Common use of Changes to GMP Clause in Contracts

Changes to GMP. Subject to the condition precedent that the Construction Manager have complied with the notice and documentation provisions of this Article, and subject to the limitations stated in this Agreement, the Construction Manager is entitled to an adjustment to the Guaranteed Maximum Price in the following cases: .1 If the Department issues a Change Directive or Change Order that directs the Construction Manager to proceed with work which is beyond the scope of Work included within this Agreement; or .2 The Construction Manager encounters Differing Site Conditions or Hazardous Materials not identified in the Preconstruction Phase.

Appears in 4 contracts

Samples: Construction Management at Risk Agreement, Construction Management at Risk Agreement, Construction Management at Risk Agreement

AutoNDA by SimpleDocs

Changes to GMP. Subject to the condition precedent that the Construction Manager Contractor have complied with the notice and documentation provisions of this Article, and subject to the limitations stated in this Agreement, the Construction Manager Contractor is entitled to an adjustment to the Guaranteed Maximum Price in the following cases: .1 If the Department issues a Change Directive or Change Order that directs the Construction Manager Contractor to proceed with work which is beyond the scope of Work work included within this Agreement; or .2 The Construction Manager Contractor encounters Differing Site Conditions or Hazardous Materials not identified in the Preconstruction Phase.

Appears in 3 contracts

Samples: Construction Management at Risk Services Agreement, Construction Management at Risk Services, Construction Management at Risk Agreement

AutoNDA by SimpleDocs

Changes to GMP. Subject to the condition precedent that the Construction Manager have complied with the notice and documentation provisions of this Article, and subject to the limitations stated in this Agreement, the Construction Manager is entitled to an adjustment to the Guaranteed Maximum Price in the following cases: .1 (1) If the Department issues a Change Directive or Change Order that directs the Construction Manager to proceed with work which is beyond the scope of Work included within this Agreement; or .2 (2) The Construction Manager encounters Differing Site Conditions or Hazardous Materials not identified in the Preconstruction Phase.

Appears in 2 contracts

Samples: Construction Management at Risk Agreement, Construction Management at Risk Agreement

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!