APPLICABLE TARIFF AND SHARING OF CDM BENEFITS. 12.1. The Developer shall be entitled to receive the Tariff of INR……. / kWh of enery supplied by it to BESCOM in accordance with the terms of this Agreement during the period between COD and the Expiry Date. 12.2. Provided further that as a consequence of delay in Commissioning of the Project beyond the Scheduled Commissioning Date, subject to Article 14, the changed applicable Effective Tariff for the Project shall be 80% (eighty percent) of the Effective Tariff quoted by the Bidder, if the Project is commissioned within 3 (three) months thereafter.
Appears in 3 contracts
Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement
APPLICABLE TARIFF AND SHARING OF CDM BENEFITS.
12.1. The Developer shall be entitled to receive the Tariff of INR……. / kWh of enery supplied by it to BESCOM in accordance with the terms of this Agreement during the period between COD and the Expiry Date.
12.2. Provided further that as a consequence of delay in Commissioning of the Project beyond the Scheduled Commissioning Date, subject to Article 14, the changed applicable Effective Tariff for the Project shall be 80% (eighty percent) of the Effective Tariff quoted by the Bidder, if the Project is commissioned within 3 (three) months thereafter.
Appears in 1 contract
Samples: Power Purchase Agreement