Correction of Defects. 35.1 The Engineer shall give notice to the Contractor of any Defects before the end of the Defects Liability Period, which begins at Completion and is defined in the Contract Data. The Defects Liability Period shall be extended for as long as Defects remain to be corrected. 35.2 Every time notice of a Defect is given, the Contractor shall correct the notified Defect within the length of time specified by the Engineer’s notice.
Appears in 53 contracts
Samples: Construction Contract, Construction Contract, Construction Contract
Correction of Defects. 35.1 The Engineer Engineer-in-Charge shall give notice to the Contractor of any Defects before the end of the Defects Liability Period, which begins at Completion and is defined in the Contract Dataon Completion. The Defects Liability Period defects liability period shall be extended for as long as Defects defects remain to be corrected.
35.2 corrected by the Contractor. Every time notice of a Defect is given, the Contractor shall correct the notified Defect defect within the length of time specified by the Engineer-in-Charge’s notice.
Appears in 7 contracts
Samples: Proposed Rate Contract for Routine Maintenance Works, Proposed Rate Contract for Routine Maintenance Works, Rate Contract
Correction of Defects. 35.1 The Engineer shall give notice to the Contractor of any Defects before the end of the Defects Liability Period, which begins at Completion and is defined in the Contract Datacompletion. The Defects Liability Period shall be extended for as long as Defects remain to be corrected.
35.2 . Every time time, notice of a Defect is given, the Contractor shall correct the notified Defect within the length of time specified by the Engineer’s 's notice.
Appears in 3 contracts
Samples: Turnkey Contract, Turnkey Contract, Turnkey Contract
Correction of Defects. 35.1 The Engineer shall give notice to the Contractor of any Defects before the end of the Defects Liability Period, which begins at Completion and is defined in the Contract Data. The Defects Liability Period shall be extended for as long as Defects remain to be corrected.
35.2 Every time notice of a Defect is given, the Contractor shall correct the notified Defect within the length of time specified by the Engineer’s Engineer‟s notice.
Appears in 3 contracts
Samples: Bidding Agreement, Bidding Agreement, Punjab Rural Water Supply & Sanitation Project Agreement
Correction of Defects. 35.1 35.1. The Engineer shall give notice to the Contractor of any Defects before the end of the Defects Liability Period, which begins at Completion and is defined in the Contract Data. The Defects Liability Period shall be extended for as long as Defects remain to be corrected.
35.2 35.2. Every time notice of a Defect is given, the Contractor shall correct the notified Defect within the length of time specified by the Engineer’s notice.
Appears in 2 contracts
Samples: Construction Contract, Bidding Document
Correction of Defects. 35.1 33.1. The Engineer shall give notice to the Contractor of any Defects before the end of the Defects Liability Period, which begins at Completion and is defined in the Contract Data. The Defects Liability Period shall be extended for as long as Defects remain to be corrected.
35.2 Every time notice of a Defect is given, the Contractor shall correct the notified Defect within the length of time specified by the Engineer’s notice.
Appears in 2 contracts
Samples: Bid Document, Bid Document
Correction of Defects. 35.1 The Engineer shall give notice to the Contractor of any Defects before the end of the Defects Liability Period, which begins at Completion and is defined in the Contract Data. The Defects Liability Period shall be extended for as long as Defects remain to be corrected.
35.2 Every time notice of a Defect is given, the Contractor shall correct the notified Defect within the length of time specified by the Engineer’s notice.
Appears in 2 contracts
Samples: Tender Agreement, Construction Contract
Correction of Defects. 35.1 The Engineer shall give notice to the Contractor of any Defects (specifying a time by which it should be corrected) before the end of the Defects Liability Period, which begins at Completion and is defined in the Contract Data. The Defects Liability Period shall be extended for as long as Defects remain to be corrected.
35.2 Every time notice of a Defect is given, the Contractor shall correct the notified Defect within the length of time specified by the Engineer’s notice.
Appears in 1 contract
Samples: Construction Contract
Correction of Defects. 35.1 31.1 The Engineer shall give notice to the Contractor of any Defects before the end of the Defects Liability Period, which begins at Completion and is defined in the Contract Data. The Defects Liability Period shall be extended for as long as Defects remain to be corrected.
35.2 31.2 Every time notice of a Defect is given, the Contractor shall correct the notified Defect within the length of time specified by the Engineer’s notice.
Appears in 1 contract
Samples: Construction Contract
Correction of Defects. 35.1 The 1The Engineer shall give notice to the Contractor of any Defects before the end of the Defects Liability Period, which begins at Completion and is defined in the Contract Data. The Defects Liability Period shall be extended for as long as Defects remain to be corrected.
35.2 Every time notice of a Defect is given, the Contractor shall correct the notified Defect within the length of time specified by the Engineer’s notice.
Appears in 1 contract
Samples: Construction Contract
Correction of Defects. 35.1 The Engineer shall give notice to the Contractor of any Defects (specifying a time by which it should be corrected) before the end of the Defects Liability Period, which begins at Completion and is defined in the Contract Data. The Defects Liability Period shall be extended for as long as Defects remain to be corrected.
35.2 Every time notice of a Defect is given, the Contractor shall correct the notified Defect within the length of time specified by the Engineer’s Engineer‘s notice.
Appears in 1 contract
Samples: Construction Contract
Correction of Defects. 35.1 31.1 The Engineer Employer shall give notice Notice to the Contractor of any Defects before the end End of the Defects Liability Period, which begins at Completion and is defined in the Contract Data. The Defects Liability Period shall be extended for as long as Defects remain to be corrected.
35.2 31.2 Every time notice Notice of a Defect is given, the Contractor shall correct the notified Notified Defect within the length Length of time Time specified by the EngineerEmployer’s noticeNotice.
Appears in 1 contract
Samples: Construction Contract
Correction of Defects. 35.1 The Engineer shall give notice to the Contractor of any Defects before the end of the Defects Liability Period, which begins at Completion and is defined in the Contract Data. The Defects Liability Period shall be extended for as long as Defects remain to be corrected.
35.2 Every time notice of a Defect is given, the Contractor shall correct the notified Defect within the length of time specified by the Engineer’s 's notice.
Appears in 1 contract
Samples: Construction Agreement
Correction of Defects. 35.1 35.1. The Engineer shall give notice to the Contractor of any Defects before the end of the Defects Liability Period, which begins at Completion and is defined in the Contract Data. The Defects Liability Period shall be extended for as long as Defects remain to be corrected.
35.2 35.2. Every time notice of a Defect is given, the Contractor shall correct the notified Defect within the length of time specified by the Engineer’s 's notice.
Appears in 1 contract
Samples: Procurement Agreement
Correction of Defects. 35.1 The Engineer shall give notice to the Contractor of any Defects before the end of the Defects Liability Period, which begins at Completion and is defined in the Contract Data. The Defects Liability Period shall be extended for as long as Defects remain to be corrected.
35.2 Every time notice of a Defect is given, the Contractor shall correct the notified Defect defect within the length of time specified by the Engineer’s notice.
35.3 The Contractor shall correct the defects noticed during the Operation and Maintenance of the Plant within the time specified in the Engineers notice.
Appears in 1 contract
Samples: Construction Contract
Correction of Defects. 35.1 35.1. The Engineer shall give notice to the Contractor of any Defects before the end of the Defects Liability Period, which begins at Completion and is defined in the Contract Data. The Defects Liability Period shall be extended for as long as Defects remain to be corrected.
35.2 35.2. Every time notice of a Defect is given, the Contractor shall correct the notified Defect within the length of time specified by the Engineer’s notice.notified
Appears in 1 contract
Samples: Bid Document