Suspension of unsafe Construction Works Sample Clauses

Suspension of unsafe Construction Works. (i) Upon recommendation of the Authority’s Engineer to this effect, the Authority may by notice require the Contractor to suspend forthwith the whole or any part of the Works if, in the reasonable opinion of the Authority’s Engineer, such work threatens the safety of the Users and pedestrians.
AutoNDA by SimpleDocs
Suspension of unsafe Construction Works. 13.5.1 Upon recommendation of the Independent Engineer to this effect, the Authority may by notice require the Concessionaire to suspend forthwith the whole or any part of the Construction Works if, in the reasonable opinion of the Authority, such work threatens the safety of the Users and pedestrians. Provided, however, that in case of an Emergency, the Authority may suo moto issue the notice referred to hereinabove.
Suspension of unsafe Construction Works. 13.5.1 Upon recommendation of the Independent Engineer to this effect, MOR may by notice require the Concessionaire to suspend forthwith the whole or any part of the Construction Works if, in the reasonable opinion of MOR, such work threatens the safety of the Users and pedestrians.
Suspension of unsafe Construction Works. 13.3.1 Upon recommendation of the Independent Expert on any error or defect of a technical nature in the designs and Drawing without rectification of which the Project cannot be carried out as per this Agreement, the Authority may by notice require the Concessionaire to suspend forthwith the whole or any part of the Construction Works if, in the reasonable opinion of the Authority, such work threatens the safety of any equipment, maintenance or any individual on or about the Project. Provided, however, that in case of an emergency, the Authority may suo moto issue the notice referred to hereinabove.
Suspension of unsafe Construction Works. 13.5.1 Upon recommendation of the Independent Engineer to this effect, the Authority may by notice require the Concessionaire to suspend forthwith the whole or any part of the Construction Works if, in the reasonable opinion of the Authority, Such work threatens the safety of the Users and pedestrians. Provided, however, that in case of an emergency, the Authority may suo-moto issue the notice referred to hereinabove.
Suspension of unsafe Construction Works. Downloaded from
Suspension of unsafe Construction Works. 15.4.1 Upon recommendation of the PMC to this effect, the Licensor may by notice require the Licensee to suspend forthwith the whole or any part of the Construction Works if, in the reasonable opinion of the Licensor, such work threatens the safety of the users or people.
AutoNDA by SimpleDocs
Suspension of unsafe Construction Works. (i) Upon recommendation of the Authority’s Engineer to this effect, the Authority may by notice require the Contractor to suspend forthwith the whole or any part of the Works if, in the reasonable opinion of the Authority’s Engineer, such work threatens the safety of the Users and pedestrians. NH-202 for Package-I (Design Chainage 283+000 Km to 325+440 Km) in the State of Nagaland on EPC mode under NH (O)-NE mode” JAN 2022
Suspension of unsafe Construction Works. 13.5.1 Upon recommendation of the Independent Engineer to this effect, the Lead ULB may, by notice, require the Concessionaire to suspend forthwith the whole or any part of the Construction Work if, in the reasonable opinion of the Lead ULB, such work is unsafe and potential safety hazard.
Suspension of unsafe Construction Works. 9.13.1 In event its come to the notice of RSCL/PMC any impending risk to the work or the personnel on and around the project site, the RSCL may by notice require the Contractor to suspend forthwith the whole or any part of work if, in the reasonable opinion of the RSCL/PMC, such work threatens the safety of the Users and pedestrians.