Concurrent Delays. If an Inexcusable Delay occurs concurrently with either an Excusable Delay or a Compensable Delay, the Contractor may not recover damages for the period of the concurrency under the provisions of Article 6.6.2, and the maximum extension of the Contract Time shall be equal to the Excusable Delay or the Compensable Delay.

Appears in 2 contracts

Samples: Master Site Lease, Master Site Lease

AutoNDA by SimpleDocs

Concurrent Delays. 6.6.5.1. If an Inexcusable Delay occurs concurrently with either an Excusable Delay or a Compensable Delay, the Contractor may not recover damages for the period of the concurrency under the provisions of Article 6.6.2, and the maximum extension of the Contract Time shall be equal to the Excusable Delay or the Compensable Delay. 6.6.5.2. Notwithstanding the foregoing, the District’s failure to require compliance of any past delays shall not constitute a waiver or preclude it from enforcing such provisions in connection with any present or future delays.

Appears in 2 contracts

Samples: Master Site Lease, Master Site Lease

AutoNDA by SimpleDocs
Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!