Change Orders; Construction Progress Reports Sample Clauses
Change Orders; Construction Progress Reports. Promptly after receipt thereof, any Change Order or any document or written notice from the EPC Contractor, requesting or recommending the initiation of a Change Order. On or before the fifteenth day of each month until the Maturity Date, a construction progress report (with a copy to the Independent Engineer), in form and substance satisfactory to Agent and the Independent Engineer, detailing (i) Project Costs expended and construction milestones accomplished to date, (ii) projections of Project Costs necessary to complete the Project, (iii) the estimated PPA Commercial Operation Date, EPC Substantial Completion Date and date of Completion, (iv) the estimated date on which each remaining construction milestone set forth in the Construction Budget will be achieved, (v) status of Change Orders, (vi) monthly staffing levels and (vii) schedule deviations in construction milestone events.