Interconnection Customer Provided Services The services provided by Interconnection Customer under this LGIA are set forth in Article 9.6 and Article 13.5.1. Interconnection Customer shall be paid for such services in accordance with Article 11.6.
Interconnection Points 8.5.1 The IP of a Party (“Receiving Party”) for Measured Internet Traffic delivered to the Receiving Party by the other Party shall be the same as the IP of the Receiving Party for Reciprocal Compensation Traffic under Section 7.1 above.
Synchronization, Commissioning and Commercial Operation 4.1.1 The Power Producer shall give at least thirty (30) days written notice to the SLDC and GUVNL, of the date on which it intends to synchronize the Power Project to the Grid System.
FREQUENCY AND CAPACITY LEVELS No restriction on frequency, capacity and aircraft type
Synchronisation Commissioning and Commercial Operation 8.1 The Developer shall provide at least forty (40) days advanced preliminary written notice and at least twenty (20) days advanced final written notice to ESCOM of the date on which it intends to synchronize the Power Project to the Grid System.
Service Specification The Parties have agreed upon the scope and specification of the Services provided under this Service Agreement in the Service Specification.
Interconnection Point The Service Provider is responsible for connecting to the LFC Network at the Interconnection Point. The LFC may only change an Interconnection Point if a change is necessary to protect the security or integrity of that Interconnection Point in order to maintain the continuity of supply of the Wholesale Services. In the event of any such change:
Interconnection Customer (1) Interconnection Customer shall construct and, unless otherwise indicated, shall own, the following Interconnection Facilities: None
Supervisory Control and Data Acquisition (SCADA) Capability The wind plant shall provide SCADA capability to transmit data and receive instructions from the ISO and/or the Connecting Transmission Owner for the Transmission District to which the wind generating plant will be interconnected, as applicable, to protect system reliability. The Connecting Transmission Owner for the Transmission District to which the wind generating plant will be interconnected and the wind plant Developer shall determine what SCADA information is essential for the proposed wind plant, taking into account the size of the plant and its characteristics, location, and importance in maintaining generation resource adequacy and transmission system reliability in its area.