Changes Ordered By City. City may at any time issue a written directive ordering additions, deletions, or changes to the Work. Contractor shall proceed with the work in accordance with the directive. To the extent the directive results in extra work or requires additional Contract Time, Contractor shall request a Change Order within seven (7) days of receiving the Work Directive. If any costs are not capable of being determined within seven (7) days, then Contractor shall request a Change Order within seven (7) days of when the costs are capable of being determined.
Appears in 4 contracts
Samples: Construction Contract, Construction Contract, Short Form Construction Contract