Changes to Cost. Subject to PMT approval, the Target Cost may be adjusted by the estimated increase in Chargeable Costs caused by one of the conditions set forth in Sections 12.1.1 through 12.1.6 above.
Changes to Cost. Subject to PMT approval, the Base Target Cost or Final Target Cost may be adjusted by the estimated increase in Chargeable Costs caused by one of the conditions set forth in Sections 11.1.1 through 11.1.10 above. Additional costs resulting from a Permitted Delay under Section 10.5 will not adjust the Base Target Cost, Final Target Cost or ICL unless and only to the extent that the delay was caused by one of the conditions set forth in Sections 11.1.1 through 11.1.10 above.