Cleanup; Non-Interference. Contractor shall keep the Site reasonably free from waste materials or rubbish caused by its activities. During the period from Mechanical Completion until Commercial Operation, Contractor shall endeavor not to unreasonably interfere with the operation of the Facility. As soon as practicable after Mechanical Completion, Contractor shall remove its equipment and materials not constituting part of the Facility and not reasonably required by Contractor in connection with its achievement of Commercial Operation and shall completely remove waste material and rubbish from the Site and from surrounding areas to the extent generated by Contractor.
Appears in 3 contracts
Samples: Engineering, Procurement and Construction Agreement (USA Synthetic Fuel Corp), Engineering, Procurement and Construction Agreement (USA Synthetic Fuel Corp), Engineering, Procurement and Construction Agreement (Global Energy, Inc.)
Cleanup; Non-Interference. Contractor at all times shall keep the Site reasonably free from waste materials or rubbish caused by its or its Subcontractor's activities. During the period from Mechanical Substantial Completion until Commercial OperationFinal Completion, Contractor shall endeavor ensure that the performance of the Work does not to unreasonably interfere with the commercial operation of the FacilityFacilities. As soon as practicable after Mechanical Substantial Completion, Contractor shall remove its equipment Contractor's Equipment and materials not constituting part of the Facility and not reasonably required by Contractor in connection with its achievement of Commercial Operation and shall completely remove all waste material and rubbish from the Site and from surrounding areas and, to the extent generated by Contractorthe Work, from the surrounding areas.
Appears in 1 contract
Samples: Engineering, Procurement and Construction Contract (Omega Protein Corp)
Cleanup; Non-Interference. Contractor shall keep the Site reasonably free from waste materials or rubbish caused by its activities. During the period from Mechanical Substantial Completion until Commercial OperationFinal Completion, Contractor shall endeavor endeavour not to unreasonably interfere with the commercial operation of the Facility. As soon as practicable after Mechanical Substantial Completion, Contractor shall remove its equipment and materials not constituting part of the Facility and not reasonably required by Contractor in connection with its achievement of Commercial Operation and shall completely remove waste material and rubbish from the Site and from surrounding areas to the extent generated by Contractor.
Appears in 1 contract
Cleanup; Non-Interference. Contractor shall keep the Site reasonably free from waste materials or rubbish caused by its activities. During the period from Mechanical Substantial Completion until Commercial OperationFinal Completion, Contractor shall endeavor not to unreasonably interfere with the commercial operation of the Facility. As soon as practicable after Mechanical Substantial Completion, Contractor shall remove its equipment and materials not constituting part of the Facility and not reasonably required by Contractor in connection with its achievement of Commercial Operation and shall completely remove waste material and rubbish from the Site and from surrounding areas to the extent generated by Contractor.
Appears in 1 contract