Connectivity Synchronization Commissioning and Commercial Operation Sample Clauses

Connectivity Synchronization Commissioning and Commercial Operation 
AutoNDA by SimpleDocs

Related to Connectivity Synchronization Commissioning and Commercial Operation

  • Synchronization, Commissioning and Commercial Operation 4.1.1 The Power Producer shall give at least thirty (30) days written notice to the SLDC and GUVNL, of the date on which it intends to synchronize the Power Project to the Grid System.

  • Synchronisation Commissioning and Commercial Operation 8.1 The Developer shall provide at least forty (40) days advanced preliminary written notice and at least twenty (20) days advanced final written notice to ESCOM of the date on which it intends to synchronize the Power Project to the Grid System.

  • Design Development Phase Services 3.3.1 Based on the Owner’s approval of the Schematic Design Documents, and on the Owner’s authorization of any adjustments in the Project requirements and the budget for the Cost of the Work, the Architect shall prepare Design Development Documents for the Owner’s approval. The Design Development Documents shall illustrate and describe the development of the approved Schematic Design Documents and shall consist of drawings and other documents including plans, sections, elevations, typical construction details, and diagrammatic layouts of building systems to fix and describe the size and character of the Project as to architectural, structural, mechanical and electrical systems, and other appropriate elements. The Design Development Documents shall also include outline specifications that identify major materials and systems and establish, in general, their quality levels.

  • Building Commissioning Services The Owner may provide as a part of its testing services the Building Commissioning services involving the project’s HVAC and exhaust systems, temperature control systems, fire detection and alarm systems, emergency power and lighting system, fire suppression system, security locks and security locking control systems, food service equipment (if applicable), and laundry equipment (if applicable). In the event the Using Agency’s Program specifies additional commissioning services, the Owner shall procure such services as well. The Owner, through its Executive Administrator, may engage an independent Commissioning Authority. It is the intent of this Article that the Commissioning Authority enforce the requirements mentioned herein and certify that the systems and equipment listed all function properly prior to the initiation of each final inspection.

  • Project Management Plan 1 3.4.1 Developer is responsible for all quality assurance and quality control 2 activities necessary to manage the Work, including the Utility Adjustment Work.

  • Start-Up and Synchronization Consistent with the mutually acceptable procedures of the Developer and Connecting Transmission Owner, the Developer is responsible for the proper synchronization of the Large Generating Facility to the New York State Transmission System in accordance with NYISO and Connecting Transmission Owner procedures and requirements.

  • TESTING AND COMMISSIONING 24 Allow for a Lump Sum for testing and commissioning of the entire electrical installation, including the provision of Compliance Certificate. Item Carried to Collection R Section No. 4 Electrical Installation (Provisional) Bill No. 1 Electrical Installation COLLECTION Total Brought Forward from Page No. Carried to Final Summary 76 77 R Amount FINAL SUMMARY Section No Page No 1 Preliminaries 26 2 Alterations (Provisional) 30 3 External Works (Provisional) 73

  • Commercial Operation (i) On or before December 31, 2021, Interconnection Customer must demonstrate commercial operation of all generating units. Demonstrating commercial operation includes achieving Initial Operation in accordance with Section 1.4 of Appendix 2 to this ISA and making commercial sales or use of energy, as well as, if applicable, obtaining capacity qualification in accordance with the requirements of the Reliability Assurance Agreement Among Load Serving Entities in the PJM Region.

  • Network Interconnection Architecture Each Party will plan, design, construct and maintain the facilities within their respective systems as are necessary and proper for the provision of traffic covered by this Agreement. These facilities include but are not limited to, a sufficient number of trunks to the point of interconnection with the tandem company, and sufficient interoffice and interexchange facilities and trunks between its own central offices to adequately handle traffic between all central offices within the service areas at P.01 grade of service or better. The provisioning and engineering of such services and facilities will comply with generally accepted industry methods and practices, and will observe the rules and regulations of the lawfully established tariffs applicable to the services provided.

  • INTERNET PLANNING, ENGINEERING AND OPERATIONS ‌ Job Title: Internet/Web Engineer Job#: 2620 General Characteristics Integrally involved in the development and support of all Internet/Intranet/Extranet sites and supporting systems. Works closely with other IT groups and customers to define the system design and user interface based on customer needs and objectives. Participates in all phases of the development and implementation process, and may act as a project manager on special projects. Ensures the integration of the Web servers and all other supporting systems. Responsible for system tuning, optimization of information/data processing, maintenance and support of the production environment.