Change and Budget Management Plan. The Construction Manager shall include in the Administrative Management Plans a Change and Budget Management Plan that includes: (a) a sample monthly report to the Owner showing clear tracking of all bid package forecasts and results with any savings to, or overages against, the Cost Estimate. (b) samples of forms utilized to authorize changes on the Project; (c) a flow diagram indicating the process to be utilized for changes; (d) a sample log page showing the number and dollar amounts of Change Orders covering cumulative costs and effects on the Guaranteed Maximum Price; (e) samples of standard change control reports submitted to the Owner and Design Professional;
Appears in 3 contracts
Samples: Professional Services, Professional Services Agreement, Professional Services
Change and Budget Management Plan. The Construction Manager shall include in the Administrative Management Plans a Change and Budget Management Plan that includes:
(a) a sample monthly report to the Owner showing clear tracking of all bid package forecasts and results with any savings to, or overages against, the Cost Estimate.
(b) samples of forms utilized to authorize changes on the Project;
(c) a flow diagram indicating the process to be utilized for changes;
(d) a sample log page showing the number and dollar amounts of Change Orders covering cumulative costs and effects on the Guaranteed Maximum Price;; and
(e) samples of standard change control reports submitted to the Owner and Design Professional;.
Appears in 2 contracts
Samples: Professional Services, Professional Services Agreement
Change and Budget Management Plan. The Construction Manager shall shallwill include in the Administrative Management Plans a Change and Budget Management Plan that includes:
(a) a sample monthly report to the Owner showing clear tracking of all bid package forecasts and results with any savings to, or overages against, the Cost Estimate.
(b) samples of forms utilized to authorize changes on the Project;
(c) a flow diagram indicating the process to be utilized for changes;
(d) a sample log page showing the number and dollar amounts of Change Orders covering cumulative costs and effects on the Guaranteed Maximum Price;; and
(e) samples of standard change control reports submitted to the Owner and Design Professional;.
Appears in 1 contract
Samples: Construction Management Agreement