Common use of DAILY REPORTS BY CONTRACTOR Clause in Contracts

DAILY REPORTS BY CONTRACTOR. ‌ 3.14.1 At the end of each working day, Contractor shall submit a daily report to the Construction Manager (on a form provided by or accepted by the Construction Manager) listing: (i) Labor - Names of workers, classification, hourly rates and hours worked. (ii) Material - Description and list of quantities of materials used. (iii) Equipment - Type of equipment, size, identification number, and hours of operation, including loading and transportation, if applicable. (iv) Inspection and Testing Activities - Name, City or company and items involved. (v) Areas of Work - The areas of the Site on which Work was performed and a detailed description of the stage, status and progress of the Work in each such area at the beginning and end of the day. (vi) Accidents, Delays, Defective Work - Description in detail of any injuries to workers, accidents, Delays, or Defective Work that were encountered. (vii) Other Services and Expenditures - Description in such detail as City may require of other services and expenditures. 3.14.2 Reports by Subcontractors that comply with the requirements of this Section 3.14 shall also be submitted to the Construction Manager through Contractor at the end of each working day 3.14.3 Submission of daily reports by Contractor and Subcontractors performing Work on the Site shall be a condition precedent to Contractor's right to payment under the Contract. 3.14.4 Facts, notice or information contained in daily reports of Contractor or its Subcontractors, whether known or not known to City or Construction Manager, shall under no circumstances be considered evidence of compliance by Contractor with any of the specific written notice requirements of the Contract Documents.

Appears in 27 contracts

Samples: Construction Contract, Construction Contract, Construction Contract

AutoNDA by SimpleDocs

DAILY REPORTS BY CONTRACTOR. 3.14.1 At the end of each working day, Contractor shall submit a daily report to the Construction Manager (on a form provided by or accepted by the Construction Manager) listing: (i) Labor - Names of workers, classification, hourly rates and hours worked. (ii) Material - Description and list of quantities of materials used. (iii) Equipment - Type of equipment, size, identification number, and hours of operation, including loading and transportation, if applicable. (iv) Inspection and Testing Activities - Name, City or company and items involved. (v) Areas of Work - The areas of the Site on which Work was performed and a detailed description of the stage, status and progress of the Work in each such area at the beginning and end of the day. (vi) Accidents, Delays, Defective Work - Description in detail of any injuries to workers, accidents, Delays, or Defective Work that were encountered. (vii) Other Services and Expenditures - Description in such detail as City may require of other services and expenditures. 3.14.2 Reports by Subcontractors that comply with the requirements of this Section 3.14 shall also be submitted to the Construction Manager through Contractor at the end of each working day 3.14.3 Submission of daily reports by Contractor and Subcontractors performing Work on the Site shall be a condition precedent to Contractor's right to payment under the Contract. 3.14.4 Facts, notice or information contained in daily reports of Contractor or its Subcontractors, whether known or not known to City or Construction Manager, shall under no circumstances be considered evidence of compliance by Contractor with any of the specific written notice requirements of the Contract Documents.

Appears in 7 contracts

Samples: Construction Contract, Construction Contract, Construction Contract

AutoNDA by SimpleDocs
Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!