Commercial Operation Date. 3.7.1 The Seller shall use its reasonable endeavours to achieve the Commercial Operation Date by the Scheduled COD. 3.7.2 If the Seller becomes aware that, for any reason, the Commercial Operation Date will not be achieved by the Scheduled COD, the Seller shall, without any unreasonable delay, notify the Buyer in writing of that fact and the measures that it will take to mitigate such delay and of the impact of such measures on its ability to achieve the Scheduled COD, upon implementing such measures.
Appears in 7 contracts
Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement
Commercial Operation Date. 3.7.1 The Seller shall use its reasonable endeavours to achieve the Commercial Operation Date by the Scheduled COD.
3.7.2 If the Seller becomes aware that, for any reason, the Commercial Operation Date will not be achieved by the Scheduled COD, the Seller shall, without any unreasonable delay, notify the Buyer DoE in writing of that fact and the measures that it will take to mitigate such delay and of the impact of such measures on its ability to achieve the Scheduled COD, upon implementing such measures.
Appears in 2 contracts
Commercial Operation Date. 3.7.1 The Seller shall use its reasonable endeavours to achieve the Commercial Operation Date by the Scheduled COD.
3.7.2 If the Seller becomes aware that, for any reason, the Commercial Operation Date will not be achieved by the Scheduled COD, the Seller shall, without any unreasonable delay, notify the Buyer in writing of that fact and the measures that it will take to mitigate such delay and of the impact of such measures on its ability to achieve the Scheduled COD, upon implementing such measures.
Appears in 1 contract
Samples: Power Purchase Agreement