Basis of Guaranteed Maximum Price. The Construction Manager shall include with the GMP proposal a written statement of its basis, which shall include: 3.10.4.1 A list of the Drawings and Specifications, including all addenda thereto and the conditions of the Contract, which were used in preparation of the GMP proposal. 3.10.4.2 A list of allowances and a statement of their basis. 3.10.4.3 A list of the clarifications and assumptions made by the Construction Manager in the preparation of the GMP proposal to supplement the information contained in the Drawings and Specifications 3.10.4.4 The proposed GMP, including a statement of the estimated cost organized by trade categories, allowances, contingency, and other items and the fee that comprise the GMP. 3.10.4.5 The Date of Substantial Completion upon which the proposed GMP is based, and a schedule of the Construction Documents issuance dates upon which the date of substantial completion is based.
Appears in 11 contracts
Samples: Construction Management Continuing Works Agreement, Construction Management Agreement, Construction Management Agreement
Basis of Guaranteed Maximum Price. The Construction Manager shall include with the GMP proposal a written statement of its basis, which shall include:
3.10.4.1 (a) A list of the Drawings and Specifications, including all addenda thereto and the conditions of the Contract, which were used in preparation of the GMP proposal.
3.10.4.2 (b) A list of allowances and a statement of their basis.
3.10.4.3 (c) A list of the clarifications and assumptions made by the Construction Manager in the preparation of the GMP proposal to supplement the information contained in the Drawings and Specifications.
3.10.4.4 (d) The proposed GMP, including a statement of the estimated cost organized by trade categories, allowances, contingency, and other items and items and the fee that comprise the GMP.
3.10.4.5 (e) The Date of Substantial Completion upon which the proposed GMP is based, and a schedule of the Construction Documents issuance dates upon which the date of substantial completion is based.
Appears in 5 contracts
Samples: Construction Management Agreement, Construction Management Agreement, Construction Management Agreement
Basis of Guaranteed Maximum Price. The Construction Manager shall include with the GMP proposal a written statement of its basis, which shall include:
3.10.4.1 3.6.4.1 A list of the Drawings and Specifications, including all addenda thereto and the conditions of the Contract, which were used in preparation of the GMP proposal.
3.10.4.2 3.6.4.2 A list of allowances and a statement of their basis.
3.10.4.3 3.6.4.3 A list of the clarifications and assumptions made by the Construction Manager in the preparation of the GMP proposal to supplement the information contained in the Drawings and Specifications
3.10.4.4 3.6.4.4 The proposed GMP, including a statement of the estimated cost organized by trade categories, allowances, contingency, and other items and the fee that comprise the GMP.
3.10.4.5 3.6.4.5 The Date of Substantial Completion upon which the proposed GMP is based, and a schedule of the Construction Documents issuance dates upon which the date of substantial completion is based.
Appears in 1 contract
Samples: Construction Management Agreement
Basis of Guaranteed Maximum Price. The Construction Manager Design-Build Firm shall include with the GMP proposal a written statement of its basis, which shall include:
3.10.4.1 A list of the Drawings and Specifications, including all addenda thereto and the conditions of the Contract, which were used in preparation of the GMP proposal.
3.10.4.2 A list of allowances and a statement of their basis.
3.10.4.3 A list of the clarifications and assumptions made by the Construction Manager Design-Build Firm in the preparation of the GMP proposal to supplement the information contained in the Drawings and Specifications
3.10.4.4 The proposed GMP, including a statement of the estimated cost organized by trade categories, allowances, contingency, and other items and the fee that comprise the GMP.
3.10.4.5 The Date of Substantial Completion upon which the proposed GMP is based, and a schedule of the Construction Documents issuance dates upon which the date of substantial completion is based.