Correction Period. If within one (1) year after the date of Substantial Completion or such longer period of time as may be prescribed by Laws or Regulations or by the terms of any applicable special guarantee required by the Contract Documents or by any specific provision of the Contract Documents, any Work is found to be defective, or if the repair of any damages to the land or areas made available for Contractor's use by Owner or permitted by Laws and Regulations is found to be defective, Contractor shall promptly, without cost to Owner and in accordance with Owner's written instructions: (i) repair such defective land or areas, or (ii) correct such defective Work or, if the defective Work has been rejected by Architect and/or Owner, remove it from the Project and replace it with Work that is not defective, and (iii) satisfactorily correct or repair or remove and replace any damage to other Work, to the work of others or other land or areas resulting therefrom. If Contractor does not promptly comply with the terms of such instructions, or in an emergency where delay would cause serious risk of loss or damage, Owner may have the defective Work corrected or repaired or may have the rejected Work removed and replaced, and all Claims, costs, losses, and damages (including but not limited to all fees and charges of Architect, Architect’s Consultants, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to such correction or repair or such removal and replacement (including but not limited to all costs of repair or replacement of work of others) will be paid by Contractor. In special circumstances where a particular item of equipment is placed in continuous service before Substantial Completion of all the Work, the correction period for that item may start to run from an earlier date if so provided in the Specifications or by Written Amendment. Where defective Work (and damage to other Work resulting therefrom) has been corrected or removed and replaced, the correction period hereunder with respect to such Work will be extended for an additional period of one (1) year after such correction or removal and replacement has been satisfactorily completed. Contractor's obligations under this paragraph are in addition to any other obligation or warranty. The provisions of this paragraph shall not be construed as a substitute for or a waiver of the provisions of any applicable statute of limitation or repose. Contr...
AutoNDA by SimpleDocs
Correction Period. (1) End of correction period. The last day of the correction period for an Operational Failure is the last day of the second plan year following the plan year for which the failure occurred. However, in the case of a failure to satisfy the requirements of § 401(k)(3), 401(m)(2), or 401(m)(9), the correction period does not end until the last day of the second plan year following the plan year that includes the last day of the additional period for correction permitted under § 401(k)(8) or 401(m)(6). If a 403(b) Plan does not have a plan year, the plan year is deemed to be the calendar year for purposes of this subsection.
Correction Period. A. For a period of one (1) year from the date of Substantial Completion of the Work or a designated portion thereof, unless otherwise stated in Substantial Completion Notice(s) from OWNER, the Contractor shall remedy at the Contractor’s expense any failure to conform to the Contract requirements or any defect. B. The Contractor shall remedy at the Contractor’s expense any damage to real or personal property owned or controlled by the OWNER, when the damage is the result of: 1. Contractor’s failure to conform to Contract requirements; or 2. Any defect of equipment, material, workmanship, or design furnished. C. The Contractor shall restore any Work damaged in fulfilling the terms and conditions of this Article. The Contractor warranty with respect to work repaired or replaced shall run for one year from the date of repair or replacement. D. The OWNER shall notify the Contractor, in writing, within a reasonable time after the discovery of any failure, defect, or damage. E. If the Contractor fails to remedy any failure, defect, or damage within a reasonable time after receipt of notice, the OWNER shall have the right to replace, remove, or otherwise remedy the failure, defect, or damage at the Contractor’s expense.
Correction Period. If within one (1) year after the date of final acceptance or such longer period of time as may be prescribed by laws or regulations or by the terms of any applicable special warranty or guarantee required by the Contract or supplied with regard to the Work or required by any specific provision of the Contract, any Work is found to be defective, Contractor shall promptly, without cost to the County and in accordance with the County's written instructions, (i) correct such defective work or, if it has been rejected by the County, remove it from the Site and replace it with Work that is not defective, and (ii) satisfactorily correct or remove and replace any damage to other Work or the work of others resulting therefrom. If Contractor does not promptly comply with the terms of such instructions, or in an emergency where delay would cause serious risk of loss or damage, the County may have the defective work corrected or the rejected Work removed and replaced, and all claims, costs, losses and damages caused by or resulting therefrom (including but not limited to all costs of repair or replacement of work of others) shall be paid by Contractor. Where Contractor fails to correct defective Work, or defects are discovered outside the correction period, County shall have all the rights and remedies granted by law.
Correction Period. A. If within one year after the date of substantial completion, any Work is found to be defective, or if the repair of any damages to the Site, adjacent areas that Contractor has arranged to use through construction easements or otherwise, and other adjacent areas used by Contractor as permitted by Laws and Regulations, is found to be defective, then Contractor shall promptly and without cost to Owner, correct such defective Work.
Correction Period. The time after Substantial Completion during which a Contractor must correct, at no cost to Owner, any Defective Work, normally one year after the date of Substantial Completion or such longer period of time as may be prescribed by Laws or Regulations or by the terms of any applicable special guarantee or specific provision of the Contract Documents.
Correction Period. The Contractor at its own cost and expense will remedy all defects in workmanship and material which may be discovered within a period of one year after the final completion and acceptance of any Work assigned by the Engineer.
AutoNDA by SimpleDocs
Correction Period. A. For a period of one (1) year from the date of Substantial Completion of the Work or a designated portion thereof, unless otherwise stated in Substantial Completion Notice(s) from OWNER, the Contractor shall remedy at the Contractor’s expense any failure to conform to the Contract requirements or any defect. B. The Contractor shall remedy at the Contractor’s expense any damage to real or personal property owned or controlled by the OWNER, when the damage is the result of: 1. Contractor’s failure to conform to Contract requirements; or 2. Any defect of equipment, material, workmanship, or design furnished.
Correction Period. The time after Substantial Completion during which Contractor must correct, at no cost to PCCA, any Defective Work; normally one year after the date of Substantial Completion or such longer period of time as may be prescribed by Laws or Regulations or by the terms of any applicable special guarantee or specific provision of the Construction Contract Documents.
Correction Period. A. If within two (2) years after the date of Final Acceptance (or such longer period of time as may be prescribed by the terms of any applicable special guarantee required by the Contract Documents), any Work is found to be defective, or if the repair of any damages to the land or areas made available for Contractor’s use by City or permitted by Laws and Regulations as contemplated in Paragraph 6.10.A is found to be defective, Contractor shall promptly, without cost to City and in accordance with City’s written instructions: 1. repair such defective land or areas; or 2. correct such defective Work; or 3. if the defective Work has been rejected by City, remove it from the Project and replace it with Work that is not defective, and 4. satisfactorily correct or repair or remove and replace any damage to other Work, to the work of others or other land or areas resulting therefrom. B. If Contractor does not promptly comply with the terms of City’s written instructions, or in an emergency where delay would cause serious risk of loss or damage, City may have the defective Work corrected or repaired or may have the rejected Work removed and replaced. All claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or other dispute resolution costs) arising out of or relating to such correction or repair or such removal and replacement (including but not limited to all costs of repair or replacement of work of others) will be paid by Contractor. C. In special circumstances where a particular item of equipment is placed in continuous service before Final Acceptance of all the Work, the correction period for that item may start to run from an earlier date if so provided in the Contract Documents. D. Where defective Work (and damage to other Work resulting therefrom) has been corrected or removed and replaced under this Paragraph 13.07, the correction period hereunder with respect to such Work may be required to be extended for an additional period of one year after the end of the initial correction period. City shall provide 30 days written notice to Contractor should such additional warranty coverage be required. Contractor may dispute this requirement by filing a Contract Claim, pursuant to Paragraph 10.06. E. Contractor’s obligations under this Paragraph 13.07 are in addition to any other obligation or warranty. The provisions of this Paragraph 13.07 shall not be co...