CAW Facilities. CAW shall cause: (i) Completion of Preliminary Design Documents for CAW Facilities: not later than 11 months after Program Initiation Date. (ii) Selection of design engineer for CAW Facilities: not later than 2 months after completion of Preliminary Design Documents. (iii) Authorization of design engineer for CAW Facilities: not later than 2 months after selection of design engineer. (iv) Completion of 100% Construction Documents for CAW Facilities: not later than 9 months after authorization of design engineer. (v) Substantial Completion of CAW Facilities: not later than 16 months after completion of 100% Construction Documents for the CAW Facilities.
Appears in 3 contracts
Samples: Water Purchase Agreement, Water Purchase Agreement, Water Purchase Agreement
CAW Facilities. CAW shall cause:
(i) : Completion of Preliminary Design Documents for CAW Facilities: not later than 11 months after Program Initiation Date.
(ii) . Selection of design engineer for CAW Facilities: not later than 2 months after completion of Preliminary Design Documents.
(iii) . Authorization of design engineer for CAW Facilities: not later than 2 months after selection of design engineer.
(iv) . Completion of 100% Construction Documents for CAW Facilities: not later than 9 months after authorization of design engineer.
(v) . Substantial Completion of CAW Facilities: not later than 16 months after completion of 100% Construction Documents for the CAW Facilities. Acceptance of CAW Facilities: not later than 2 months after Substantial Completion of the CAW Facilities.