Excusable Delay. The Contractor is entitled to an equitable adjustment of time, issued via Change Order, for delays caused by the following:
Excusable Delay. The parties shall not be obligated to perform and shall not be deemed to be in default hereunder, if the performance of a non-monetary obligation required hereunder is prevented by the occurrence of any of the following, other than as the result of the financial inability of the party obligated to perform: acts of God, strikes, lock-outs, other industrial disturbances, acts of a public enemy, war or war-like action (whether actual, impending or expected and whether de jure or de facto), acts of terrorists, arrest or other restraint of government (civil or military), blockades, insurrections, riots, epidemics, landslides, lightning, earthquakes, fires, hurricanes, storms, floods, washouts, sink holes, civil disturbances, explosions, breakage or accident to equipment or machinery, confiscation or seizure by any government or public authority, nuclear reaction or radiation, radioactive contamination or other causes, whether of the kind herein enumerated or otherwise, that are not reasonably within the control of the party claiming the right to delay performance on account of such occurrence.
Excusable Delay. (a) SELLER shall be excused from, and shall not be liable for, failure of performance to the extent due to causes beyond SELLER's control and without SELLER's fault or negligence, including, but not limited to, acts of God or public enemy, acts of Government in either sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, unusually severe weather and delays of common carriers.
Excusable Delay. Contractor shall be excused any delay in completion of the Work arising from a cause beyond its control which it could not with the exercise of due diligence have either foreseen or avoided, including act of governmental authority, act of God, extraordinary weather conditions, flood, accident such as fire or explosion not due to the negligence of Contractor, strike which is not the result of an unfair labor practice or other unlawful activity by Contractor, riot, failure of public transportation facilities, inability of Con Edison to provide access due to plant malfunctions, and inability to perform caused solely by Con Xxxxxx's act or failure to act in breach of an express obligation under the Contract. Delay in Contractor's receipt of subcontracted supplies or services for reasons beyond the control of the Subcontractor shall not be excusable delay hereunder to the extent that the supplies or services are available to Contractor from another source. The unavailability of sufficient, qualified labor to perform the Work shall not be excusable delay hereunder unless the unavailability is caused by a strike which is not the result of an unfair labor practice or other unlawful activity by Contractor. Contractor shall give written notice and full particulars of the cause of any delay within 48 hours after its occurrence and thereafter shall update Con Edison on a bi-weekly basis. The time for performance in any such instance shall be extended by a period equal to the time lost by reason of the excusable delay. Such extension shall be Contractor's sole and exclusive remedy for such delay and Con Edison shall not be liable for any damages or additional costs incurred as a result of such delay.
Excusable Delay. 9.1 If either party is unable to perform any of its obligations hereunder due to Force Majeure, the failure to perform by such party shall not constitute a basis for termination or default under this Agreement provided that notice thereof is given to the other party within seven (7) days after the party becomes aware of such event. OTG shall not be required to make any payment to the Consultant pursuant to Article 7 during the period of the Consultant's inability, as a result of an event of Force Majeure, to provide the Services and Facilities.
Excusable Delay. Neither party will be liable for any failure of or delay in performance of its obligations under this Agreement (other than failure to pay money when due) to the extent such failure or delay is due to circumstances beyond its reasonable control, including, without limitation, acts of God, acts of a public enemy, fires, wars, terrorist acts, civil disturbances, sabotage, accidents, pandemics, insurrections, blockades, embargoes, explosions, labor disputes, acts of any governmental body, failure or delay of third parties (including subcontractors) or governmental bodies from whom a party must obtain approvals, franchises, or permits, equipment failure or breakdown, or inability to obtain labor, materials, equipment or transportation, power shortage or blackouts (the foregoing collectively called “Excusable Delay”). Each party will use its best efforts to minimize the duration and consequences of any failure of or delay in performance resulting from an Excusable Delay.
Excusable Delay. A Delay for which Contractor may be entitled under the Contract Documents to an extension of time, but not compensation.
Excusable Delay. Notwithstanding anything to the contrary contained in this Agreement, the City’s exercise of any of its rights or remedies under this Article 11 shall be subject to the provisions regarding Excusable Delay in Section 15.8 below.
Excusable Delay. In the event of a delay caused by inclement weather, fire, flood, strike or other labor dispute, acts of God, acts of Governmental officials or agencies, or any other cause beyond the control of UCSD, UCSD's performance is excused hereunder for the periods of time attributable to such a delay, which may extend beyond the time lost due to one or more of the causes mentioned above. The Company's duty to pay for past or continuing costs is not suspended hereunder.
Excusable Delay. 16.2.1 Developer shall not be charged for liquidated damages because of any delays in completion of the Work which are not the fault of Developer or its Subcontractors, including without limitation acts of God as defined in Public Contract Code section 7105, acts of enemy, epidemics, and quarantine restrictions. Developer shall, within five (5) calendar days of beginning of any delay, including a Force Majeure event, notify District in writing of causes of delay including documentation and facts explaining the delay and the direct correlation between the cause and effect (“Notice of Delay”). If Developer fails to provide its written Notice of Delay within this timeframe, Developer waives, releases, and discharges any right to assert or claim any entitlement to an adjustment to the Guaranteed Maximum Price and/or the Contract Time based on circumstances giving rise to the asserted delay. District shall review the facts and extent of any delay and shall grant extension(s) of time for completing Work when, in its judgment, the findings of fact justify an extension. Extension(s) of time shall apply only to that portion of Work affected by delay and shall not apply to other portions of Work not so affected. An extension of time may only be granted if Developer has timely submitted the Construction Schedule as required herein.