Changes to Critical Path Sample Clauses

POPULAR SAMPLE Copied 1 times
Changes to Critical Path. (a) Any changes to the critical path of the Construction Schedule initiated by Project Co which affect the Phased Occupancy Dates, the Scheduled Substantial Completion Date or the Scheduled Final Completion Date must be approved in writing by Owner. Subject to the terms of Schedule 11 – Change Procedure, any Owner approval of such changes to the critical path does not entitle Project Co to a Change Order, an extension of the Contract Time or an addition to the Guaranteed Price.
Changes to Critical Path. (a) Any changes to the critical path of the Works Schedule initiated by Project Co which affect the Scheduled Substantial Completion Date or the Scheduled Final Completion Date must be approved in writing by the College. Subject to the terms of Schedule 22 – Variation Procedure, any College approval of such changes to the critical path does not entitle Project Co to a Variation, an extension of time or an addition to the Guaranteed Price.
Changes to Critical Path. (a) Any changes to the critical path of the Works Schedule initiated by Project Co which affect the Scheduled Substantial Completion Date or the Scheduled Final Completion Date must be approved in writing by HMQ. Subject to the terms of Schedule 22 – Variation Procedure, any HMQ approval of such changes to the critical path does not entitle Project Co to a Variation, an extension of the Contract Time or an addition to the Guaranteed Price.
Changes to Critical Path. (a) Any change to the critical path of the Works Schedule initiated by Project Co which affects the Scheduled Phase Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion Date must be approved in writing by Contracting Authority. Subject to the terms of Schedule 22 – Variation Procedure, any Contracting Authority approval of such changes to the critical path does not entitle Project Co to a Variation, an extension of time or an addition to the Guaranteed Price. (b) Where Project Co proposes any change to the critical path of the Works Schedule, Project Co shall, no later than 2 Business Days following the written request of Contracting Authority, deliver to Contracting Authority a copy of the most current version of the Works Schedule and/or any past version of the Works Schedule requested by Contracting Authority in its native software format.
Changes to Critical Path. (a) Any changes to the critical path of the Construction Schedule initiated by Project Co which affect the Scheduled Substantial Completion Date or the Scheduled Final Completion Date must be approved in writing by STEGH. Subject to the terms of Schedule 11Change Procedure, any STEGH approval of such changes to the critical path does not entitle Project Co to a Change Order, an extension of the Contract Time or an addition to the Guaranteed Price. (b) Where Project Co proposes any change to the critical path of the Construction Schedule, Project Co shall, no later than 2 Business Days following the written request of STEGH, deliver to STEGH a copy of the most current version of the Construction Schedule and/or any past version of the Construction Schedule requested by STEGH in its native software format.
Changes to Critical Path. (a) Any changes to the critical path of the Construction Schedule initiated by Project Co which affect the Scheduled Substantial Completion Date or the Scheduled Final Completion Date must be approved in writing by CHH. Subject to the terms of Schedule 11Change Procedure, any CHH approval of such changes to the critical path does not entitle Project Co to a Change Order, an extension of the Contract Time or an addition to the Guaranteed Price. (b) Where Project Co proposes any change to the critical path of the Construction Schedule, Project Co shall, no later than 2 Business Days following the written request of CHH, deliver to CHH a copy of the most current version of the Construction Schedule and/or any past version of the Construction Schedule requested by CHH in its native software format.
Changes to Critical Path. (a) Any changes to the critical path of the Construction Schedule initiated by Project Co which affect the applicable Phased Occupancy Dates, the Scheduled Interim Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion Date must be approved in writing by CMH. Subject to the terms of Schedule 11Change Procedure, any CMH approval of such changes to the critical path does not entitle Project Co to a Change Order, an extension of the Contract Time or an addition to the Guaranteed Price. (b) At any time during the Project Term, Project Co shall, no later than 2 Business Days following the written request of CMH, deliver to CMH a copy of the most current version of the Construction Schedule and/or any past version of the Construction Schedule requested by CMH in electronic (non-PDF) software format.
Changes to Critical Path. (a) Any change to the critical path of the Works Schedule initiated by Project Co which affects a Scheduled Phase Completion Date, the Scheduled Tower Interim Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion Date must be approved in writing by JBH. Subject to the terms of Schedule 22 – Variation Procedure, any JBH approval of such changes to the critical path does not entitle Project Co to a Variation, an extension of time or an addition to the Guaranteed Price.