Completion of remaining Works Sample Clauses
Completion of remaining Works. All items in the Punch List shall be completed by the Contractor in accordance with the provisions of this Agreement. For any delay in their completion other than for the reasons solely attributable to the Authority or due to Force Majeure, the Authority shall be entitled to recover Damages from the Contractor in accordance with the provisions of Clause 10.3.2 of this Agreement.
Completion of remaining Works. All items in the Punch List shall be completed by the Contractor in accordance with the provisions of this Agreement. For any delay in their completion other than for the reasons solely attributable to the RSCL or due to Force Majeure, the RSCL shall be entitled to recover Damages from the Contractor in accordance with this Agreement.