Costs Not To Be Reimbursed. The Cost of the Work shall not include the following items: 1. Salaries and other compensation of Construction Contractor’s personnel stationed at Construction Contractor’s principal office or offices other than the Project site office. 2. Expenses of Construction Contractor’s principal office and offices other than the Project site office. 3. Discretionary bonuses, incentive compensation and other discretionary payments paid to anyone hired by Construction Contractor or paid to any subcontractor or supplier. 4. Overhead and general expenses, except as may be expressly included in Subsection 5.A. above. 5. Construction Contractor’s capital expenses, including interest on Construction Contractor’s capital employed for the Work. 6. Rental costs of machinery and equipment, except as specifically provided in Subsection 5.A.4.b. above. 7. Except as expressly provided in Subsection 5.A.5.h. above or otherwise expressly agreed to in writing by Owner, costs due to the fault or negligence of Construction Contractor, subcontractors, anyone directly or indirectly employed by any of them, or for whose acts any of them may be liable, including costs for the correction of damaged, defective, or nonconforming Work, disposal and replacement of materials and equipment incorrectly ordered or supplied, and repairing or remedying damage to property not otherwise included in the Work. 8. Any costs not specifically and expressly described in Subsection 5.A. above. 9. Costs which would cause the GMP to be exceeded (as the GMP may be adjusted pursuant to the terms herein for Change Order and Construction Change Directive).
Appears in 10 contracts
Samples: Construction Management Services Agreement, Construction Management Contract, Construction Management Contract
Costs Not To Be Reimbursed. The Cost of the Work shall not include the following items:
1. Salaries and other compensation of Construction Contractor’s personnel stationed at Construction Contractor’s principal office or offices other than the Project site office.
2. Expenses of Construction Contractor’s principal office and offices other than the Project site office.
3. Discretionary bonuses, incentive compensation and other discretionary payments paid to anyone hired by Construction Contractor or paid to any subcontractor or supplier.
4. Overhead and general expenses, except as may be expressly included in Subsection 5.A. above.
5. Construction Contractor’s capital expenses, including interest on Construction Contractor’s capital employed for the Work.
6. Rental costs of machinery and equipment, except as specifically provided in Subsection 5.A.4.b. above.
7. Except as expressly provided in Subsection 5.A.5.h. above or otherwise expressly agreed to in writing by Owner, costs due to the fault or negligence of Construction Contractor, subcontractors, anyone directly or indirectly employed by any of them, or for whose acts any of them may be liable, including costs for the correction of damaged, defective, or nonconforming Work, disposal and replacement of materials and equipment incorrectly ordered or supplied, and repairing or remedying making good damage to property not otherwise included in forming part of the Work.
8. Any costs not specifically and expressly described in Subsection 5.A. 5.A above.
9. Costs which would cause the GMP to be exceeded (as the GMP may be adjusted pursuant to the terms herein for Change Order and Construction Change Directive).
Appears in 2 contracts
Samples: Construction Management Contract, Construction Management Contract
Costs Not To Be Reimbursed. The Cost of the Work shall not include the following items:
1. Salaries and other compensation of Construction Contractor’s personnel stationed at Construction Contractor’s principal office or offices other than the Project site office.
2. Expenses of Construction Contractor’s principal office and offices other than the Project site office.
3. Discretionary bonuses, incentive compensation and other discretionary payments paid to anyone hired by Construction Contractor or paid to any subcontractor or supplier.
4. Overhead and general expenses, except as may be expressly included in Subsection 5.A. subsection A above.
5. Construction Contractor’s capital expenses, including interest on Construction Contractor’s capital employed for the Work.
6. Rental costs of machinery and equipment, except as specifically provided in Subsection 5.A.4.b. subsection A.4.b above.
7. Except as expressly provided in Subsection 5.A.5.hsubsection A.5.h. above or otherwise expressly agreed to in writing by Owner, costs due to the fault or negligence of Construction Contractor, subcontractors, anyone directly or indirectly employed by any of them, or for whose acts any of them may be liable, including costs for the correction of damaged, defective, or nonconforming Work, disposal and replacement of materials and equipment incorrectly ordered or supplied, and repairing or remedying making good damage to property not otherwise included in forming part of the Work.
8. Any costs not specifically and expressly described in Subsection 5.A. subsection A above.
9. Costs which would cause the GMP to be exceeded (as the GMP may be adjusted pursuant to the terms herein for Change Order and Construction Change Directive).
Appears in 2 contracts
Samples: Construction Management Contract, Construction Management Contract
Costs Not To Be Reimbursed. The Cost of the Work shall not include the following items:
1. Salaries and other compensation of Construction Contractor’s personnel stationed at Construction Contractor’s principal office or offices other than the Project site office.
2. Expenses of Construction Contractor’s principal office and offices other than the Project site office.
3. Discretionary bonuses, incentive compensation and other discretionary payments paid to anyone hired by Construction Contractor or paid to any subcontractor or supplier.
4. Overhead and general expenses, except as may be expressly included in Subsection 5.A. above.
5. Construction Contractor’s capital expenses, including interest on Construction Contractor’s capital employed for the Work.
6. Rental costs of machinery and equipment, except as specifically provided in Subsection 5.A.4.b. above.
7. Except as expressly provided in Subsection 5.A.5.h. above or otherwise expressly agreed to in writing by Owner, costs due to the fault or negligence of Construction Contractor, subcontractors, anyone directly or indirectly employed by any of them, or for whose acts any of them may be liable, including costs for the correction of damaged, defective, or nonconforming Work, disposal and replacement of materials and equipment incorrectly ordered or supplied, and repairing or remedying making good damage to property not otherwise included in forming part of the Work.
8. Any costs not specifically and expressly described in Subsection 5.A. above.
9. Costs which would cause the GMP to be exceeded (as the GMP may be adjusted pursuant to the terms herein for Change Order and Construction Change Directive).
Appears in 1 contract
Samples: Construction Management Contract