Biogas Delivery Subsequent to Commercial Operations Date Sample Clauses

Biogas Delivery Subsequent to Commercial Operations Date. After the Commercial Operations Date, Phoenix shall tender to Developer at the Delivery Point all Biogas produced at the Plant, other than Biogas unavailable due to the permissible excuses described in Section 5.04, and Developer shall have the option to accept from time to time some or all of such Biogas and Developer shall purchase or pay for such Biogas in accordance with Article XII of this Agreement.
AutoNDA by SimpleDocs

Related to Biogas Delivery Subsequent to Commercial Operations Date

  • Commercial Operation (i) On or before December 31, 2021, Interconnection Customer must demonstrate commercial operation of all generating units. Demonstrating commercial operation includes achieving Initial Operation in accordance with Section 1.4 of Appendix 2 to this ISA and making commercial sales or use of energy, as well as, if applicable, obtaining capacity qualification in accordance with the requirements of the Reliability Assurance Agreement Among Load Serving Entities in the PJM Region.

  • Commercial Operation Date (COD) Bus Terminal and Commercial Complex shall be deemed to be complete when the Completion Certificate or the Provisional Certificate, as the case may be, is issued under the provisions of Article 14, and accordingly the commercial operation date of the Project shall be the date on which such Completion Certificate or the Provisional Certificate is issued (the “COD”). The Bus Terminal and Commercial Complex shall enter into commercial service on COD whereupon the Concessionaire shall be entitled to demand and collect Fee in accordance with provisions of Article 27 and that the entry of Bus Terminal or part thereof into commercial service shall always be subject to compliance with the provisions of Clause 18.3 and Clause 26.2.

  • Commercial Operation Date (COD 15.1.1 The Project shall be deemed to be complete when the Completion Certificate or the Provisional Certificate, as the case may be, is issued under the provisions of Article 14, and accordingly the commercial operation date of the Project shall be the date on which such Completion Certificate or the Provisional Certificate is issued (the “COD”). The Project shall enter into commercial service on COD whereupon the Concessionaire shall be entitled to demand and collect Annuity Payments in accordance with the provisions of this Agreement.

  • Initial Operation The following requirements shall be satisfied prior to Initial Operation of the Customer Facility:

  • Notice to Centrelink Where a decision has been made to terminate the employment of employees, the employer shall notify Centrelink thereof as soon as possible giving relevant information including the number and categories of the employees likely to be affected and the period over which the terminations are intended to be carried out.

  • Synchronisation Commissioning and Commercial Operation 8.1 The Developer shall provide at least forty (40) days advanced preliminary written notice and at least twenty (20) days advanced final written notice to ESCOM of the date on which it intends to synchronize the Power Project to the Grid System.

  • Synchronization, Commissioning and Commercial Operation 4.1.1 The Power Producer shall give at least thirty (30) days written notice to the SLDC and GUVNL, of the date on which it intends to synchronize the Power Project to the Grid System.

  • Notice to Proceed (NTP Following the JOA and purchase order issuance, the County will issue a Notice to Proceed (NTP) that will provide the construction start date, the Work duration period, and the Substantial Completion date. The Contractor agrees to begin and complete construction within the dates specified on the NTP. The County must approve all extensions of time in writing. The County may also issue an Emergency Notice to Proceed (NTP). In the event the County requires the Contractor to respond to an immediate request for work, a Job Order will be created and an Emergency NTP will be issued. The Contractor will be required to perform the Scope of Work included with the Emergency NTP as directed by the County’s Project Manager or designee. The Detailed Scope of Work, Quotation, Subcontractor Listing, Shop Drawings and required Non Pre-priced backup documentation will be submitted upon completion of the emergency work in accordance with the Ordering Procedures detailed in Section III above.

  • Service Commencement Date The date the Transmission Provider begins to provide service pursuant to the terms of an executed Service Agreement, or the date the Transmission Provider begins to provide service in accordance with Section 15.3 or Section 29.1 under the Tariff.

  • Industrial Operations Analyst (IOA ‌ The IOA is a GSA Government official who audits Contractor records and conducts Contractor Assistance Visits (CAVs) to the Contractor’s place of business to assist the Contractor with task order reporting, Contract Access Fee (CAF) management, and other general contract administration functions deemed necessary by the Government.