CONSTRUCTION STAGE COMPENSATION. 3.1 As described in the General Conditions, the parties will establish the Contract Sum, Contract Times, Milestones, and other commercial terms relevant to the Construction Stage through at least one GMP Amendment, the form of which is attached as Exhibit G. 3.2 The DB shall propose the amount of the DB’s Construction Stage Personnel Costs portion of the Cost of the Work as a part of the proposed GMP Amendment; provided, however, that the DB’s Construction Stage Personnel Costs shall not exceed «insert DB’s Construction Stage Personnel Costs cap» dollars ($0.00). 3.2.1 The DB’s Construction Stage Personnel Costs shall be based upon the rates set forth in the Personnel Costs Rate Schedule attached as Exhibit D. 3.3 The DB shall propose the amount of the General Conditions Costs portion of the Cost of the Work as a part of the proposed GMP Amendment; provided, however, that the General Conditions Costs shall not exceed «insert General Conditions Costs cap» dollars ($0.00). 3.3.1 A detailed description of the items of Work included in the General Conditions Costs portion of the Cost of the Work is set forth in the General Conditions Costs Description attached as Exhibit F. 3.4 The DB shall propose the amount of the DB’s Contingency as a part of the proposed GMP Amendment; provided, however, that the DB’s Contingency shall not exceed an amount equal to «insert DB Contingency percentage» percent (0.0%) of the Cost of the Work identified by the DB in the proposed GMP Amendment. Section 3.4.1 is immediately below and shall be used in this Agreement unless the University and DB agree otherwise, in which case it should be revised to the agreed percentage.
Appears in 2 contracts
Samples: Professional Services, Professional Services
CONSTRUCTION STAGE COMPENSATION. 3.1 As described in the General Conditions, the parties will establish the Contract Sum, Contract Times, Milestones, and other commercial terms relevant to the Construction Stage through at least one GMP Amendment, the form of which is attached as Exhibit G.D.
3.2 The DB CM shall propose the amount of the DBCM’s Construction Stage Personnel Costs portion of the Cost of the Work as a part of the proposed GMP Amendment; provided, however, that the DBCM’s Construction Stage Personnel Costs shall not exceed «insert DBCM’s Construction Stage Personnel Costs cap» cap dollars ($0.000,000.00)».
3.2.1 The DBCM’s Construction Stage Personnel Costs shall be based upon the rates set forth in the Personnel Costs Rate Schedule attached as Exhibit D.A.
3.3 The DB CM shall propose the amount of the General Conditions Costs portion of the Cost of the Work as a part of the proposed GMP Amendment; provided, however, that the General Conditions Costs shall not exceed «insert General Conditions Costs cap» cap dollars ($0.000,000.00).
3.3.1 A detailed description of the items of Work included in the General Conditions Costs portion of the Cost of the Work is set forth in the General Conditions Costs Description attached as Exhibit F.C.
3.4 The DB CM shall propose the amount of the DBCM’s Contingency as a part of the proposed GMP Amendment; provided, however, that the DBCM’s Contingency shall not exceed an amount equal to «insert DB CM Contingency percentage» percent (0.0%x%) of the Cost of the Work identified by the DB CM in the proposed GMP Amendment.
Section 3.4.1 is immediately below and shall be used in this Agreement unless the University and DB CM agree otherwise, in which case it should be revised to the agreed percentage.
Appears in 2 contracts
Samples: Professional Services, Construction Manager at Risk Agreement
CONSTRUCTION STAGE COMPENSATION. 3.1 As described in the General Conditions, the parties will establish the Contract Sum, Contract Times, Milestones, and other commercial terms relevant to the Construction Stage through at aat least one GMP Amendment, the form of which is attached as Exhibit G.D.
3.2 The DB CM shall propose the amount of the DBCM’s Construction Stage Personnel Costs portion of the Cost of the Work as a part of the proposed GMP Amendment; provided, however, that the DBCM’s Construction Stage Personnel Costs shall not exceed $«insert DBCM’s Construction Stage Personnel Costs cap» dollars ($0.00).». Version Control Document
3.2.1 The DBCM’s Construction Stage Personnel Costs shall be based upon the rates set forth in the Personnel Costs Rate Schedule attached as Exhibit D.A.
3.3 The DB CM shall propose the amount of the General Conditions Costs portion of the Cost of the Work as a part of the proposed GMP Amendment; provided, however, that the General Conditions Costs shall not exceed an amount equal to «$«insert General Conditions Costs cappercentage» dollars ($0.00)percent of the Cost of the Work identified by the CM in the proposed GMP Amendment.cap».
3.3.1 A detailed description of the items of Work included in the General Conditions Costs portion of the Cost of the Work is set forth in the General Conditions Costs Description attached as Exhibit F.C.
3.4 The DB CM shall propose the amount of the DBCM’s Contingency as a part of the proposed GMP Amendment; provided, however, that the DBCM’s Contingency shall not exceed an amount equal to «insert DB CM Contingency percentage» percent (0.0%) of the Cost of the Work identified by the DB CM in the proposed GMP Amendment.
Section 3.4.1 is immediately below and shall be used in this Agreement unless the University and DB agree otherwise, in which case it should be revised to the agreed percentage.
Appears in 1 contract
Samples: Cm at Risk Contract