Continuing the Work. Except as otherwise provided, Contractor shall carry on the Work and adhere to the Project Schedule during all disputes or disagreements with City. No Work shall be delayed or postponed pending resolution of any disputes or disagreements, except as City and Contractor may otherwise agree in writing.
Appears in 7 contracts
Samples: Construction Contract, Construction Contract, Construction Contract
Continuing the Work. Except as otherwise provided, Contractor shall carry on the Work and adhere to the Project Schedule progress schedule during all disputes disputes, disagreements, or disagreements alternative resolution processes with City. No Contractor shall not delay or postpone any Work shall be delayed because of pending unresolved disputes, disagreements or postponed pending alternative resolution of any disputes or disagreementsprocesses, except as City and Contractor may otherwise agree in writing.
Appears in 1 contract
Samples: Design Build Services Agreement