Contract Price Adjustment; Contractor Documentation. If a Change Order is executed on a time and material basis pursuant to Section 6.1C or 6.2D, then the Contract Price shall be adjusted as set forth in Schedule D-4. Contractor shall use reasonable efforts to minimize such costs (consistent with the requirements of this Agreement).
Appears in 17 contracts
Samples: Lump Sum Turnkey Agreement, Lump Sum Turnkey Agreement (Sabine Pass Liquefaction, LLC), Fixed Price Separated Turnkey Agreement (Cheniere Corpus Christi Holdings, LLC)
Contract Price Adjustment; Contractor Documentation. If a Change Order is executed on a time and material basis pursuant to Section 6.1C or 6.2D, then the Contract Price shall be adjusted as set forth in Schedule D-44-4. Contractor shall use reasonable efforts to minimize such costs (consistent with the requirements of this Agreement).
Appears in 4 contracts
Samples: Lump Sum Turnkey Agreement (Tellurian Inc. /De/), Lump Sum Turnkey Agreement (Tellurian Inc. /De/), Lump Sum Turnkey Agreement (Tellurian Inc. /De/)
Contract Price Adjustment; Contractor Documentation. If a Change Order is executed on a time and material materials basis pursuant to Section 6.1C or 6.2D, then the Contract Price costs incurred in performing such Change Order shall be adjusted determined as set forth in Schedule D-4. Contractor shall use reasonable efforts to minimize such costs (consistent with the requirements of this Agreement).follows:
Appears in 2 contracts
Samples: Lump Sum Turnkey Agreement (Mirant Corp), Lump Sum Turnkey Agreement (Mirant Corp)