CONNECTION WORKS. [Only applicable if new connection or extension] 4.1 Each Party will carry out their own respective Connection Works in accordance with this Clause 4.0, and the Quotation Letter. For the avoidance of doubt, the Customer’s Connection Works shall include the Terminal Sub-Station (if applicable) at no cost to the Company. 4.2 The Company shall prepare and provide the following specifications to the Customer: 4.2.1 the civil works, electrical and building services specification for the Terminal Sub-Station building and compound (if applicable) including services ("Terminal Sub-Station Works"); 4.2.2 the requirements and design for any equipment to be provided by the Customer under this Agreement which is not already specified in the Distribution Code or the documents listed in the Annexe “Supplementary Publications” of the Distribution Code, such requirements to be reasonably consistent with the Distribution Code and Good Industry Practice. 4.3 Each Party shall, immediately following satisfaction of the conditions precedent to the Agreement set out in Schedule 3, use its reasonable endeavours to obtain (and maintain) all such Consents as shall be necessary to enable their respective Connection Works to be completed. Any costs or reasonable expenses incurred by the Company in obtaining such Consents or meeting any conditions attached to such Consents shall be for the account of the Customer (in addition to the Connection Charges set out in the Quotation Letter) who shall, on receipt of the Company's invoice in respect of such costs and/or expenses, pay to the Company the amount of the invoice in accordance with the payment provisions contained in Clause 3.0 of the General Conditions (and, for the avoidance of doubt, regardless of whether the Company’s Connection Works are or can be completed and/or whether Energisation has occurred or can occur). The Company (acting in accordance with Good Industry Practice) shall incur only such costs and/or expenses as are reasonably necessary in the circumstances. 4.4 The Customer acknowledges that the Company has quoted the costs of the Company’s Connection Works to the Customer based on the assumptions set out in the Quotation Letter (“the Assumptions”). If at any time prior to completion of the Connection Works, the Company reasonably determines that any Assumption has not been, or is unlikely to be, met (for whatever reason) then without prejudice to the rights under Clause 4.3: 4.4.1.1 the Parties shall meet as soon as reasonably practicable to discuss alternative options available and the costs and expenses thereof; 4.4.1.2 and the Company shall prepare and submit to the Customer a revised Quotation Letter containing an alternative proposal which it is reasonably anticipated, will enable the Assumptions to be met, and/or the required Consents to be obtained but which is not, in the opinion of the Company (acting reasonably), likely to have adverse long term financial or technical implications for the Company.
Appears in 7 contracts
Samples: Connection Agreement, Connection Agreement, Connection Agreement
CONNECTION WORKS. [Only applicable if new connection or extension]
4.1 Each Party will carry out their own respective Connection Works in accordance with this Clause 4.0, and 4.0and the Quotation Letter. For the avoidance of doubt, the Customer’s Connection Works shall include the Terminal Sub-Sub- Station (if applicable) at no cost to the Company.
4.2 The Company shall prepare and provide the following specifications to the Customer:
4.2.1 the civil works, electrical and building services specification for the Terminal Sub-Station building and compound (if applicable) including services ("Terminal Sub-Station Works");
4.2.2 the requirements and design for any equipment to be provided by the Customer under this Agreement which is not already specified in the Distribution Code or the documents listed in the Annexe “Supplementary Publications” of the Distribution Code, such requirements to be reasonably consistent with the Distribution Code and Good Industry Practice.
4.3 Each Party shall, immediately following satisfaction of the conditions precedent to the Agreement set out in Schedule 3, use its reasonable endeavours to obtain (and maintain) all such Consents as shall be necessary to enable their respective Connection Works to be completed. Any costs or reasonable expenses incurred by the Company in obtaining such Consents or meeting any conditions attached to such Consents shall be for the account of the Customer (in addition to the Connection Charges set out in the Quotation Letter) who shall, on receipt of the Company's invoice in respect of such costs and/or expenses, pay to the Company the amount of the invoice in accordance with the payment provisions contained in Clause 3.0 of the General Conditions (and, for the avoidance of doubt, regardless of whether the Company’s Connection Works are or can be completed and/or whether Energisation has occurred or can occur). The Company (acting in accordance with Good Industry Practice) shall incur only such costs and/or expenses as are reasonably necessary in the circumstances.
4.4 The Customer acknowledges that the Company has quoted the costs of the Company’s Connection Works to the Customer based on the assumptions set out in the Quotation Letter (“the Assumptions”). If at any time prior to completion of the Connection Works, the Company reasonably determines that any Assumption has not been, or is unlikely to be, met (for whatever reason) then without prejudice to the rights under Clause 4.3:
4.4.1.1 the Parties shall meet as soon as reasonably practicable to discuss alternative options available and the costs and expenses thereof;
4.4.1.2 and the Company shall prepare and submit to the Customer a revised Quotation Letter containing an alternative proposal which it is reasonably anticipated, will enable the Assumptions to be met, and/or the required Consents to be obtained but which is not, in the opinion of the Company (acting reasonably), likely to have adverse long term financial or technical implications for the Company.
Appears in 1 contract
Samples: Major User Connection Agreement
CONNECTION WORKS. [Only applicable if new connection or extension]
4.1 Each Party will carry out their own respective Connection Works in accordance with this Clause 4.0, and the Quotation Letter. For the avoidance of doubt, the Customer’s Connection Works shall include the Terminal Sub-Station (if applicable) at no cost to the Company.
4.2 The Company shall prepare and provide the following specifications to the Customer:
4.2.1 the The civil works, electrical and building services specification for the Terminal Sub-Station building and compound (if applicable) including services ("Terminal Sub-Station Works");
4.2.2 the The requirements and design for any equipment to be provided by the Customer under this Agreement which is not already specified in the Distribution Code or the documents listed in the Annexe “Supplementary Publications” of the Distribution Code, such requirements to be reasonably consistent with the Distribution Code and Good Industry Practice.
4.3 Each Party shall, immediately following satisfaction of the conditions precedent to the Agreement set out in Schedule 3, use its reasonable endeavours to obtain (and maintain) all such Consents as shall be necessary to enable their respective Connection Works to be completed. Any costs or reasonable expenses incurred by the Company in obtaining such Consents or meeting any conditions attached to such Consents shall be for the account of the Customer (in addition to the Connection Charges set out in the Quotation Letter) who shall, on receipt of the Company's invoice in respect of such costs and/or expenses, pay to the Company the amount of the invoice in accordance with the payment provisions contained in Clause 3.0 of the General Conditions (and, for the avoidance of doubt, regardless of whether the Company’s Connection Works are or can be completed and/or whether Energisation has occurred or can occur). The Company (acting in accordance with Good Industry Practice) shall incur only such costs and/or expenses as are reasonably necessary in the circumstances.
4.4 The Customer acknowledges that the Company has quoted the costs of the Company’s Connection Works to the Customer based on the assumptions set out in the Quotation Letter (“the Assumptions”). If at any time prior to completion of the Connection Works, the Company reasonably determines that any Assumption has not been, or is unlikely to be, met (for whatever reason) then without prejudice to the rights under Clause 4.3:
4.4.1.1 the Parties shall meet as soon as reasonably practicable to discuss alternative options available and the costs and expenses thereof;
4.4.1.2 and the Company shall prepare and submit to the Customer a revised Quotation Letter containing an alternative proposal which it is reasonably anticipated, will enable the Assumptions (as set out in the Quotation Letter) to be met, and/or the required Consents to be obtained but which is not, in the opinion of the Company (acting reasonably), likely to have adverse long term financial or technical implications for the Company.
Appears in 1 contract
Samples: Connection Agreement
CONNECTION WORKS. [Only applicable if new connection or extension]
4.1 Each Party will carry out their own respective Connection Works in accordance with this Clause 4.0, and the Quotation Letter. For the avoidance of doubt, the Customer’s Connection Works shall include the Terminal Sub-Station (if applicable) at no cost to the Company.
4.2 The Company shall prepare and provide the following specifications to the Customer:
4.2.1 the civil works, electrical and building services specification for the Terminal Sub-Station building and compound (if applicable) including services ("Terminal Sub-Station Works");
4.2.2 the requirements and design for any equipment to be provided by the Customer under this Agreement which is not already specified in the Distribution Code or the documents listed in the Annexe “Supplementary Publications” of the Distribution Code, such requirements to be reasonably consistent with the Distribution Code and Good Industry Practice.
4.3 Each Party shall, immediately following satisfaction of the conditions precedent to the Agreement set out in Schedule 3, use its reasonable endeavours to obtain (and maintain) all such Consents as shall be necessary to enable their respective Connection Works to be completed. Any costs or reasonable expenses incurred by the Company in obtaining such Consents or meeting any conditions attached to such Consents shall be for the account of the Customer (in addition to the Connection Charges set out in the Quotation Letter) who shall, on receipt of the Company's invoice in respect of such costs and/or expenses, pay to the Company the amount of the invoice in accordance with the payment provisions contained in Clause 3.0 of the General Conditions (and, for the avoidance of doubt, regardless of whether the Company’s Connection Works are or can be completed and/or whether Energisation has occurred or can occur). The Company (acting in accordance with Good Industry Practice) shall incur only such costs and/or expenses as are reasonably necessary in the circumstances.
4.4 The Customer acknowledges that the Company has quoted the costs of the Company’s Connection Works to the Customer based on the assumptions set out in the Quotation Letter (“the Assumptions”). If at any time prior to completion of the Connection Works, the Company reasonably determines that any Assumption has not been, or is unlikely to be, met (for whatever reason) then without prejudice to the rights under Clause 4.3:
4.4.1.1 the Parties shall meet as soon as reasonably practicable to discuss alternative options available and the costs and expenses thereof;
4.4.1.2 4.4.1. 2 and the Company shall prepare and submit to the Customer a revised Quotation Letter containing an alternative proposal which it is reasonably anticipated, will enable the Assumptions to be met, and/or the required Consents to be obtained but which is not, in the opinion of the Company (acting reasonably), likely to have adverse long term financial or technical implications for the Company.