Construction Responsibilities. A. The State shall advertise for construction bids, issue bid proposals, receive and tabulate the bids, and award and administer the contract for construction of Project. Administration of the contract includes the responsibility for construction engineering and for issuance of any change orders, supplemental agreements, amendments, or additional work orders that may become necessary subsequent to the award of the construction contract. To ensure federal funding eligibility, projects must be authorized by State prior to advertising for construction. B. All contract letting and award procedures must be approved by State prior to letting and award of the construction contract, whether the construction contract is awarded by State or by Local Government. C. All contract change order review and approval procedures must be approved by State prior to start of construction. D. If the Local Government is the responsible party, the State must review and approve change orders. E. Upon completion of Project, the party constructing Project will issue and sign a “Notification of Completion” acknowledging Project’s construction completion. F. For federally funded contracts, the parties to this Agreement will comply with federal construction requirements provided in 23 CFR Parts 633 and 635, and shall include the latest version of Form “FHWA-1273” in the contract bidding documents. If force account work will be performed, a finding of cost effectiveness shall be made in compliance with 23 CFR Subpart 635.B. G. Any field changes, supplemental agreements, or revisions to the design plans that may occur after the construction contract is awarded will be mutually agreed to by State and Local Government prior to authorizing the contractor to perform the work. Prior to completion of Project, the party responsible for construction will notify the other party to this Agreement of the anticipated completion date. All parties will be afforded the opportunity to assist in the final review of the construction services performed by the contractor.
Appears in 3 contracts
Samples: Advance Funding Agreement, Advance Funding Agreement, Advance Funding Agreement
Construction Responsibilities. A. The State Local Government shall advertise for construction bids, issue bid proposals, receive and tabulate the bids, and award and administer the contract for construction of Project. Administration of the contract includes the responsibility for construction engineering and for issuance of any change orders, supplemental agreements, amendments, or additional work orders that may become necessary subsequent to the award of the construction contract. To ensure federal funding eligibility, projects must be authorized by State prior to advertising for construction.
B. All contract letting and award procedures must be approved by State prior to letting and award of the construction contract, whether the construction contract is awarded by State or by Local Government.
C. All contract change order review and approval procedures must be approved by State prior to start of construction.
D. If the Local Government is the responsible party, the State must review and approve change orders.
E. Upon completion of Project, the party constructing Project will issue and sign a “Notification of Completion” acknowledging Project’s construction completion.
F. For federally funded contracts, the parties to this Agreement will comply with federal construction requirements provided in 23 CFR Parts 633 and 635, and shall include the latest version of Form “FHWA-1273” in the contract bidding documents. If force account work will be performed, a finding of cost effectiveness shall be made in compliance with 23 CFR Subpart 635.B.
G. Any field changes, supplemental agreements, or revisions to the design plans that may occur after the construction contract is awarded will be mutually agreed to by State and Local Government prior to authorizing the contractor to perform the work. Prior to completion of Project, the party responsible for construction will notify the other party to this Agreement of the anticipated completion date. All parties will be afforded the opportunity to assist in the final review of the construction services performed by the contractor.
Appears in 3 contracts
Samples: Advance Funding Agreement, Advance Funding Agreement, Advance Funding Agreement
Construction Responsibilities. A. The State 9.1. Local Government shall advertise for construction bids, issue bid proposals, receive and tabulate the bids, and award and administer the contract for construction of Project. Administration of the contract includes the responsibility for construction engineering and for issuance of any change orders, supplemental agreements, amendments, or additional work orders that may become necessary subsequent to the award of the construction contract. To In order to ensure federal funding eligibility, projects must be authorized by State prior to advertising for construction.
B. 9.2. All contract letting and award procedures must be approved by State prior to letting and award of the construction contract, whether the construction contract is awarded by State or by Local Government.
C. 9.3. All contract change order review and approval procedures must be approved by State prior to start of construction.
D. If the Local Government is the responsible party, the State must review and approve change orders.
E. 9.4. Upon completion of Project, the party constructing Project will issue and sign a “Notification of Completion” acknowledging Project’s construction completion.
F. 9.5. For federally funded contracts, the parties to this Agreement will comply with federal construction requirements provided in 23 CFR Parts 633 and 635, and shall include the latest version of Form “FHWA-1273FHWA- 1273” in the contract bidding documents. If force account work will be performed, a finding of cost effectiveness shall be made in compliance with 23 CFR Subpart 635.B.
G. 9.6. Any field changes, supplemental agreements, or revisions to the design plans that may occur after the construction contract is awarded will be mutually agreed to by State and Local Government prior to authorizing the contractor to perform the work. Prior to completion of Project, the party responsible for construction will notify the other party to this Agreement of the anticipated completion date. All parties will be afforded the opportunity to assist in the final review of the construction services performed by the contractor.
Appears in 2 contracts
Samples: Local Project Advance Funding Agreement, Local Project Advance Funding Agreement
Construction Responsibilities. A. The State Local Government shall advertise for construction bids, issue bid proposals, receive and tabulate the bids, and award and administer the contract for construction of Project. Administration of the contract includes the responsibility for construction engineering and for issuance of any change orders, supplemental agreements, amendments, or additional work orders that may become necessary subsequent to the award of the construction contract. To In order to ensure federal funding eligibility, projects must be authorized by State prior to advertising for construction.
B. All contract letting and award procedures must be approved by State prior to letting and award of the construction contract, whether the construction contract is awarded by State or by Local Government.
C. All contract change order review and approval procedures must be approved by State prior to start of construction.
D. If the Local Government is the responsible party, the State must review and approve change orders.
E. Upon completion of Project, the party constructing Project will issue and sign a “Notification of Completion” acknowledging Project’s construction completion.
F. E. For federally funded contracts, the parties to this Agreement will comply with federal construction requirements provided in 23 CFR Parts 633 and 635, and shall include the latest version of Form “FHWA-1273” in the contract bidding documents. If force account work will be performed, a finding of cost effectiveness shall be made in compliance with 23 CFR Subpart 635.B.
G. F. Any field changes, supplemental agreements, or revisions to the design plans that may occur after the construction contract is awarded will be mutually agreed to by State and Local Government prior to authorizing the contractor to perform the work. Prior to completion of Project, the party responsible for construction will notify the other party to this Agreement of the anticipated completion date. All parties will be afforded the opportunity to assist in the final review of the construction services performed by the contractor.
Appears in 1 contract
Samples: Advance Funding Agreement
Construction Responsibilities. A. The State Local Government shall advertise for construction bids, issue bid proposals, receive and tabulate the bids, and award and administer the contract for construction of Project. Administration of the contract includes the responsibility for construction engineering and for issuance of any change orders, supplemental agreements, amendments, or additional work orders that may become necessary subsequent to the award of the construction contract. To ensure federal funding eligibility, projects must be authorized by State prior to advertising for construction.
B. All contract letting and award procedures must be approved by State prior to letting and award of the construction contract, whether the construction contract is awarded by State or by Local Government.
C. All contract change order review and approval procedures must be approved by State prior to start of construction.
D. If the Local Government is the responsible party, the State must review and approve change orders.
E. Upon completion of Project, the party constructing Project will issue and sign a “Notification of Completion” acknowledging Project’s construction completion.
F. For federally funded contracts, the parties to this Agreement will comply with federal construction requirements provided in 23 CFR Parts 633 and 635, and shall include the latest version of Form “FHWA-1273” in the contract bidding documents. If force account work will be performed, a finding of cost effectiveness shall be made in compliance with 23 CFR Subpart 635.B.
G. Any field changes, supplemental agreements, or revisions to the design plans that may occur after the construction contract is awarded will be mutually agreed to by State and Local Government prior to authorizing the contractor to perform the work. Prior to completion of Project, the party responsible for construction will notify the other party to this Agreement of the anticipated completion date. All parties will be afforded the Project Name Main Street ADA Ramps & 1st Street Sidewalks AFA Not Used For Research & Development opportunity to assist in the final review of the construction services performed by the contractor.
Appears in 1 contract
Samples: Advance Funding Agreement
Construction Responsibilities. A. 10.1. The State shall advertise for construction bids, issue bid proposals, receive and tabulate the bids, and award and administer the contract for construction of Project. Administration of the contract includes the responsibility for construction engineering and for issuance of any change orders, supplemental agreements, amendments, or additional work orders that may become necessary subsequent to the award of the construction contract. To In order to ensure federal funding eligibility, projects must be authorized by State prior to advertising for construction.
B. 10.2. All contract letting and award procedures must be approved by State prior to letting and award of the construction contract, whether the construction contract is awarded by State or by Local Government.
C. 10.3. All contract change order review and approval procedures must be approved by State prior to start of construction.
D. If the Local Government is the responsible party, the State must review and approve change orders.
E. 10.4. Upon completion of Project, the party constructing Project will issue and sign a “Notification of Completion” acknowledging Project’s construction completion.. AFA-AFA_TAP Page 6 of 14 Revised 2016-03-23 CSJ: 0000-00-000 District #: CRP 16 Code Chart 64#: 01550 Project: Aransas Pass Shared Use Path CFDA Title: Highway Planning and Construction CFDA Number: 20.205 Federal Highway Administration Not Research and Development
F. 10.5. For federally funded contracts, the parties to this Agreement will comply with federal construction requirements provided in 23 CFR Parts 633 and 635, and shall include the latest version of Form “FHWA-1273FHWA- 1273” in the contract bidding documents. If force account work will be performed, a finding of cost effectiveness shall be made in compliance with 23 CFR Subpart 635.B.
G. 10.6. Any field changes, supplemental agreements, or revisions to the design plans that may occur after the construction contract is awarded will be mutually agreed to by State and Local Government prior to authorizing the contractor to perform the work. Prior to completion of Project, the party responsible for construction will notify the other party to this Agreement of the anticipated completion date. All parties will be afforded the opportunity to assist in the final review of the construction services performed by the contractor.
Appears in 1 contract
Samples: Advance Funding Agreement
Construction Responsibilities. A. The State Local Government shall advertise for construction bids, issue bid proposals, receive and tabulate the bids, and award and administer the contract for construction of Project. Administration of the contract includes the responsibility for construction engineering and for issuance of any change orders, supplemental agreements, amendments, or additional work orders that may become necessary subsequent to the award of the construction contract. To In order to ensure federal funding eligibility, projects must be authorized by State prior to advertising for construction.
B. All contract letting and award procedures must be approved by State prior to letting and award of the construction contract, whether the construction contract is awarded by State or by Local Government.
C. All contract change order review and approval procedures must be approved by State prior to start of construction.
D. If the Local Government is the responsible party, the State must review and approve change orders.
E. Upon completion of Project, the party constructing Project will issue and sign a “Notification of Completion” acknowledging Project’s construction completion.
F. E. For federally funded contracts, the parties to this Agreement will comply with federal construction requirements provided in 23 CFR Parts 633 and 635, and shall include the latest version of Form “FHWA-1273” in the contract bidding documents. If force account work will be performed, a finding of cost effectiveness shall be made in compliance with 23 CFR Subpart 635.B.
G. F. Any field changes, supplemental agreements, or revisions to the design plans that may occur after the construction contract is awarded will be mutually agreed to by State and Local Government prior to authorizing the contractor to perform the work. Prior to completion of Project, the party responsible for construction will notify the other party to this Agreement of the anticipated completion date. All parties will be afforded the opportunity to assist in the final review of the construction services performed by the contractor.the
Appears in 1 contract
Samples: Advance Funding Agreement
Construction Responsibilities. A. The State {Select LG or State} shall advertise for construction bids, issue bid proposals, receive and tabulate the bids, and award and administer the contract for construction of Project. Administration of the contract includes the responsibility for construction engineering and for issuance of any change orders, supplemental agreements, amendments, or additional work orders that may become necessary subsequent to the award of the construction contract. To ensure federal funding eligibility, projects must be authorized by State prior to advertising for construction.
B. All contract letting and award procedures must be approved by State prior to letting and award of the construction contract, whether the construction contract is awarded by State or by Local Government.
C. All contract change order review and approval procedures must be approved by State prior to start of construction.
D. If the Local Government is the responsible party, the State must review and approve change orders.
E. Upon completion of Project, the party constructing Project will issue and sign a “Notification of Completion” acknowledging Project’s construction completion.
F. For federally funded contracts, the parties to this Agreement will comply with federal construction requirements provided in 23 CFR Parts 633 and 635, and shall include the latest version of Form “FHWA-1273” in the contract bidding documents. If force account work will be performed, a finding of cost effectiveness shall be made in compliance with 23 CFR Subpart 635.B.
G. Any field changes, supplemental agreements, or revisions to the design plans that may occur after the construction contract is awarded will be mutually agreed to by State and Local Government prior to authorizing the contractor to perform the work. Prior to completion of Project, the party responsible for construction will notify the other party to this Agreement of the anticipated completion date. All parties will be afforded the opportunity to assist in the final review of the construction services performed by the contractor.
Appears in 1 contract
Samples: Advance Funding Agreement
Construction Responsibilities. A. The State shall advertise for construction bids, issue bid proposals, receive and tabulate the bids, and award and administer the contract for construction of Project. Administration of the contract includes the responsibility for construction engineering and for issuance of any change orders, supplemental agreements, amendments, or additional work orders that may become necessary subsequent to the award of the construction contract. To ensure federal funding eligibility, projects must be authorized by State prior to advertising for construction.
B. All contract letting and award procedures must be approved by State prior to letting and award of the construction contract, whether the construction contract is awarded by State or by Local Government.
C. All contract change order review and approval procedures must be approved by State prior to start of construction.
D. If the Local Government is the responsible party, the State must review and approve change orders.
E. Upon completion of Project, the party constructing Project will issue and sign a x “Notification of Completion” acknowledging Project’s construction completion.
F. For federally funded contracts, the parties to this Agreement will comply with federal construction requirements provided in 23 CFR Parts 633 and 635, and shall include the latest version of Form “FHWA-1273” in the contract bidding documents. If force account work will be performed, a finding of cost effectiveness shall be made in compliance with 23 CFR Subpart 635.B.
G. Any field changes, supplemental agreements, or revisions to the design plans that may occur after the construction contract is awarded will be mutually agreed to by State and Local Government prior to authorizing the contractor to perform the work. Prior to completion of Project, the party responsible for construction will notify the other party to this Agreement of the anticipated completion date. All parties will be afforded the opportunity to assist in the final review of the construction services performed by the contractor.
Appears in 1 contract
Samples: Advance Funding Agreement
Construction Responsibilities. A. The State Local Government shall advertise for construction bids, issue bid proposals, receive and tabulate the bids, and award and administer the contract for construction of the Project. Administration of the contract includes the responsibility for construction engineering and for issuance of any change orders, supplemental agreements, amendments, or additional work orders that may become necessary subsequent to the award of the construction contract. To In order to ensure federal funding eligibility, projects must be authorized by the State prior to advertising for construction.
B. All contract letting and award procedures must be approved by the State prior to letting and award of the construction contract, whether the construction contract is awarded by the State or by the Local Government.
C. All contract change order review and approval procedures must be approved by the State prior to start of construction.
D. If the Local Government is the responsible party, the State must review and approve change orders.
E. Upon completion of the Project, the party constructing the Project will issue and sign a “Notification of Completion” acknowledging the Project’s construction completion.
F. E. For federally funded contracts, the parties to this Agreement will comply with federal construction requirements provided cited in 23 CFR Parts 633 Part 635 and 635with requirements cited in 23 CFR Part 633, and shall include the latest version of Form “FHWA-1273” in the contract bidding documents. If force account work will be performed, a finding of cost effectiveness shall be made in compliance with 23 CFR Part 635, Subpart 635.B.B.
G. F. Any field changes, supplemental agreements, or revisions to the design plans that may occur after the construction contract is awarded will be mutually agreed to by the State and the Local Government prior to authorizing the contractor to perform the work. Prior to completion of the Project, the party responsible for construction will notify the other party to this Agreement of the anticipated completion date. All parties will be afforded the opportunity to assist in the final review of the construction services performed by the contractor.