt of the Notice of Substantial Completion and all accompanying documents or such longer period of time as specified in the Construction Schedule (the “Substantial Completion Review Period”). Section 7.4.3 Supplier shall provide System Owner with reasonable notice of the date and time of the inspection or review of the System by a representative of the applicable Governmental Authority or Host Utility, if required, for purposes of achieving Substantial Completion, and System Owner shall have the right to have one or more representatives and the Independent Engineer present during such inspection or review. If the representative of the applicable Governmental Authority or Host Utility notifies Supplier or System Owner that the requirements for achieving Substantial Completion have not been achieved, then Supplier shall promptly take such action as necessary to achieve such requirements and, to the extent applicable, schedule another inspection or review of the System. Such procedure shall be repeated until such inspection or review has been satisfactorily completed and approved. Section 7.4.4 If System Owner and the Independent Engineer approve the Notice of Substantial Completion, System Owner shall, within the Substantial Completion Review Period, (a) notify Supplier of its approval and (b) issue written notice to Supplier to complete the Work (the “Notice to Complete”). Section 7.4.5 If System Owner or the Independent Engineer has a reasonable basis not to approve the Notice of Substantial Completion because the requirements for Substantial Completion have not been met, System Owner shall, within the Substantial Completion Review Period, notify Supplier of its non-approval and include a detailed explanation for the basis thereof. Supplier shall promptly undertake such action or work as necessary to achieve such requirements and shall then issue another Notice of Substantial Completion to System Owner stating that Supplier believes that such requirements have been achieved. Such procedure shall be repeated until Substantial Completion is achieved. If Supplier disputes the reasons stated in System Owner’s notification, then such dispute shall be resolved in accordance with Article XIX.

  • Final Completion The full and final completion of all Work in accordance with the Contract Documents.

  • Date of Completion The Developer must ensure that the Developer’s Works reach Completion on or before the date or milestone referred to in clause 1 of Schedule 3 of this document.

  • Project Completion The Contractor agrees to schedule a final job walk with the County. If required, the County will prepare a list of incomplete items, the “Punch List”. The Contractor agrees to complete the “Punch List” corrections and schedule a final project completion job walk. The County will sign the “Punch List” as completed when determined, the project is finished. The Contractor agrees to submit the following along with its final payment request: